Item 2. Management’s Discussion and Analysis
Item 2. Management’s Discussion and Analysis of Financial Condition and Results of Operations
The following discussion and analysis provide information which management believes is relevant to an assessment and understanding of our condensed consolidated results of operations and financial condition. The discussion should be read in conjunction with the unaudited condensed consolidated financial statements and notes thereto contained in this Quarterly Report on Form 10-Q and the consolidated financial statements and notes thereto for the year ended December 31, 2021 contained in our 2021 Annual Report on Form 10-K. This discussion contains forward looking statements and involves numerous risks and uncertainties, including, but not limited to, those described in “Risk Factors” in Item 1A of Part II of the 2021 Annual Report on Form 10-K as updated and/or supplemented in subsequent filings with the SEC. Actual results may differ materially from those contained in any forward-looking statements. Unless the context otherwise requires, references to “we”, “us”, “our”, “TMC” and “the Company” are intended to mean the business and operations of TMC the metals company Inc. and its consolidated subsidiaries. The unaudited condensed consolidated interim financial statements for the three months ended March 31, 2022 and 2021, respectively, present the financial position and results of operations of TMC the metals company Inc. and its consolidated subsidiaries.
Overview
We are a deep-sea minerals exploration company focused on the collection and processing of polymetallic nodules found on the seafloor in international waters of the Clarion Clipperton Zone ("CCZ"), about 1,300 nautical miles south-west of San Diego, California.
The CCZ is a geological submarine fracture zone of abyssal plains and other formations in the Eastern Pacific Ocean, with a length of around 7,240 km (4,500 miles) that spans approximately 4,500,000 square kilometers (1,700,000 sq mi). Polymetallic nodules are discrete rocks that sit unattached to the seafloor, occur in significant quantities in the CCZ and have high concentrations of nickel, cobalt and copper in a single rock. These four metals contained in the polymetallic nodules are critical for the transition to clean energy. Our resource definition work to date shows that nodules in our contract areas represent the world’s largest estimated undeveloped source of critical battery metals. If we are able to collect polymetallic nodules from the seafloor on a commercial scale, we plan to use such nodules to produce three types of metal products: (i) feedstock for battery cathode precursors (nickel-copper-cobalt matte and/or nickel and cobalt sulfates) for electric vehicles (“EV”) and renewable energy storage markets, (ii) nickel-copper-cobalt matte and/or copper cathode for EV wiring, clean energy transmission and other applications and (iii) manganese silicate for manganese alloy production required for steel production. Our mission is to build a carefully managed shared stock of metal (a “metals common”) that can be used, recovered and reused for generations to come. Significant quantities of newly mined metal are required because existing metal stocks are insufficient to meet rapidly rising demand.
Exploration and exploitation of seabed minerals in international waters is regulated by the International Seabed Authority (“ISA”), an intergovernmental organization established pursuant to the 1994 Agreement Relating to the Implementation of the United Nations Convention on the Law of the Sea (“UNCLOS”). The ISA grants contracts to sovereign states or to private contractors who are sponsored by a sovereign state. The ISA requires that a contractor must obtain and maintain sponsorship by a host nation that is a member of the ISA and signatory to UNCLOS and such nation must maintain effective supervision and regulatory control over such sponsored contractor. The ISA has issued a total of 19 polymetallic nodule exploration contracts covering approximately 1.28 million km2, or 0.4% of the global seafloor, 17 of which are in the CCZ. We hold exclusive exploration and commercial rights to three of the 17 polymetallic nodule contract areas in the CCZ through our subsidiaries Nauru Ocean Resources Inc. (“NORI”) and Tonga Offshore Mining Limited (“TOML”), sponsored by the Republic of Nauru (“Nauru”) and the Kingdom of Tonga (“Tonga”), respectively, and exclusive commercial rights through our subsidiary, DeepGreen Engineering Pte. Ltd.’s (“DGE”), arrangement with Marawa Research and Exploration Limited (“Marawa”), a company owned and sponsored by the Republic of Kiribati (“Kiribati”).
We have key strategic alliances with (i) Allseas Group S.A. (“Allseas”), a leading global offshore contractor, which is developing a pilot collection system, which is expected to be modified into an initial smaller scale commercial production system and serve as the basis for the design of a full-scale commercial production system and (ii) Glencore International AG (Glencore) which holds offtake rights on 50% of the NORI nickel and copper production. In addition, we have worked with an engineering firm Hatch Ltd. and consultants Kingston Process Metallurgy Inc. to develop a near-zero solid waste flowsheet. The pyromet stages of the flowsheet were tested as part of our pilot plant program at FLSmidth & Co. A/S’s and XPS Solutions’ (Glencore subsidiary) facilities and hydrometallurgical refining stages are being carried out at SGS SA. The near-zero solid waste flowsheet is in the process design that is expected to serve as the basis for our onshore processing facilities. In March 2022, we entered into a non-binding memorandum of understanding with Epsilon Carbon Pvt, LTD. (“Epsilon Carbon”) in which Epsilon Carbon expressed its intent to conduct pre-feasibility work to potentially finance, engineer, permit, construct and operate a commercial polymetallic nodule processing plant in India.
