Item 7. Management’s Discussion and Analysis
ITEM 7.
MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS
Overview
Our water production operations and activities, and those of our affiliate OC-BVI, are conducted at 11 plants in three countries: the Cayman Islands, The Bahamas, and the British Virgin Islands. The following table sets forth the comparative combined production capacity of our retail and bulk segments and our affiliate as of December 31 of each year.
Comparative Operations
2020
2019
Location
Plants
Capacity (1)
Location
Plants
Capacity (1)
Cayman Islands
7
9.9
Cayman Islands
7
9.9
Bahamas (2)
2
14.8
Bahamas
3
14.9
British Virgin Islands
2
0.8
British Virgin Islands
2
0.8
Total
11
25.5
Total
12
25.6
(1) In millions of gallons per day.
(2) As of December 18, 2020, we ceased operations of our water production and supply business in South Bimini, The Bahamas.
Our water treatment and reuse facilities are conducted at 27 plants in the United States. The following table sets forth the comparative combined estimated production capacity of our services segment as of December 31 of each year.
Comparative Operations
2020
2019
Location
Plants
Capacity (1)
Location
Plants
Capacity (1)
USA
27
45.0
USA
21
20.3
Total
27
45.0
Total
21
20.3
(1) In estimated millions of gallons per day.
Cayman Islands
We have been operating our business on Grand Cayman since 1973 and have been using reverse osmosis technology to convert seawater to potable water since 1989. The Cayman Islands have a limited natural supply of fresh water. We have an exclusive license from the Cayman Islands government to process potable water from seawater and then sell and distribute that water by pipeline to the Seven Mile Beach and West Bay areas of Grand Cayman. This license expired in January 2018 but as discussed in the following paragraph we continue to provide water under the terms of this license. Our Grand Cayman operations consist of four company-owned seawater reverse osmosis desalination plants which provide water to approximately 6,900 retail residential and commercial customers within a government licensed area and three government-owned seawater reverse osmosis plants which supply bulk water to the WAC. Our pipeline system on Grand Cayman Island covers the Seven Mile Beach and West Bay areas of Grand Cayman and consists of approximately 100 miles of potable water pipe.
28
Table of Contents
Our exclusive license from the Cayman Islands government was originally scheduled to expire in July 2010 but was extended several times by the Cayman Islands government in order to provide the parties with additional time to negotiate the terms of a new license agreement. The most recent express extension of the license expired on January 31, 2018. We continue to operate under the terms of the 1990 license, providing water services to the level and quality specified in the 1990 license and in accordance with our understanding of its legal obligations, treating those obligations set forth in the 1990 license as operative notwithstanding the expiration of the express extension. We continue to pay the royalty required under the 1990 license. We have been informed during our retail license negotiations that the Cayman Islands government seeks to restructure the terms of our license in a manner that could significantly reduce the operating income and cash flows we have historically generated from our retail license. Our retail license negotiations have also been impacted by the passage of new legislation and the establishment of a new water regulatory body in the Cayman Islands. See further discussion of this matter at ITEM 7. MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS - Material Commitments, Expenditures and Contingencies - Cayman Water Retail License .
The Bahamas
CW-Bahamas produces potable water from two seawater reverse osmosis desalination plants. The Windsor plant and the Blue Hills plant are located in Nassau, New Providence and have a total installed capacity of 14.8 million gallons per day. CW-Bahamas supplies water from these plants to the Water and Sewerage Corporation of The Bahamas (“WSC”) under long-term supply agreements. During 2020, we supplied approximately 4.2 billion gallons (2019: 4.0 billion gallons) of water to the WSC from these plants.
From time to time (including presently), CW-Bahamas has experienced delays in collecting its accounts receivable. Representatives of the Bahamas government have informed us that their delays in paying our accounts receivables did/do not reflect any type of dispute with us with respect to the amounts owed. To date, we have not been required to provide an allowance for any delinquent CW-Bahamas accounts receivable as such amounts were eventually paid in full. Based upon our experience, we believe that the present accounts receivable from the WSC are fully collectible and therefore have not provided any allowance for possible non-payment of these receivables. Such accounts receivable balances due from The Bahamas government amounted to $16.8 million and $18.4 million as of December 31, 2020 and 2019, respectively. See further discussion of this matter at ITEM 7. MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS - LIQUIDITY AND CAPITAL RESOURCES - CW Bahamas Liquidity.
Critical Accounting Estimates
The preparation of consolidated financial statements in conformity with accounting principles generally accepted in the United States of America requires us to make estimates and assumptions that affect the reported amounts of assets and liabilities and disclosure of contingent assets and liabilities at the date of the consolidated financial statements and the reported amounts of revenue and expenses during the reporting period. Our actual results could differ significantly from such estimates and assumptions.
Certain of our accounting estimates or assumptions constitute “critical accounting estimates” for us because:
● the nature of these estimates or assumptions is material due to the levels of subjectivity and judgment necessary to account for highly uncertain matters or the susceptibility of such matters to change; and
● the impact of the estimates and assumptions on financial condition and results of operations is material.
Our critical accounting estimates relate to the valuations of our (i) goodwill and intangible assets; and (ii) long-lived assets.
Goodwill and intangible assets
Goodwill represents the excess cost over the fair value of the assets of an acquired business. Goodwill and intangible assets acquired in a business combination accounted for as a purchase and determined to have an indefinite useful life are not
29
Table of Contents
amortized but are tested for impairment at least annually. Intangible assets with estimable useful lives are amortized over their respective estimated useful lives to their estimated residual values and reviewed periodically for impairment. We evaluate the possible impairment of goodwill annually as part of our reporting process for the fourth quarter of each fiscal year. Management identifies our reporting units, which consist of our retail, bulk, services and manufacturing operations, and determines the carrying value of each reporting unit by assigning the assets and liabilities, including the existing goodwill and intangible assets, to those reporting units. We determine the fair value of each reporting unit and compare these fair values to the carrying amounts of the reporting units. To the extent the carrying amount of the reporting unit exceeds the fair value of the reporting unit, an impairment loss is recorded.
