Item 1. Legal Proceedings
ITEM 1 – LEGAL PROCEEDINGS
Periodically, we are involved in other proceedings or litigation arising in the ordinary course of business. We do not believe that the ultimate resolution
of these matters will materially affect our business, financial position or results of operations. However, we cannot ensure that we will prevail in any litigation and, regardless of the outcome, may incur significant litigation expense and may have
significant diversion of management attention.
On July 19, 2022, final judgment was entered by the United States District Court, or Court, for a Consent Decree
between the Delaware Sand and Gravel Remedial Trust, or Trust, and the United States Environmental Protection Agency, or USEPA, that governs the implementation of Amendment No 2 to the USEPA’s 1988 Record of Decision for the Delaware Sand & Gravel
Landfill Superfund Site, or Site, located in New Castle County, Delaware, issued on December 12, 2017, or ROD Amendment No. 2, confirming, among other things, the terms and conditions set forth in a Settlement Agreement upon which The Chemours Company
FC, LLC, Hercules, LLC, Waste Management of Delaware, Inc., SC Holdings, Inc., Cytec Industries, Inc., Zeneca Inc., and Bayer CropScience Inc., collectively the Percentage Settlors, and the Trust, on one hand, and Artesian Water, on the other hand,
have agreed to resolve certain of Artesian Water’s claims and issues relating to releases of contaminants from the Site.
ROD Amendment No. 2 sets forth the remedy for the contamination existing at and emanating from the Site, or the
Remedy, to address a release of contaminants of concern and of emerging concern, or COC’s, from the Site into groundwater. Artesian Water has found in groundwater that Artesian Water uses for public potable water supply certain COC’s that the Remedy
is designed to address, as a result of which Artesian has incurred, and potentially will incur additional, capital and operating costs to treat the groundwater to meet applicable drinking water standards. The Remedy includes requirements that are
directly linked to Artesian’s continued operation of the treatment plant associated with groundwater around the Site.
As set forth in the Settlement Agreement, Artesian Water shall have access to financial assurances that the Percentage Settlors have provided, or will
provide, to the USEPA in connection with the Consent Decree governing the implementation of the Remedy. In addition, the Trust shall reimburse Artesian Water for past capital and operating costs, totaling approximately $10.0 million, with
approximately $2.5 million due by August 18, 2022, within 30 days after the Court’s July 19, 2022 approval of the Consent Decree. The remaining $7.5 million will be payable in three equal installments annually on the anniversary date of the Court’s
approval of the Consent Decree. In addition, the Trust shall reimburse Artesian Water for documented reasonable and necessary capital and operating costs after July 1, 2021 that Artesian Water incurs to treat Site-related COC’s. Any reimbursements
Artesian Water receives from the Trust shall be subject to final determination by the DEPSC as to the appropriate regulatory rate-making treatment. The Trust’s reimbursement of such costs shall end if and when, based upon testing information from the
Trust’s Remedy facilities and Artesian Water’s facilities, treatment of Site-related COC’s is no longer necessary for Artesian Water to meet the treatment levels that Artesian Water chooses to not exceed in water it distributes to the general public
throughout its service territory to provide a margin of safety in complying with applicable drinking water standards.
31
Table of Contents
Text extracted from the filing as submitted to EDGAR. Formatting, tables and exhibits are simplified for reading; the original document is authoritative for anything you rely on.