18
Table of Contents
We are currently focused on applying for our first exploitation contract from the ISA on the NORI Area D contract area with the goal of potentially starting commercial production in 2024. To reach our objective and initiate commercial production in 2024, we are: (i) defining our resource and project economics, (ii) developing an offshore nodule collection system, (iii) assessing the ESG impacts of offshore nodule collection, and (iv) developing onshore technology to process collected polymetallic nodules into a manganese silicate product, and an intermediate nickel-copper-cobalt matte product and/or end-products like nickel and cobalt sulfates, and copper cathode.
We are still in the exploration phase and have not yet declared mineral reserves. We have yet to obtain exploitation contracts from the ISA to commence commercial scale polymetallic nodule collection in the CCZ and have yet to obtain the applicable environmental permits and other permits required to build and operate commercial scale polymetallic nodule processing and refining plants on land.
Developments in the First Quarter 2022
Building on the significant achievements in 2021, below are some of the major developments that occurred in the first quarter 2022.
● Project Zero Plant: In March 2022, we announced that we entered into a non-binding memorandum of understanding for a business collaboration with Epsilon Carbon to complete a pre-feasibility study for a commercial plant in India, powered by renewables and targeting capacity to process approximately 1.3 million tonnes per annum (“Mtpa”) of wet nodules into more than 30,000 tonnes per annum (“TPA”) of an intermediate nickel-copper-cobalt matte product used in active cathode material for nickel-rich cathode chemistries for lithium-ion batteries and more than 750,000 TPA of manganese silicate by-product expected to be used in manganese alloy production for the steel industry.
● Project Zero System: In March 2022, our subsidiary, NORI, and Allseas entered into a non-binding term sheet for the potential development and operation of a commercial nodule collection system. The pilot nodule collection system developed and currently being tested by Allseas is expected to be upgraded to a commercial system with a targeted production capacity of approximately 1.3 Mtpa of wet nodules, with expected production readiness by the fourth quarter of 2024.
● Environmental Filings: In March 2022, a revised Environmental Impact Study for the collector test was filed with the ISA (original filed July 29, 2021), incorporating stakeholder feedback and baseline results collected in 2021. Subsequently, a detailed Environmental Management and Monitoring Plan for the collector test was filed with the ISA on May 2, 2022. This documentation is required for the collector test to proceed, which is currently planned for the third quarter of 2022 in the NORI Area D.
● Pilot Collection System Trials:
● Harbor Trials: In March 2022, the pilot collector vehicle underwent extensive equipment testing in the Port of Rotterdam and all systems were shown to be fully functional.
● North Sea Drive Trials: In March 2022, the pilot collector vehicle and the Hidden Gem vessel underwent extensive testing of critical deployment and mobility functions in the Dutch Sector of the North Sea, covering a total of 4,533 meters. All systems were shown to be functional. Engineers successfully completed a variety of tests of the dynamic positioning system aboard Hidden Gem in advance of pilot trials in the NORI Area D in the CCZ expected in the second half of 2022.
Developments Subsequent to March 31, 2022
● Pilot Collection System Trials - Atlantic Deep-Water Trials: In April 2022, segments of the pilot nodule riser system were mobilized onboard the Hidden Gem for planned deep-sea testing with the collector vehicle in the Eastern Atlantic Basin. Vehicle drive testing down to 2,470-meter depths has now occurred, which we expect will be followed by tests in 1,500-meter depths deploying the riser and the collector, connecting them, then bringing them back onboard.
● Independent Lifecycle Impact Assessment of NORI Area D Project: In April 2022, we announced that we chose the leading lithium-ion battery supply chain research firm, Benchmark Mineral Intelligence (“Benchmark”), to conduct an independent lifecycle assessment of the environmental impacts of our planned NORI Area D polymetallic nodule project and
19
Table of Contents
compare these impacts to producing the same metals from commonly used production pathways using conventional land ores. Benchmark anticipates completing its comprehensive Lifecycle Impact Assessment for us in mid-Summer 2022.
The Business Combination
On September 9, 2021, we completed the Business Combination with SOAC. The transaction resulted in the combined company being renamed “TMC the metals company Inc.” and the combined company’s common shares and warrants to purchase common shares commenced trading on the Nasdaq Global Select Market (“Nasdaq”) on September 10, 2021 under the symbols “TMC” and “TMCWW,” respectively. As a result of the Business Combination, we received gross proceeds of $137.6 million ($104.5 million net of transactions fees).
The Business Combination was accounted for as a reverse recapitalization and DeepGreen was deemed the accounting acquirer. Under this method of accounting, SOAC was treated as the acquired company for financial statement reporting purposes. The Business Combination was accounted for as a reverse acquisition with no goodwill or intangible assets being recorded. As SOAC had no operations, the net assets acquired were recorded at their historical cost. Adjustments related to the Business Combination including consideration paid to DeepGreen shareholders and any other adjustments to eliminate the historical equity of SOAC and recapitalize the equity of DeepGreen were recorded to common shares to reflect the effective issuance of common shares to SOAC and Private Investment in Public Equity investors in the Business Combination.