For the years ended December 31, 2020 and 2019, we estimated the fair value of our reporting units by applying the discounted cash flow method, which relied upon seven-year discrete projections of operating results, working capital and capital expenditures, along with a terminal value subsequent to the discrete period. These seven-year projections were based upon historical and anticipated future results, general economic and market conditions, and considered the impact of planned business and operational strategies. The discount rates for the calculations represented the estimated cost of capital for market participants at the time of each analysis.
We also estimated the fair value of each of our reporting units for the years ended December 31, 2020 and 2019 by applying the guideline public company method. We also estimated the fair value of each of our reporting units for the year ended December 31, 2019 by referencing the market multiples implied by guideline merger and acquisition transactions (the mergers and acquisition method). We considered utilizing the mergers and acquisition method for the year ended December 31, 2020 but due to a lack of relevant meaningful mergers and acquisition activity during the year, such method was not utilized for 2020.
We weighted the fair values estimated for each of our reporting units under each method and summed such weighted fair values to estimate the overall fair value for each reporting unit. The respective weightings we applied to each method for the years ended December 31, 2020 and 2019 were as follows:
As of December 31, 2020
Method
Retail
Bulk
Services
Manufacturing
Discounted cash flow
80
%
80
%
80
%
80
%
Guideline public company
20
%
20
%
20
%
20
%
Mergers and acquisitions
—
%
—
%
—
%
—
%
100
%
100
%
100
%
100
%
As of December 31, 2019
Method
Retail
Bulk
Manufacturing
Discounted cash flow
80
%
80
%
80
%
Guideline public company
10
%
10
%
10
%
Mergers and acquisitions
10
%
10
%
10
%
100
%
100
%
100
%
The fair values we estimated for our retail, bulk, services and manufacturing reporting units exceeded their carrying amounts by 101%, 49%, 17% and 31%, respectively, as of December 31, 2020. The fair values we estimated for our retail and bulk reporting units exceeded their carrying amounts by 74% and 58%, respectively, as of December 31, 2019. The assets and liabilities for our services reporting unit consist almost entirely of those for PERC, which was acquired at fair value on October 24, 2019, and therefore we estimate the fair value of our services reporting unit closely approximated its carrying value at December 31, 2019. Our manufacturing reporting unit consists entirely of Aerex and the remaining 49% ownership interest of Aerex was purchased on January 24, 2020 for $8,500,000. We considered this purchase, the manufacturing reporting unit’s results of operations for the year ended December 31, 2019, the manufacturing reporting unit’s projected results of operations for the year ended December 31, 2020, and the amount by which the estimated fair value of the manufacturing reporting unit exceeded its carrying amount as of December 31, 2018 to determine that it is more likely than not that the fair value of our manufacturing reporting unit exceeded its carrying amount as of December 31, 2019.
30
Table of Contents
In February 2016, we acquired a 51% ownership interest in Aerex. In connection with this acquisition, we recorded goodwill of $8,035,211. Aerex’s actual results of operations for the six months in 2016 following the acquisition fell significantly short of the projected results that were included in the cash flow projections we utilized to determine the purchase price for Aerex and the fair values of its assets and liabilities. Due to this shortfall in Aerex’s results of operations, we tested Aerex’s goodwill for possible impairment as of September 30, 2016 by estimating its fair value using the discounted cash flow method. As a result of this impairment testing, we determined that the carrying value of our Aerex goodwill exceeded its fair value and recorded an impairment loss of $1,750,000 for the three months ended September 30, 2016 to reduce the carrying value of this goodwill to $6,285,211. As part of our annual impairment testing of goodwill performed during the fourth quarter, in 2017 we updated our projections for Aerex’s future cash flows, determined that the carrying value of our Aerex goodwill exceeded its fair value, and recorded an impairment loss of $1,400,000 for the three months ended December 31, 2017 to further reduce the carrying value of this goodwill to $4,885,211.
Approximately 80% and 68% of Aerex’s revenue, and 89% and 68% of Aerex’s gross profit, for the years ended December 31, 2020 and 2019, respectively, were generated from sales to one customer. In October 2020, this customer verbally informed Aerex that, for inventory management purposes, it was suspending its purchases from Aerex following 2020 for a period of approximately one year. This customer has verbally informed Aerex that it presently expects to recommence its purchases from Aerex beginning with the first quarter of 2022. However, we can offer no assurances that this customer will recommence its purchases from Aerex at that time. Furthermore, any such future purchases (should they occur) may not generate as much revenue and gross profit as Aerex has historically earned from this customer. We are seeking to replace the anticipated loss in revenue and gross profit from this customer by increasing sales of other products that we manufacture to new and existing customers, however, we may not be able to do so.
As a result of this anticipated loss of revenue for Aerex, we updated our projections for our manufacturing reporting unit’s future cash flows. Such projections assume, in part, that Aerex’s major customer will recommence its purchases from Aerex in 2022 but at a reduced aggregate amount, as compared to 2020 and 2019. Based upon these updated projections, we tested our manufacturing reporting unit’s goodwill for possible impairment as of December 31, 2020. As a result of this impairment testing, we determined that the estimated fair value of our manufacturing reporting unit exceeded its carrying value as of December 31, 2020. However, we may be required to record an impairment loss in the future to reduce the carrying value of our manufacturing reporting unit’s goodwill should we determine that Aerex’s future net cash inflows will be less than our most current expectations. Any such impairment loss could have a material adverse impact on our consolidated financial condition and results of operations.
In February 2019, we sold CW-Belize. As a result of this sale, CW-Belize has been accounted for as discontinued operations in our consolidated financial statements, and bulk segment goodwill of approximately $380,000 as of December 31, 2018 associated with CW-Belize was reclassified to long-term assets of discontinued operations in our consolidated statements of financial condition.