Following the Business Combination, we became the successor to an SEC-registered company, which resulted in us hiring additional personnel and implement procedures and processes to address public company regulatory requirements and customary practices to ensure ongoing compliance with applicable law and Nasdaq listing requirements. We expect to incur additional annual expenses as a public company for, among other things, directors’ and officers’ liability insurance, director fees, additional internal and external accounting, legal and administrative resources, including increased personnel costs, audit and other professional service fees.
Exploration Contracts
We currently hold exclusive exploration rights to certain polymetallic nodule areas in the CCZ through our subsidiaries NORI and TOML, sponsored by Nauru and Tonga, respectively, and exclusive commercial rights through our subsidiary, DGE’s, arrangement with Marawa, a company owned and sponsored by Kiribati.
NORI Exploration Contract
NORI, our wholly-owned subsidiary, was granted the NORI Exploration Contract on July 22, 2011 under the sponsorship of Nauru. This Exploration Contract provides NORI with exclusive rights to explore for polymetallic nodules in an area covering 74,830 km 2 in the CCZ (“NORI Area”) for an initial term of 15 years (renewable for successive five-year periods) subject to complying with the exploration contract terms and provides NORI with the priority right to apply for an exploitation contract to collect polymetallic nodules in the same area.
Marawa Agreements
Marawa, an entity owned and sponsored by Kiribati, was granted the Marawa Exploration Contract on May 30, 2012. DGE, our wholly-owned subsidiary, entered into agreements with Marawa and Kiribati which provide DGE with exclusive exploration rights to an area covering 74,990 km2 in the CCZ (the “Marawa Contract Area”). The exploration contract between Marawa and the ISA (the “Marawa Exploration Contract”) was signed on January 19, 2015. To date, very limited offshore marine resource definition activities in the Marawa Contract Area have occurred and DGE expects to commit future resources as contractually agreed with Marawa to evaluate the future commercial viability of any project in such area. Marawa has not completed adequate exploration to establish the economic viability of any project in the Marawa Contract Area. Further work will need to be conducted in order to assess the viability of any potential project in the Marawa Contract Area and such work may take several years until such assessment can be made. Marawa has delayed certain of its efforts in the Marawa Contract Area while it determines how it will move forward with additional assessment work.
20
Table of Contents
TOML Exploration Contract
TOML, our wholly-owned subsidiary, was granted the TOML Exploration Contract on January 11, 2012 under the sponsorship of Tonga. TOML was acquired by us on March 31, 2020 for $32 million from Deep Sea Mining Finance Ltd. (“DSMF”). The TOML Exploration Contract provides TOML with exclusive rights to explore for polymetallic nodules in an area covering 74,713 km 2 in the CCZ (“TOML Area”) for an initial term of 15 years (renewable for successive five-year periods) subject to complying with the exploration contract terms and a priority right to apply for an exploitation contract to collect polymetallic nodules in the same area. On March 8, 2008, Tonga and TOML entered into a sponsorship agreement formalizing certain obligations of the parties in relation to TOML’s exploration application to the ISA (subsequently granted) for the TOML Contract Area. The sponsorship agreement was updated on September 23, 2021.
Key Trends, Opportunities and Uncertainties
We are currently a pre-revenue company and we do not anticipate earning revenues until such time as NORI receives an exploitation contract from the ISA and we are able to successfully collect polymetallic nodules and process the nodules into saleable products on a commercial scale. We believe that our performance and future success pose risks and challenges, including those related to: finalization of ISA regulations to allow for commercial exploitation, approval of an application for the ISA exploitation contract, developing environmental regulations associated with our business and successful development of our technologies to collect and process polymetallic nodules. These risks, as well as other risks, are discussed in the section entitled “ Risk Factors ” in Item 1A of Part II of the 2021 Annual Report on Form 10-K as updated and/or supplemented in subsequent filings with the SEC.
Impact of Climate Change
We are committed to adopting the Task Force on Climate-Related Financial Disclosures recommendations. In our upcoming inaugural impact report, we will be providing the same type of climate-related disclosure to the one in the 2021 Annual Report on Form 10-K. We recognize that climate change may have a meaningful impact on our financial performance over time, and we have begun the process of consolidating key risks and corresponding action plans to mitigate their negative impact of climate change and create value.
Our climate related transition risks and opportunities are likely to be driven by changes in regulation, public policy, and technology, as disclosed in our 2021 Annual Report on Form 10-K.
COVID-19
During the first quarter of 2022, active work comprised of the integration of the collector and riser to the Hidden Gem and completion of harbor testing, offshore dynamic positioning trials and the North Sea drive test. There were some sporadic outbreaks of COVID on the Hidden Gem while the vessel was docked in Rotterdam requiring isolation of some of the members of the work crews. The project plan was adjusted to minimize the impact on the project’s schedule resulting in little impact to the overall project schedule. Allseas implemented pre-departure COVID protocols and there were no reported COVID incidents during the offshore dynamic positioning trials and the North Sea drive test.