Long-lived assets
We review the carrying amounts of our long-lived assets for impairment whenever events or changes in circumstances indicate that the carrying amount of the assets might not be recoverable. Conditions that would necessitate an impairment assessment include a significant decline in the observable market value of an asset, a significant change in the extent or manner in which an asset is used, or a significant adverse change that would indicate that the carrying amount of an asset or group of assets is not recoverable. For long-lived assets to be held and used, we recognize an impairment loss only if its carrying amount is not recoverable through its undiscounted cash flows and measure the impairment loss based on the difference between the carrying amount and fair value.
On June 29, 2020, our Mexico subsidiary, AdR, received a letter from the State of Baja California (the “State”) terminating AdR’s contract with the State involving the construction and operation of a desalination plant in Rosarito California and accompanying aqueduct to deliver the water produced by this plant to the Mexican public water system. As a result of the cancellation of this contract, we recorded an impairment loss for rights of way acquired for the contract’s proposed aqueduct of $(3.0 million) for the three months ended June 30, 2020, which is reflected in our loss from discontinued operations for the year ended December 31, 2020.
31
Table of Contents
Through our former subsidiary, PT Consolidated Water Bali (“CW-Bali”), we built and operated a seawater reverse osmosis plant with a productive capacity of approximately 264,000 gallons per day located in Nusa Dua, one of the primary tourist areas of Bali, Indonesia. We recorded operating losses for CW-Bali as the sales volumes for its plant were insufficient to cover its operating costs. In 2017 and 2016 we determined, based upon probability-weighted scenarios for CW-Bali’s future undiscounted cash flows, that the carrying values of CW-Bali’s long-lived assets and our investment in CW-Bali were not recoverable. Consequently, we recorded impairment losses of $(1.6 million) and $(2.0 million), in 2017 and 2016, respectively, to reduce the carrying values of these assets to their fair values.
Results of Operations
The following discussion and analysis of our results of operations should be read in conjunction with our audited consolidated financial statements and accompanying notes included under Part II, ITEM 8. FINANCIAL STATEMENTS AND SUPPLEMENTARY DATA, of this Annual Report.
Year Ended December 31, 2020 Compared to Year Ended December 31, 2019
Discontinued Operations – Mexico Project Development
In 2010, we began the pursuit, through our Netherlands subsidiary, Consolidated Water Cooperatief, U.A. (“CW-Cooperatief”), and our Mexico subsidiary, N.S.C. Agua, S.A. de C.V. (“NSC”), of a project (the “Project”) that originally encompassed the construction, operation and minority ownership of a 100 million gallon per day seawater reverse osmosis desalination plant to be located in northern Baja California, Mexico and accompanying pipelines to deliver water to the Mexican potable water system.
Through a series of transactions that began in 2012, NSC purchased 20.1 hectares of land for approximately $21.1 million on which the proposed Project’s plant was to be constructed.
In November 2015, the State officially commenced the required public tender for the Project, the scope of which the State defined as a first phase to be operational in 2019 consisting of a 50 million gallon per day plant and an aqueduct that connects to the Mexican potable water infrastructure and a second phase to be operational in 2024 consisting of an additional 50 million gallons per day of production capacity. A consortium (the “Consortium”) comprised of NSC, Suez Medio Ambiente México, S.A. de C.V. (“Suez MA”), a subsidiary of SUEZ International, S.A.S., and NuWater S.A.P.I. de C.V. (“Nuwater”) submitted its tender for the Project in April 2016 and in June 2016, the State designated the Consortium as the winner of the tender process for the Project.
In August 2016, NSC and NuWater incorporated Newco under the name Aguas de Rosarito S.A.P.I. de C.V. (“AdR”) to pursue completion of the Project and executed a shareholders agreement for AdR agreeing among other things that (i) AdR would purchase the land and other Project assets from NSC on the date that the Project begins commercial operation and (ii) AdR would enter into a Management and Technical Services Agreement with NSC effective on the first day that the Project begins commercial operation. NSC initially owned 99.6% of the equity of AdR. In February 2018, we acquired the remaining 0.4% ownership in AdR from NuWater.
On August 22, 2016, the Public Private Partnership Agreement for the Project (the “APP Contract”) was executed between AdR, the Comisión Estatal del Agua de Baja California (“CEA”), the Government of Baja California as represented by the Secretary of Planning and Finance and the Public Utilities Commission of Tijuana (“CESPT”). The APP Contract required AdR to design, construct, finance and operate a seawater reverse osmosis desalination plant (and accompanying aqueduct) with a capacity of up to 100 million gallons per day in two phases: the first with a capacity of 50 million gallons per day and an aqueduct to the Mexican potable water system in Tijuana, Baja California and the second phase with a capacity of 50 million gallons per day. The first phase was to be operational within 36 months of commencing construction and the second phase was to be operational by July 2024. The APP Contract further required AdR to operate and maintain the plant and aqueduct for a period of 37 years starting from the commencement of operation of the first phase. At the end of the operating period, ownership of the plant and aqueduct would have been transferred to CEA.
Both the exchange rate for the Mexican peso relative to the dollar and general macroeconomic conditions in Mexico varied since the execution of the APP Contract. These changes adversely impacted the estimated construction, operating and
32
Table of Contents
financing costs for the Project. The APP Contract and the APP Law allow for the parties to negotiate (but do not guarantee) modifications to the consideration (i.e. water tariff) under the APP Contract in the event of such significant macroeconomic
condition changes. In February 2017, AdR submitted proposals to CEA requesting the definition of the mechanism required by the APP Contract to update the consideration under the APP Contract for changes in foreign exchange rates, lending rates and certain laws which have impacted the Project. On June 1, 2018, AdR and CEA executed an amendment to the APP Contract which, among other things, increased the scope of Phase 1 of the Project by including the aqueduct originally designated for Phase 2, and addressed AdR’s concerns regarding the impact on the Project for changes in the exchange rate for the peso relative to the dollar and changes in interest rates that have occurred subsequent to the submission of the Consortium’s bid for the Project. As a result of this amendment to the APP Contract, the final cost of Phase 1 and the related consideration to be charged by AdR under the APP Contract was to be determined based upon the bid submitted by the Consortium, the changes set forth in the amendment to the APP Contract and the economic conditions (e.g. interest rates and currency exchange rates) in effect on the financial closing date for Phase 1.