We continue to closely monitor the recent developments surrounding the continued spread and potential resurgence of COVID-19 from variants. The COVID-19 pandemic may have an adverse impact on our operations, particularly because of preventive and precautionary measures that our company, other businesses, and governments are taking. Refer to the section entitled “Risk Factors” in Item 1A of Part II of the 2021 Annual Report on Form 10-K as updated and/or supplemented in subsequent filings with the SEC for more information. We are unable to predict the full impact that the COVID-19 pandemic will have on our future results of operations, liquidity and financial condition due to numerous uncertainties, including the duration of the pandemic and the actions that may be taken by government authorities. However, COVID-19 is not expected to result in any significant changes to our business or our costs in the near term. We will continue to monitor the performance of our business and re-assess the impacts of COVID-19.
Restatement of Previously Issued Quarterly Financial Statements
As disclosed in our 2021 Annual Report on Form 10-K filed March 25, 2022, we have restated our financial statements as of and for the three-month period ended March 31, 2021 in the accompanying unaudited condensed consolidated financial statements included in this Quarterly Report on Form 10-Q.
21
Table of Contents
The restatement resulted from our expensing of options granted in the first quarter of 2021 under the Company’s Short-Term Incentive Plan based on the grantee’s historical start date with us rather than the grant date of the options on March 4, 2021, as required by U.S. Generally Accepted Accounting Principles (“U.S. GAAP”). This resulted in a $1.8 million overstatement of stock-based compensation expenses as of and for the three-month period ended March 31, 2021.
Basis of Presentation
We currently conduct our business through one operating segment. As a pre-revenue company with no commercial operations, our activities to date have been limited. Our historical results are reported under U.S. GAAP and in U.S. dollars. All share and per share amounts have been adjusted to reflect the impact of the Business Combination.
Components of Results of Operations
We are an exploration-stage company with no revenue to date and a net loss of $21.1 million for the three months ended March 31, 2022, compared to a net loss of $55.7 million in the same quarter of 2021. We have an accumulated deficit of approximately $325.3 million from inception through March 31, 2022.
Our historical results may not be indicative of our future results for reasons that may be difficult to anticipate. Accordingly, the drivers of our future financial results, as well as the components of such results, may not be comparable to our historical or projected results of operations.
Revenue
To date, we have not generated any revenue. We do not expect to generate revenue until at least 2024 and only if NORI receives an exploitation contract from the ISA and we are able to successfully collect polymetallic nodules and process the nodules into saleable products on a commercial scale. Any revenue from initial production is difficult to predict.
Exploration and Evaluation Expenses
We expense all costs relating to exploration and development of mineral claims. Such exploration and development costs include, but are not limited to, ISA contract management, geological, geochemical and geophysical studies, environmental baseline studies, process development and payments to Allseas for the Pilot Mining Test System (“PMTS”). Our exploration expenses are impacted by the amount of exploration work conducted during each period. The acquisition cost of ISA polymetallic nodule exploration contracts will be charged to operations as amortization expense on a unit-of-production method based on proven and probable reserves should commercial production commence in the future.
General and Administrative Expenses
General and administrative (“G&A”) expenses consist primarily of compensation for employees, consultants and directors, including share-based compensation, consulting fees, investor relations expenses, expenses related to advertising and marketing functions, insurance costs, office and sundry expenses, professional fees (including legal, audit and tax fees), travel expenses and transfer and filing fees.
Share-based compensation costs from the issuance of stock options and restricted share units (“RSUs”) is measured at the grant date based on the fair value of the award and is recognized over the related service period. Share-based compensation costs are charged to exploration expenses and general and administrative expenses depending on the function fulfilled by the holder of the award. In instances where an award is issued for financing related services, the costs are included within equity as part of the financing costs. We recognize forfeiture of any awards as they occur.
Interest Income/Expense
Interest expense in the first quarter of 2021 resulted from our financing transactions, specifically the convertible debentures issued in February 2021, which accrued interest at 7% per annum. The convertible debentures were fully converted into DeepGreen common shares on September 9, 2021.
22
Table of Contents
Foreign Exchange Loss
The foreign exchange income or loss for the periods primarily relates to our cash held in Canadian dollars and to the settlement of costs incurred in foreign currencies, depending on either the strengthening or weakening of the U.S. dollar.
Change in Fa ir V alue of W arrants L iability
The change in fair value of warrants liability primarily consists of the change in the fair value of the 9,500,000 warrants issued to Sustainable Opportunities Holdings LLC concurrently with SOAC’s initial public offering (the “Private Warrants”). For accounting purposes, the Company was considered to have issued the Private Warrants as part of the Business Combination, and we are required to re-measure the fair value of our Private Warrants at the end of each reporting period.
Results of Operations
DeepGreen was determined to be the accounting acquirer and therefore, all information prior to the Business Combination, including the prior period financial information, represent the financial condition and operating results of DeepGreen.
The following is a discussion of our results of operations for the three months ended March 31, 2022 and 2021. Our accounting policies are described in Note 3 “Summary of Significant Accounting Policies” in our financial statements filed as part of the 2021 Annual Report on Form 10-K.
Comparison of the Three Months Ended March 31, 2022 and 2021
Three Months Ended March 31,
2021
2022
(Restated)
Change
% Change
(dollar amounts in thousands)
Exploration and evaluation expenses
7,343
38,107
(30,764)
(81%)
G&A expenses
8,564
17,364
(8,800)
(51%)
Interest expense
—
220
(220)
(100%)
Change in fair value of warrants liability
5,188
—
5,188
100%
Foreign exchange loss
22
19
3
16%
21,117
55,710
(34,593)
(62%)
Exploration and Evaluation Expenses
Exploration and evaluation expenses for the three months ended March 31, 2022 were $7.3 million, compared to $38.1 million for the same period in 2021. The decrease of $30.8 million was primarily due a decrease in offshore campaign costs of $16.4 million, due to the completion of the NORI Area D baseline campaigns in the fourth quarter of 2021. The first quarter of 2021 offshore campaign costs included a fair value increase of $12.2 million that was recognized on the issuance of DeepGreen common shares to Maersk. The decrease in the first quarter year over year also reflects a reduction in share-based compensation of $15.2 million in the 2022 period, as a significant number of stock options were awarded in March 2021, in recognition of past services and in anticipation of the Business Combination, while no stock options were awarded in the first quarter of 2022. Work on the PMTS progressed in the first quarter of 2022 resulting in increased PMTS expenses of $1.3 million, which partially offset the above expense reductions.
General and Administrative Expenses
G&A expenses for the three months ended March 31, 2022 were $8.6 million compared to $17.4 million for the same period in 2021. The decrease of $8.8 million in G&A expenses in the first quarter of 2022 was mainly the result of lower share-based compensation in the 2022 period as the first quarter of 2021 included the award of a significant number of stock options in recognition of past services and in anticipation of the Business Combination. This decrease was partially offset by higher G&A expenses in the first quarter of 2022, reflecting an increase in personnel, legal and other expenses associated with being a public company.
23
Table of Contents
Change in F air V alue of W arrants Liability
The change in fair value of warrants liability during the first quarter of 2022 resulted in a charge of $5.2 million. The charge was primarily due to a 25% increase in our share price in the first three months of 2022. The warrants liability was initially recorded as part of the Business Combination and therefore did not exist in the prior year.
Liquidity and Capital Resources
Prior to closing of the Business Combination, our primary sources of capital have been private placements of DeepGreen common shares and DeepGreen preferred shares and the issuance of convertible debentures completed in February 2021, which were automatically converted into DeepGreen common shares immediately prior to the completion of the Business Combination. In addition, on September 9, 2021, we completed the Business Combination with SOAC, and as a result we received gross proceeds of $137.6 million ($104.5 million net of transaction fees). As of March 31, 2022, we had cash on hand of $69.0 million.
We have yet to generate any revenue from our business operations. We are an exploration-stage company and the recovery of our investment in mineral exploration contracts and attainment of profitable operations is dependent upon many factors including, among other things, the development of production system for collecting polymetallic nodules from the seafloor as well as the development of our processing technology for the metallurgical treatment of such nodules, the establishment of mineable reserves, the demonstration of commercial and technical feasibility of seafloor polymetallic nodule collection and processing systems, metal prices, and securing ISA exploitation contracts. While we have obtained financing in the past, there is no assurance that such financing will continue to be available on favorable terms, if at all.
We believe that our cash on hand will be sufficient to meet our working capital and capital expenditure requirements for at least the next twelve months, however, additional cash resources may be required due to changes in business conditions or other developments, including, but not limited to, deferral of approvals, capital and operating cost escalation, currently unrecognized technical and development challenges or changes in external business environment. We may need to seek additional equity or debt financing. If the financing is not available, or if the terms of financing are less desirable than we expect, we may be forced to delay our exploration and/or exploitation activities or scale back our operations, which could have a material adverse impact on our business and financial prospects.
Cash Flows Summary
Comparison of the Three Months Ended March 31, 2022 and March 31, 2021
Presented below is a summary of our operating, investing and financing cash flows:
Three Months Ended March 31,
2022
2021 (Restated)
(in thousands)
(in thousands)
Net cash used in operating activities
$
(15,529)
$
(10,060)
Net cash used in investing activities
$
(210)
$
(2,190)
Net cash (used in) provided by financing activities
$
(78)
$
27,377
(Decrease) increase in cash
$
(15,817)
$
15,127
Cash flows used in Operating Activities
Net cash used in operating activities for the three months ended March 31, 2022 was $15.5 million, attributable to a net loss of $21.1 million and an increase in net operating assets and liabilities of $5.3 million, partially offset by non-cash adjustments of $12.2 million. Non-cash adjustments primarily consisted of $6.9 million of expenses settled with share-based payments and $5.2 million related to the increase in the fair value of the Private Warrants, mainly as a result of the increase in our share price during the first three months of 2022. The increase in our net operating assets and liabilities was primarily due to a $5.9 million decrease in accounts payable and accrued liabilities in the 2022 period due to the timing of supplier payments.