In February 2018, AdR executed a subscription agreement (the “Subscription Agreement”) for the equity funding required for the Project. The Subscription Agreement called for NSC to retain a minimum of 25% of the equity in AdR. One or more affiliates of Greenfield SPV VII, S.A.P.I. de C.V. (“Greenfield”), a Mexico company managed by an affiliate of a leading U.S. asset manager, would acquire a minimum of 55% of the equity of AdR. The Subscription Agreement also provided Suez MA with the option to purchase 20% of the equity of AdR. If Suez MA did not exercise this option, NSC would retain 35% of the equity of AdR and Greenfield will acquire 65% of the equity of AdR. The Subscription Agreement became effective when the additional conditions precedent related to the Project were met. The aggregate funding to be provided by AdR’s shareholders for the Project, in the form of equity and subordinated shareholder loans, was estimated at approximately 20% of the total cost of Phase 1 of the Project. This Subscription Agreement was scheduled to expire on September 30, 2020. NSC expected to generate a portion of its additional future equity investment in AdR through the sale to AdR of the land it had purchased for the Project.
On June 29, 2020, AdR received a letter (the “Letter”) from the Director General of CEA and the Director General of CESPT terminating the APP Contract. The reasoning provided in the Letter for the decision to terminate the APP Contract is that the Project (a) is not financially feasible due to increases in the construction, operating and financing costs for the Project in addition to negative changes in economic conditions (e.g. interest rates and currency exchange rates); (b) is not sustainable for CEA and CESPT given its financial unfeasibility; (c) puts pressure to increase the rates charged to customers; (d) would force the Government of the State to cover a deficit of CEA and CESPT, thus preventing the State Government from spending on investment programs or social expenditures; and (e) negatively affects the general interest. The Letter requested that AdR provide an inventory of the assets that currently comprise the “Project Works” (as defined in the APP Contract) for the purpose of acknowledging and paying the non-recoverable expenses made by AdR in connection with the Project, with such reimbursement to be calculated in accordance with the terms of the APP Contract. The applicable law requires this list of non-recoverable expenses made by AdR in connection with the Project be submitted to CEA and CESPT within 20 business days from the date of receipt of the Letter. AdR initiated an amparo claim before a federal district court in Tijuana, Baja California, to challenge the provision of the applicable law requiring submittal of the list of non-recoverable expenses within the 20 business days term, as AdR considered such term to be unreasonably short due to the magnitude of the Project and the scope of supporting documentation required to be provided with respect to the non-recoverable expenses. AdR obtained an initial provisional suspension of the lapsing of such 20 day term from the court, and on August 10, 2020 the court made such suspension definitive until the completion of the amparo trial. As such, the 20 day term for filing the list of non-recoverable expenses was suspended. Therefore, on August 28, 2020, AdR submitted their list of non-recoverable expenses, including those of NSC, to CEA and CESPT which was comprised of 51,144,525 United States dollars and an additional 137,333,114 Mexican pesos. In February 2021, AdR withdrew this claim which was accepted by the federal district court in Tijuana.
We plan to vigorously pursue all legal remedies and courses of action available under the APP Contract and applicable law (including international treaties and agreements) with respect to any rights we may have upon termination of the APP Contract, including the reimbursement of expenses and investments. However, we cannot provide any assurances that we will be able to obtain reimbursement for any expenses or investments made with respect to the Project.
As a result of the cancellation of the APP Contract, during the three months ended September 30, 2020, we discontinued all development activities associated with the Project and commenced active marketing efforts to sell the land NSC
33
Table of Contents
purchased for the Project. Accordingly, the assets and liabilities of CW-Cooperatief, NSC and AdR, as well as all Project development expenses and the impairment loss these subsidiaries incurred, have been reclassified from the services segment to discontinued operations in the accompanying consolidated financial statements as of and for the years ended December 31, 2020 and 2019. Our net losses from discontinued operations for the years ended December 31, 2020 and 2019 of $(4,902,243) and $(2,333,255), respectively, consist of legal, accounting, engineering, administrative, consulting and other costs relating to Project development activities and, for 2020, our activities following the cancellation of the APP Contract to pursue reimbursement from the State.
Consolidated Results
Including discontinued operations, net income attributable to Consolidated Water Co. Ltd. stockholders for 2020 was $3,711,528 ($0.24 per share on a fully diluted basis), as compared to $12,176,093 ($0.80 per share on a fully diluted basis) for 2019.
The following discussion and analysis of our consolidated results of operations and our results by segment refers only to our continuing operations.
Net income from continuing operations attributable to Consolidated Water Co. Ltd. stockholders for 2020 was $8,613,771 ($0.56 per share on a fully diluted basis), as compared to $10,888,178 ($0.72 per share on a fully diluted basis) for 2019 .
Total revenue for 2020 increased to $72,628,126 from $68,793,651 in 2019, primarily as a result of the addition of PERC’s revenue to our services segment. Gross profit for 2020 was $26,768,455 (37% of total revenue) as compared to $28,274,348 (41% of total revenue) for 2019. For further discussion of revenue and gross profit see the “Results by Segment” discussion and analysis that follows.
General and administrative expenses (“G&A expenses”) on a consolidated basis increased to $18,434,898 for 2020 as compared to $17,001,164 for 2019 due to the addition in 2020 of PERC’s G&A expenses of approximately $2.8 million, which includes approximately $564,000 of amortization expense for certain intangible assets recorded in connection with the acquisition of PERC. Serving to partially offset the incremental PERC expenses was a decrease of approximately $536,000 in business development expenses and a decrease of approximately $514,000 in amortization expense resulting from the completion of the amortization period for certain intangible assets recorded in connection with the acquisition of Aerex.
In June 2019, we completed the sales of our CW-Bali assets and its stock for $365,000 and $25,000, respectively. Such sales constitute most of the $445,041 gain on asset dispositions for 2019.