24
Table of Contents
Cash flows used in Investing Activities
Net cash used in investing activities for the three months ended March 31, 2022 was $0.2 million for the purchase of equipment, as compared to $2.2 million in the first three months of 2021, which related to the initial payments made to DSMF in connection with our acquisition of TOML in 2020.
Cash flows provided by Financing Activities
Net cash used in financing activities for the three months ended March 31, 2022 was $0.1 million, compared to $27.4 million provided by financing activities in the first three months of 2021, which consisted of $26.0 million from the issuance of convertible debentures in February 2021 and $1.4 million from the exercise of incentive stock options.
Contractual Obligations and Commitments
NORI Exploration Contract
As part of the NORI Exploration Contract with the ISA, NORI submitted a periodic review report to the ISA in 2021, covering its intended work plan the 2017-2021 period. The periodic review report included a summary of work completed over the previous 5-year period (2017 to 2021) and a work plan and estimated budget for the next five-year period (2022 to 2026). NORI had committed to spend approximately $5 million to deliver on its intended work plan from 2017 to 2021, which it has significantly exceeded. The periodic review report, which included a proposed work plan and estimated budget for 2022 to 2026, has been reviewed by and agreed with the ISA, and we are implementing the next five-year plan. NORI has estimated its work plan for 2022 and 2023 to be approximately $40 million and $25 million, respectively, which may be settled in cash or equity. The cost of the estimated work plan for 2024 onwards is contingent on the ISA’s approval of the NORI Area D exploitation application. Should the approval of NORI’s exploitation application for NORI Area D be delayed or rejected, NORI intends to revise its estimated future work plan in respect of its NORI Area. Work plans are reviewed annually by the Company, agreed with the ISA and may be subject to change depending on the Company’s progress to date.
Marawa Option Agreement and Services Agreement
Through DGE’s Marawa Option Agreement and Services Agreement with Marawa with respect to the Marawa Area, DGE committed to spend a defined amount of funds on exploration activities on an annual basis. The commitment for fiscal 2022, 2023 and 2024 is AUD $1 million, AUD $3 million and AUD $2 million, respectively. Such commitment is negotiated with the ISA as part of a five-year plan submissions and is subject to regular periodic reviews. To date, very limited offshore marine resource definition activities in the Marawa Contract Area have occurred and DGE expects to commit future resources as contractually agreed with Marawa to evaluate the future commercial viability of any project in such area. Marawa has not completed adequate exploration to establish the economic viability of any project in the Marawa Contract Area. Further work will need to be conducted in order to assess the viability of any potential project in the Marawa Contract Area and such work may take several years until such assessment can be made. Marawa has delayed certain of its efforts in the Marawa Contract Area while it determines how it will move forward with additional assessment work.
TOML Exploration Contract
As part of the TOML Exploration Contract, TOML submitted a periodic review report to the ISA in 2021, covering the 2017-2021 period. The periodic review report included a summary of work completed over the five-year period and a program of activities and estimated budget for the next five-year period. TOML had committed to spend $30.0 million over the five-year period from 2017 to 2021. Such commitment has flexibility where the amount can be reduced by the ISA and such reduction would be dependent upon various factors including the success of the exploration programs and the availability of funding. The ISA is currently reviewing the periodic report, which includes the next 5-year program of work, at which point the next five-year commitment will be finalized.
25
Table of Contents
Regulatory Obligations Relating to Exploration Contracts
Each of TOML and NORI require sponsorship from their host sponsoring nations, Tonga and Nauru, respectively. Each company has been registered and incorporated within the applicable host nation’s jurisdiction. The ISA requires that a contractor must obtain and maintain sponsorship by a host nation that is a member of the ISA and such nation must maintain effective supervision and regulation over such sponsored contractor. Each of TOML and NORI is subject to the registration and incorporation requirements of these nations. In the event the sponsorship is otherwise terminated, such subsidiary will be required to obtain new sponsorship from another nation that is a member of the ISA. Failure to obtain such new sponsorship would have a material impact on the operations of such subsidiary and us.
Sponsorship Agreements
On July 5, 2017, Nauru, the Nauru Seabed Minerals Authority and NORI entered into the NORI Sponsorship Agreement formalizing certain obligations of the parties in relation to NORI's exploration and potential exploitation of the NORI Area. Upon reaching the minimum recovery level within the exploitation contract area, NORI will pay Nauru a seabed mineral recovery payment based on the polymetallic nodules recovered from the exploitation contract area. In addition, NORI will pay an administration fee each year to Nauru for such administration and sponsorship, which is subject to review and increase in the event NORI is granted an ISA exploitation contract.
On March 8, 2008, Tonga and TOML entered into the TOML Sponsorship Agreement formalizing certain obligations of the parties in relation to TOML's exploration and potential exploitation of the TOML Area. Upon reaching the minimum recovery level within the exploitation contract area, TOML has agreed to pay Tonga a seabed mineral recovery payment based on the polymetallic nodules recovered from the exploitation contract area. In addition, TOML has agreed to pay the reasonable direct costs incurred by Tonga to administer the obligations of Tonga to the ISA. On September 23, 2021, Tonga updated the TOML Sponsorship Agreement harmonizing the terms of its engagement with TOML with those held by NORI with Nauru.
Allseas Agreements
On March 29, 2019, we entered into a strategic alliance with Allseas to develop a system to collect, lift and transport nodules from the seafloor to shore and agreed to enter into a nodule collection and shipping agreement whereby Allseas would provide commercial services for the collection of the first 200 million metric tonnes of polymetallic nodules on a cost plus 50% profit basis. In furtherance of this agreement, on July 8, 2019, we entered into a Pilot Mining Test Agreement with Allseas (“PMTA”), which was amended on three occasions in 2020 and 2021, to develop and deploy a PMTS, successful completion of which is a prerequisite for our application for an exploitation contract with the ISA. Under the PMTA, Allseas agreed to cover the development cost of the project in exchange for a payment from us upon successful completion of the pilot trial of the PMTS in NORI Area D.
On March 16, 2022, NORI and Allseas entered into a non-binding term sheet for the development and operation of commercial nodule collection system The pilot nodule collection system developed and currently being tested by Allseas and is expected to be upgraded to a commercial system with a targeted production capacity of 1.3 million tonnes of wet nodules per year with expected production readiness by the fourth quarter of 2024. NORI and Allseas intend to equally finance all costs related to developing and getting the first commercial system. Once in production, NORI expects to pay Allseas a nodule collection and transshipment fee estimated at approximately EUR 150 per wet tonne in the first year of operations and expected to be reduced as Allseas scales up production to 1.3 million wet tonnes per year. The parties intend to further detail and revise these cost estimates in the definitive agreement contemplated by the non-binding term sheet, which the parties expect to enter into no later than December 31, 2022 following the completion of the planned pilot collection tests. Subject to the necessary regulatory approvals Allseas and NORI also intend to investigate acquiring a second production vessel similar to the Hidden Gem, a Samsung 10000, with the potential for it to be engineered to support a higher production rate of three million tonnes of wet nodules. There can be no assurances, however, that we will enter into definitive agreements with Allseas contemplated by the non-binding term sheet in a particular time period, or at all, or on terms similar to those set forth in the non-binding term sheet, or that if such definitive agreements are entered into by us that the proposed commercial systems and second production vessel will be successfully developed or operated in a particular time period, or at all.
Through December 31, 2021, we have made the following payments to Allseas under the PMTA: (a) $10 million in cash in February 2020, (b) $10 million through the issuance of 3.2 million common shares valued at $3.11 per share in February 2020, (c) issued Allseas
26
Table of Contents
warrants to purchase 11.6 million common shares at a nominal exercise price per share in March 2021 and (d) $10 million in cash in October 2021, following the closing of the Business Combination and meeting certain progress targets on the PMTS.
We made the second $10 million payment to Allseas under the PMTA on April 25, 2022, following the successful completion of the North Sea drive test. The third and final $10 million payment to Allseas will be due upon successful completion of the pilot trial of the PMTS in NORI Area D.
Maersk Agreements
Effective March 15, 2017, we entered into a strategic partnership with Maersk to undertake the exploration, environmental baseline and offshore testing required to support development of feasibility studies for economic production of polymetallic nodules from the CCZ. Under the agreement, Maersk provided vessel services and project management services, which enabled us to undertake the various offshore campaigns to support required pre-feasibility studies. During these offshore campaigns, we undertook baseline studies required to complete an ESIA, collected nodules for metallurgical test work and collected samples and survey data for resource evaluation. The invoiced cost related to the vessel was settled through issuance of common shares at an agreed upon price of $1.08 per common share. Project management services provided by Maersk for managing these offshore campaigns are paid in cash.
On March 3, 2021, the agreement with Maersk was amended whereby all costs incurred on or after February 5, 2021, pertaining to the use of the marine vessel, would be paid in cash rather than through issuance of common shares. Under this amendment, Maersk also agreed that amounts owed to Maersk for services rendered through February 5, 2021 in the aggregate amount of $4.6 million had been satisfied by the issuance of 4.2 million common shares at a contractual price per share of $1.08.
Our agreement with Maersk ended pursuant to its terms in January 2022. We are currently in discussion with a third party to provide a survey vessel and specialized remotely operated vehicles, and autonomous underwater vehicles services required to support the implementation of the collector test monitoring survey planned for 2022 in the NORI Area D.
Offtake Agreement
On May 25, 2012, DGE and Glencore International AG (“Glencore”) entered into a copper offtake agreement and a nickel offtake agreement. DGE has agreed to deliver to Glencore 50% of the annual quantity of copper and nickel produced by a DGE-owned facility from nodules derived from the NORI Area at London Metal Exchange referenced market pricing with allowances for product quality and delivery location. Either party may terminate the agreement upon a material breach or insolvency of the other party. Glencore may also terminate the agreement by giving twelve months’ notice.
Off-Balance Sheet Arrangements
We are not party to any off-balance sheet arrangements.