Other income, net, increased to $1,082,946 in 2020, as compared to $786,552 in 2019. This increase is primarily attributable to the income generated from our investment in the profit-sharing plan of OC-BVI and our equity in the earnings of OC-BVI, which in the aggregate were approximately $446,000 higher in 2020 than in 2019 as a result of the receipt by OC-BVI in 2020 of approximately $815,648 in delinquent interest income.
Results by Segment
Retail Segment:
The retail segment incurred a net loss from operations of $(1,004,924) for 2020. The retail segment contributed $1,820,077 to our income from operations for 2019.
Revenue generated by our retail water operations decreased to $22,952,370 in 2020 from $26,456,022 in 2019. The reduction in revenue reflects a 13% decrease in the volume of water sold by Cayman Water due to the closing of Grand Cayman Island to all tourist travel in March 2020 in response to the COVID-19 pandemic and lower energy prices in 2020 than in 2019, which decreased the energy pass-through component of our Cayman Water retail revenue by approximately $861,000.
34
Table of Contents
Retail segment gross profit decreased to $11,871,556 (52% of retail revenue) for 2020 as compared to $14,844,857 (56% of retail revenue) for 2019 principally as a result of the drop in revenue.
Consistent with prior periods, we record all non-direct G&A expenses in our retail segment and do not allocate any of these non-direct costs to our other three business segments. Retail G&A expenses decreased to $12,879,445 for 2020 as compared to $13,422,821 for 2019 primarily as a result of a decrease in business development expenses of approximately $536,000.
Bulk Segment:
The bulk segment contributed $6,100,134 and $7,188,007 to our income from operations for 2020 and 2019, respectively.
Bulk segment revenue was $24,312,546 and $26,986,108 for 2020 and 2019, respectively. The decrease in bulk segment revenue from 2019 to 2020 is attributable to both OC-Cayman and CW-Bahamas. OC-Cayman experienced a decline in revenue of approximately $1,213,000 as a result of the two new contracts at lower rates with the WAC for water supplied from (1) the Red Gate and North Sound plants which commenced in February 2019 and expires in 2024 and (2) the North Side Water Works plant, which commenced in July 2019 and expires in 2026. CW-Bahamas experienced a decline in revenue of approximately $1.5 million due to lower energy costs, which correspondingly decreased the energy pass-through component of CW-Bahamas’ rates.
Gross profit for the bulk segment was $7,352,983 (30% of bulk segment revenue) and $8,379,303 (31% of bulk segment revenue) for 2020 and 2019, respectively. Gross profit decreased in 2020 as compared to 2019 due to repairs and maintenance for CW-Bahamas for 2020 that exceeded those incurred in 2019 and lower margins earned by OC-Cayman on its new contracts (as compared to its previous contracts) with the WAC.
Bulk segment G&A expenses remained relatively consistent at $1,260,062 for 2020 as compared to $1,238,296 for 2019.
Services Segment:
The services segment contributed $408,529 and $151,828 to our income from operations for 2020 and 2019, respectively.
Services segment revenue increased to $12,937,859 for 2020 from $1,759,446 for 2019 due to the addition of $11,116,383 in revenue from PERC as a result of our acquisition of a controlling interest in this company in late October 2019.
The gross profit for the services segment increased to $3,239,645 (25% of services segment revenue) for 2020 from $544,253 (31% of services segment revenue) for 2019 as a result of the addition of PERC.
G&A expenses for the services segment increased to $2,834,917 for 2020 as compared to $392,425 for 2019 due to the addition of PERC.
Manufacturing Segment:
The manufacturing segment contributed $2,843,815 and $2,558,313 to our income from operations for 2020 and 2019, respectively.
Manufacturing segment revenue was $12,425,351 and $13,592,075 for 2020 and 2019, respectively. Manufacturing segment revenue decreased from 2019 to 2020 due to a decrease in orders in the fourth quarter of 2020.
Manufacturing segment gross profit was $4,304,271 (35% of manufacturing segment revenue) and $4,505,935 (33% of manufacturing segment revenue) for 2020 and 2019, respectively. The increase in manufacturing segment gross profit as a percentage of revenue stems from a mix of higher margin projects, coupled with overall higher production activity that led to improved plant efficiency.
35
Table of Contents
G&A expenses for the manufacturing segment dropped to $1,460,474 for 2020 as compared to $1,947,622 for 2019 as a result of a decrease of approximately $514,000 in the amortization expenses resulting from the completion of the amortization period for certain intangible assets recorded in connection with the acquisition of Aerex.
Approximately 80% and 68% of our manufacturing segment revenue, and 89% and 68% of our manufacturing segment gross profit, for 2020 and 2019, respectively, were generated from sales to one customer. In October 2020, this customer verbally informed Aerex that, for inventory management purposes, it was suspending its purchases from Aerex following 2020 for a period of approximately one year. This customer has verbally informed Aerex that it presently expects to recommence its purchases from Aerex beginning with the first quarter of 2022. However, we can offer no assurances that this customer will recommence its purchases from Aerex at that time. Furthermore, any such future purchases (should they occur) may not generate as much revenue and gross profit as Aerex has historically earned from this customer. We are seeking to replace this anticipated loss in revenue and gross profit by increasing sales of other products that we manufacture to new and existing customers, however, we may not be able to do so. Consequently, our manufacturing segment revenue and gross profit for 2021 may decline as compared to the two prior years.
FINANCIAL CONDITION
The significant changes in the components of our consolidated balance sheet as of December 31, 2020 as compared to December 31, 2019 (other than the change in our cash and cash equivalents, which is discussed later in “LIQUIDITY AND CAPITAL RESOURCES”) and the reasons for these changes are discussed in the following paragraphs.
Accounts receivable decreased by approximately $1.5 million. This net decrease reflects a decrease in CW-Bahamas’ accounts receivable of approximately $1.6 million from the WSC and a decrease of $450,000 of retail accounts receivable due to lower water sales in Cayman Islands. The decreases were offset by an increase of approximately $414,000 in accounts receivable arising from the addition of PERC.
Prepaid expenses and other current assets increased by approximately $853,000 primarily due to the prepayment of taxes of approximately $441,000, new lease assets of approximately $65,000 as well as additional prepaid insurance of approximately $55,000.