Critical Accounting Policies and Significant Judgments and Estimates
Our management's discussion and analysis of our financial condition and results of operations is based on our condensed consolidated interim financial statements, which have been prepared in accordance with U.S. GAAP. The preparation of these condensed consolidated interim financial statements requires us to make estimates and assumptions that affect the reported amounts of assets and liabilities and the disclosure of contingent assets and liabilities at the date of these statements, as well as expenses incurred during the reporting periods. Our estimates are based on our historical experience and various other factors that we believe are reasonable under the circumstances, the results of which form the basis for making judgments about items that are not readily apparent from other sources. Actual results may differ from these estimates under different assumptions or conditions.
27
Table of Contents
Except as described in Note 3 to our condensed consolidated interim financial statements included in this Quarterly Report on Form 10-Q, there have been no material changes to our critical accounting policies and estimates as compared to the critical accounting policies and estimates disclosed in our 2021 Annual Report on Form 10-K filed with the SEC on March 25, 2022.
Recent Accounting Pronouncements
See Note 3 to the condensed consolidated interim financial statements included in this Quarterly Report on Form 10-Q for more information about recent accounting pronouncements, the timing of their adoption, and our assessment, to the extent we have made one, of their potential impact on our financial condition and our results of operations and cash flows.
Emerging Growth Company Status
Section 102(b)(1) of the Jumpstart Our Business Startups (“JOBS”) Act exempts emerging growth companies from being required to comply with new or revised financial accounting standards until private companies are required to comply with the new or revised financial accounting standards. The JOBS Act provides that a company can choose not to take advantage of the extended transition period and comply with the requirements that apply to non-emerging growth companies, and any such election to not take advantage of the extended transition period is irrevocable.
We are an “emerging growth company” as defined in Section 2(a) of the Securities Act and have elected to take advantage of the benefits of the extended transition period for new or revised financial accounting standards. Following the closing of the Business Combination, we remained an emerging growth company through the end of the 2021 fiscal year and we expect to continue to take advantage of the benefits of the extended transition period at least to the end of the fiscal year, although we may decide to early adopt such new or revised accounting standards to the extent permitted by such standards. This may make it difficult or impossible to compare our financial results with the financial results of another public company that is either not an emerging growth company or is an emerging growth company that has chosen not to take advantage of the extended transition period exemptions because of the potential differences in accounting standards used.
Cautionary Statements Regarding the NORI Initial Assessment and TOML Mineral Resource Statement
We have defined the size and quality of our resource in the NORI and TOML Areas, as described below, in our SEC Regulation S-K (subpart 1300) compliant Technical Report Summary - Initial Assessment, of the NORI Property, Clarion-Clipperton Zone, Pacific Ocean dated March 17, 2021 ( “ NORI Initial Assessment ” ) and Technical Report Summary - TOML Mineral Resource, Clarion-Clipperton Zone, Pacific Ocean dated March 26, 2021 ( “ TOML Mineral Resource Statement ” ), respectively, prepared by AMC Consultants Ltd. ( “ AMC ” ). We plan to continue to define our resource in the NORI and TOML Areas and develop the project economics. The initial assessment included in the NORI Initial Assessment is a conceptual study of the potential viability of mineral resources in the NORI Area D. This initial assessment indicates that development of the mineral resource in the NORI Area D is potentially technically and economically viable; however, due to the preliminary nature of project planning and design, and the untested nature of the specific seafloor production systems at a commercial scale, economic viability has not yet been demonstrated.
The NORI Initial Assessment and TOML Mineral Resource Statement do not include the conversion of mineral resources to mineral reserves.
As used in this Quarterly Report on Form 10-Q or in the applicable report summary, the terms “ mineral resource, ” “ measured mineral resource, ” “ indicated mineral resource ” and “ inferred mineral resource ” , as applicable, are defined and used in accordance with the SEC Mining Rules.
You are specifically cautioned not to assume that any part or all of the mineral deposits in these categories will ever be converted into mineral reserves, as defined by the SEC. You are also cautioned that mineral resources do not have demonstrated economic value. Information concerning our mineral properties in the NORI and TOML Technical Report Summaries and in this Quarterly Report on Form 10-Q includes information that has been prepared in accordance with the requirements of the SEC Mining Rules forth in subpart 1300 of Regulation S-K. Under SEC standards, mineralization, such as mineral resources, may not be classified as a “ reserve ” unless the determination has been made that the mineralization could be economically and legally produced or extracted at the time of the reserve determination. Inferred mineral resources have a high degree of uncertainty as to their existence and to whether they can be economically or legally commercialized. Under the SEC Mining Rules, estimates of inferred mineral resources may not form the basis
28
Table of Contents
of an economic analysis. It cannot be assumed that all or any part of an inferred mineral resource will ever be upgraded to a higher category. A significant amount of exploration must be completed in order to determine whether an inferred mineral resource may be upgraded to a higher category. Therefore, you are cautioned not to assume that all or any part of an inferred mineral resource exists, that it can be economically or legally commercialized, or that it will ever be upgraded to a higher category. Approximately 97% of the NORI Area D resource is categorized as measured or indicated.
Likewise, you are cautioned not to assume that all or any part of measured or indicated mineral resources will ever be upgraded to mineral reserves.
Text extracted from the filing as submitted to EDGAR. Formatting, tables and exhibits are simplified for reading; the original document is authoritative for anything you rely on.