Contract assets decreased by approximately $1.2 million due to the completion of a major project by Aerex.
Construction in progress decreased by approximately $895,000 primarily due to the completion of the renovation of the North Side Water Works plant on Grand Cayman.
LIQUIDITY AND CAPITAL RESOURCES
Liquidity Position
Our projected liquidity requirements for 2021 include capital expenditures for our existing operations of approximately $6.3 million, which includes $4.0 million for the replacement of the 26 year old West Bay seawater desalination plant in Grand Cayman and approximately $1.3 million for dividends payable. Our liquidity requirements may also include future quarterly dividends, if such dividends are declared by our Board. Our dividend payments amounted to approximately $5.1 million for the years ended December 31, 2020 and 2019.
As of December 31, 2020, we had cash and cash equivalents of $43.8 million and working capital of $66.0 million.
With the exception of the liquidity matter relating to CW-Bahamas that is discussed in the paragraphs that follow, we are not presently aware of anything that would lead us to believe that we will not have sufficient liquidity to meet our needs.
CW-Bahamas Liquidity
CW-Bahamas’ accounts receivable balances (which include accrued interest) due from the WSC amounted to $16.8 million and $18.4 million as of December 31, 2020 and 2019, respectively. Approximately 76% of the December 31, 2020
36
Table of Contents
accounts receivable balance was delinquent as of that date. The delay in collecting these accounts receivable has adversely impacted the liquidity of this subsidiary.
From time to time (including presently), CW-Bahamas has experienced delays in collecting its accounts receivable from the WSC. When these delays occur, we hold discussions and meetings with representatives of the WSC and The Bahamas government, and as a result, payment schedules are developed for WSC’s delinquent accounts receivable. All previous delinquent accounts receivable from the WSC, including accrued interest thereon, were eventually paid in full. Based upon this payment history, CW-Bahamas has never been required to provide an allowance for doubtful accounts for any of its accounts receivable, despite the periodic accumulation of significant delinquent balances. As of December 31, 2020, we have not provided an allowance for doubtful accounts for CW-Bahamas’ accounts receivable from the WSC.
We believe the delays we have experienced in collecting CW-Bahamas’ receivables were extended due to the impact of Hurricane Dorian, which devastated the northern Bahamas in September 2019 and the severe economic impact of the COVID-19 pandemic on The Bahamas government’s revenue sources .
As of February 28, 2021, CW-Bahamas’ accounts receivable from the WSC totaled $19.6 million.
If CW-Bahamas continues to be unable to collect a significant portion of its delinquent accounts receivable, one or more of the following events may occur: (i) CW-Bahamas may not have sufficient liquidity to meet its obligations; (ii) we may be required to cease the recognition of revenue on CW-Bahamas’ water supply agreements with the WSC; and (iii) we may be required to provide an allowance for doubtful accounts for CW-Bahamas’ accounts receivable. Any of these events could have a material adverse impact on our consolidated financial condition, results of operations, and cash flows .
Discussion of Cash Flows for the Year Ended December 31, 2020
Our cash and cash equivalents increased to $43,794,150 as of December 31, 2020 from $42,071,083 as of December 31, 2019.
Cash Flows from Operating Activities
Our operating activities from continuing operations provided cash of $18,970,938. This net cash provided reflects net income generated for the year ended December 31, 2020 from continuing and discontinued operations of $4,441,533 as adjusted for (i) various items included in the determination of net income that do not affect cash flows during the year; and (ii) changes in the other components of working capital. The more significant of such items and changes in working capital components included depreciation and amortization of $7,406,509, a loss from discontinued operations of $(4,902,243), and a decrease in accounts receivable and contract assets of $2,541,096.
Cash Flows from Investing Activities
Net cash used by our investing activities was $11,119,755. In January 2020, we acquired the remaining 49% ownership in Aerex for $8,500,000 in cash. In August 2020, we acquired an additional 10% of PERC for $900,000. Additions to property, plant and equipment and construction in progress used $1,728,393 in cash.
Cash Flows from Financing Activities
Net cash used by our financing activities was $5,169,926, almost all of which related to the payment of dividends.
Material Commitments, Expenditures and Contingencies
COVID-19
The worldwide coronavirus (COVID-19) pandemic, which was formally recognized by the World Health Organization on March 11, 2020, has had a profound negative impact on the economies of the countries in which we operate. Consequently,
37
Table of Contents
the COVID-19 pandemic has had, and will continue to have, a material adverse impact on our consolidated financial condition, results of operations, and cash flows.
A discussion of the current effects of the COVID-19 pandemic on each of our operating subsidiaries is provided in the following paragraphs. However, as the worldwide impact of COVID-19 continues to develop and expand, its future effects on our company could differ materially from the information we are providing herein.
Cayman Water
As preventative measures to combat the possible spread of COVID-19, the Cabinet of the Cayman Islands (“the Cabinet”) closed all Cayman Islands sea ports to international passenger arrivals effective March 13, 2020; and closed all Cayman Islands airports to international passenger arrivals effective March 22, 2020. Effective March 28, 2020, the Cabinet and Cayman Islands law enforcement enacted various ‘stay-at-home’ regulations and curfews, which closed all businesses not deemed essential by the government and required citizens to stay at home unless they were purchasing necessities or engaged in an essential errand. In May 2020, the Cabinet started the phased relaxation of the shelter-in-place regulations and on October 1, 2020, the Cayman Islands reopened its borders for residents or individuals who own property in the Cayman Islands that provide evidence of a negative COVID-19 test performed within three days prior to arrival in the Cayman Islands and agree to remain in quarantine for 14 days after arrival. No date has yet been set for the planned reopening of the Cayman Islands to tourists.
As a result of these measures taken by the Cayman Islands government, tourism in the Cayman Islands has temporarily ceased. The preventative measures taken by the Cayman Islands government in response to the COVID-19 pandemic commenced in the latter half of March 2020 and thus affected our retail sales volumes for the last nine months of the year ended December 31, 2020. Consequently, our retail sales volume for the year ended December 31, 2020 declined by approximately 13% from the year ended December 31, 2019. However, the retail sales volume for the three months ended December 31, 2020 was approximately 28% less than that for the three months ended December 31, 2019. We expect that our retail segment revenue and cash flows will continue to be materially adversely impacted until such time as tourism and the economy in the Cayman Islands fully recover from the impact and effects of the COVID-19 pandemic.
Cayman Water’s operations have been designated as essential services by the Cayman Islands government. Presently, the day-to-day operations of Cayman Water’s water production facilities and distribution network have not been materially impeded by the COVID-19 pandemic – we continue to produce and supply water to meet the demand for water in our retail license area. We believe Cayman Water has adequate spare parts and supplies in stock to continue normal operations.
OC-Cayman
Although it operates on Grand Cayman - and therefore is also affected by the preventative measures enacted by government that have been discussed previously - OC-Cayman sells water on a bulk basis to the WAC, which in turn provides this water to areas of Grand Cayman that are more residential, and less tourist related, than the license area served by Cayman Water. The monthly amounts OC-Cayman charges the WAC for water supplied under its water supply agreements consist of fixed amounts that constitute the majority of the amounts charged, and lesser amounts that vary with the volume of water supplied. Therefore, unlike Cayman Water, OC-Cayman’s revenue is not as directly affected by tourism on Grand Cayman and, due to the structure of the underlying water supply agreements, is not as acutely sensitive to declines in water demand.
The amount of water provided by OC-Cayman to the WAC for the year ended December 31, 2020 was approximately 1% less than that provided for the year ended December 31, 2019. We cannot presently determine to what extent OC-Cayman’s future revenue will be impacted by the COVID-19 pandemic.
OC-Cayman’s operations have been designated as essential services by the Cayman Islands government. Presently, OC-Cayman’s day-to-day operations have not been materially impeded by the COVID-19 pandemic – we continue to produce and supply water to meet the requirements of our two water supply agreements with the WAC. We believe OC-Cayman has adequate spare parts and supplies in stock to continue normal operations.
CW-Bahamas
38
Table of Contents
The government of The Bahamas enacted Emergency Powers Regulations which became effective March 18, 2020 in an effort to combat the spread of COVID-19. These regulations closed all businesses not deemed essential by the government, encouraged the employees of non-essential businesses to work remotely and imposed 24 hour shelter-in-place curfew on all residents of The Bahamas other than those engaged in essential or pre-approved activities. On March 24, 2020, the government banned all international travel to The Bahamas by closing all airports and seaports. As a result of the measures taken by The Bahamas government, tourism on New Providence Island, where CW-Bahamas operates, temporarily ceased and economic activity in The Bahamas slowed dramatically. In May 2020, the Bahamian government relaxed some of the shelter-in-place regulations and in July 2020, the government of The Bahamas enacted a limited reopening of The Bahamas to air travel. However, increased travel restrictions were reimposed shortly thereafter due to an increase in COVID-19 cases. As of November 2020, shelter-in-place regulations were loosened and commercial and retail operations were permitted to open with limited capacity; additional economic activity (including the operation of restaurants and bars with outdoor and limited indoor seating) has since been permitted. Conditions for travel to The Bahamas have also been loosened and individuals that wish to travel to The Bahamas must obtain a health travel visa which will be issued upon receipt of a negative RTPCR COVID-19 test five days in advance of travel; they must submit to a mandatory COVID-19 rapid antigen test five days after arrival in The Bahamas or upon exhibiting symptoms of COVID-19 while in The Bahamas. As of March 2021, it is anticipated that a limited number of cruise ship departures from the Port of Nassau may commence in June 2021, but a date for cruise ship arrivals has not yet been set.
CW-Bahamas sells the water produced by its plants on a bulk basis to the WSC, which in turn provides water to the residences, businesses, and other end users on New Providence. Under the terms of each of its water supply agreements with the WSC, CW-Bahamas charges the WSC a fixed monthly amount, an amount each month that is based upon the amount of water supplied during the month, and pass-through energy charges, therefore CW-Bahamas’ revenue is impacted by changes in water demand and energy prices. To date, the volume of water CW-Bahamas sells to the WSC has not been adversely impacted by the COVID-19 pandemic despite the downturn in economic activity on New Providence that began in April 2020 stemming from the preventative measures taken by the government in March 2020. In addition, the adverse impact of the COVID-19 pandemic on The Bahamas government’s revenue sources may further delay the collection of CW-Bahamas’ delinquent accounts receivable from the WSC.
CW-Bahamas’ operations have been designated as essential services by the government of The Bahamas. Presently, CW-Bahamas’ day-to-day operations have not been materially impeded by the COVID-19 pandemic – we continue to produce and supply water to meet the requirements of our two water agreements with the WSC. We believe CW-Bahamas has sufficient spare parts and consumables inventories to continue normal operations.
Aerex
Presently, the COVID-19 pandemic has not materially impeded Aerex’s day-to-day operations.
Aerex presently has 14 plant employees. Should a number of these employees become ill or be required to enter quarantine as a result of COVID-19, Aerex could be required to reduce or cease its manufacturing activities, which could have a material adverse impact on our consolidated financial condition, results of operations and cash flows.
PERC
PERC’s operations are considered essential services by the states within which it operates. Presently, the COVID-19 pandemic has not materially impeded PERC’s day-to-day operations.
Approximately 75% of PERC’s revenue of $12.5 million for the year ended December 31, 2020 was generated in California under contracts with government entities. The State of California has publicly acknowledged its on-going financial difficulties as a result of the COVID-19 pandemic, and such difficulties presently, or could in the future, extend to the various counties, municipalities and other government-related entities in California, including PERC’s customers, which could adversely impact PERC’s revenue and the collection of its accounts receivable.
PERC employs state-certified water and wastewater operators to operate various water treatment facilties in California and Arizona. Should a number of these employees become ill or be required to enter quarantine as a result of COVID-19,
39
Table of Contents
PERC could have difficulty meeting its contractual and statutory obligations for operating these water treatment facilities, which could have a material adverse impact on our consolidated financial condition, results of operations and cash flows.
Cayman Water Retail License
We sell water through our retail operations under a license issued in July 1990 by the Cayman Islands government (the “1990 license”) that granted Cayman Water the exclusive right to provide potable water to customers within its licensed service area. Although the 1990 license was not expressly extended after January 2018, we continue to supply water under the terms of the 1990 license, as further discussed in the following paragraph. Pursuant to the 1990 license, Cayman Water has the exclusive right to produce potable water and distribute it by pipeline to its licensed service area, which consists of two of the three most populated areas of Grand Cayman Island: Seven Mile Beach and West Bay. In 2020 and 2019, we generated approximately 32% and 38%, respectively, of our consolidated revenue and 44% and 53%, respectively, of our consolidated gross profit from the retail water operations conducted under the 1990 license.
The 1990 license was originally scheduled to expire in July 2010 but was extended several times by the Cayman Islands government in order to provide the parties with additional time to negotiate the terms of a new license agreement. The most recent express extension of the license expired on January 31, 2018. We continue to operate under the terms of the 1990 license, providing water services to the level and quality specified in the 1990 license and in accordance with our understanding of its legal obligations, treating those obligations set forth in the 1990 license as operative notwithstanding the expiration of the express extension. We continue to pay the royalty required under the 1990 license.
In October 2016, the Government of the Cayman Islands passed legislation which created a new utilities regulation and competition office (“OfReg”). OfReg is an independent and accountable regulatory body with a view of protecting the rights of consumers, encouraging affordable utility services and promoting competition. OfReg, which began operations in January 2017, has the ability to supervise, monitor and regulate multiple utility undertakings and markets. Supplemental legislation was passed by the Government of the Cayman Islands in April 2017, which transferred responsibility for economic regulation of the water utility sector and the retail license negotiations from the WAC to OfReg in May 2017. We began license negotiations with OfReg in July 2017 and such negotiations are continuing. We have been informed during our retail license negotiations, both by OfReg and its predecessor in these negotiations, that the Cayman Islands government seeks to restructure the terms of our license in a manner that could significantly reduce the operating income and cash flows we have historically generated from our retail license.
The Cayman Islands government could seek to grant a third party a license to service some or all of Cayman Water’s present service area. However, as set forth in the 1990 license, “the Governor hereby agrees that upon the expiry of the term of this Licence or any extension thereof, he will not grant a licence or franchise to any other person or company for the processing, distribution, sale and supply of water within the Licence Area without having first offered such a licence or franchise to the Company on terms no less favourable than the terms offered to such other person or company.”
We are presently unable to determine what impact the resolution of our retail license negotiations will have on our cash flows, financial condition or results of operations but such resolution could result in a material reduction (or the loss) of the operating income and cash flows we have historically generated from our retail operations and could require us to record an impairment losses to reduce the carrying value of our retail segment assets. Such impairment losses could have a material adverse impact on our consolidated financial condition, results of operation and cash flows .
CW-Bahamas Performance Guarantees
Our contracts to supply water to the WSC from our Blue Hills and Windsor plants require us to guarantee delivery of a minimum quantity of water per week. If WSC requires the water and we do not meet this minimum, we are required to pay the WSC for the difference between the minimum and actual gallons delivered at a per gallon rate equal to the price per gallon that WSC is currently paying us under the contract. The Blue Hills contract expires in 2032 and requires us to deliver 63.0 million gallons of water each week. The Windsor contract expires in 2033 and requires us to deliver 16.8 million gallons of water each week.
40
Table of Contents
Adoption of New Accounting Standards:
None.
Effect of newly issued but not yet effective accounting standards:
In March 2020, the FASB issued ASU No. 2020-04, Reference Rate Reform (Topic 848), which provides optional expedients and exceptions to the current guidance on contract modifications and hedging relationships to ease the financial reporting burdens of the expected market transition from LIBOR and other interbank offered rates to alternative reference rates. The guidance was effective upon issuance and may be applied prospectively to contract modifications made and hedging relationships entered into or evaluated on or before December 31, 2022. We are currently evaluating the impact of the new guidance on our consolidated financial statements, however the adoption of this standard is not expected to have a material impact on our financial position, results of operations or cash flows .
Dividends
● On January 31, 2020, we paid a dividend of $0.085 to shareholders of record on January 2, 2020.
● On April 30, 2020, we paid a dividend of $0.085 to shareholders of record on April 1, 2020.
● On July 31, 2020, we paid a dividend of $0.085 to shareholders of record on July 1, 2020.
● On October 30, 2020, we paid a dividend of $0.085 to shareholders of record on October 1, 2020.
● On February 1, 2021, we paid a dividend of $0.085 to shareholders of record on January 4, 2021.
● On February 23, 2021, our Board declared a dividend of $0.085 payable on April 30, 2021 to shareholders of record on April 1, 2021.
We have paid dividends to owners of our common stock and redeemable preferred stock since we began declaring dividends in 1985. Our payment of any future cash dividends will depend upon our earnings, financial condition, cash flows, capital requirements and other factors our Board of Directors deems relevant in determining the amount and timing of such dividends.
Dividend Reinvestment and Common Stock Purchase Plan
This plan is available to our shareholders, who may reinvest all or a portion of their common stock dividends into shares of common stock at prevailing market prices and may also invest optional cash payments to purchase additional shares at prevailing market prices as part of this plan.
Impact of Inflation
Under the terms of our Cayman Islands license and our water sales agreements in The Bahamas and the British Virgin Islands, our water rates are automatically adjusted for inflation on an annual basis. We, therefore, believe that the impact of inflation on our gross profit, measured in consistent dollars, should not be material. However, significant increases in items such as fuel and energy costs could create additional credit risks for us, as our customers’ ability to pay our invoices could be adversely affected by such increases.
ITEM 7A.
QUANTITATIVE AND QUALITATIVE DISCLOSURE ABOUT MARKET RISK
Not applicable.
41