3 unchanged sentences
During the 12 months ended December 31, 2021, the high and low price for each commodity are set forth in the following table:
−Removed: Metal Low Price for 2020 Date High Price for 2020 Date
−Removed: Gold (per ounce) $1,474 March 19, 2020 $2,067 August 6, 2020
−Removed: Silver (per ounce) $12.00 March 19, 2020 $28.89 September 1, 2020
−Removed: Zinc (per pound) $0.82 March 24, 2020 $1.29 December 18, 2020
−Removed: Lead (per pound) $0.71 March 24, 2020 $0.95 December 9, 2020
+Added: Metal High Price for 2021 Date Low Price for 2021 Date
+Added: Gold (per ounce) $1,943 January 4, 2021 $1,684 March 30, 2021
+Added: Silver (per ounce) $29.59 February 1, 2021 $21.53 September 30, 2021
+Added: Zinc (per pound) $1.74 October 15, 2021 $1.15 February 2, 2021
+Added: Lead (per pound) $1.13 August 18, 2021 $0.86 March 17, 2021
Gold, silver, zinc and lead prices are affected by many factors beyond the Company’s control, including U.S.
−Removed: dollar strength or weakness, speculation, global currency values, the price of products that incorporate gold, silver, zinc or lead, global and regional demand and production, political and economic conditions and other factors.
+Added: dollar strength or weakness, speculation, global currency values, global and regional demand and production, political and economic conditions and other factors.
In addition, Exchange Traded Funds (“ETFs”), which have substantially facilitated the ability of large and small investors to buy and sell precious metals and base metals, have become significant holders of gold, silver, zinc and lead.
−Removed: Gold and silver prices are also affected by prevailing interest rates and returns on other asset classes, expectations regarding inflation and governmental decisions regarding precious metals stockpiles.
+Added: Gold and silver prices are also affected by prevailing interest rates and returns on other asset classes, expectations regarding inflation and governmental monetary decisions regarding central bank holdings.
Because we derive a significant portion of our revenues from sales of these metals, our results of operations and cash flows will fluctuate as the prices of these metals change.
3 unchanged sentences
Operating costs at our mines are also affected by the price of input commodities, such as fuel, electricity, labor, chemical reagents, explosives, steel and concrete.
−Removed: Prices for these input commodities are volatile and can fluctuate due to conditions that are difficult to predict, including global competition for resources, currency fluctuations, consumer or industrial demand and other factors.
+Added: Prices for these input commodities are volatile and can fluctuate due to conditions that are difficult to predict, including global competition for resources, inflation, currency fluctuations, consumer or industrial demand and other factors.
Continued volatility in the prices of commodities and other supplies we purchase could lead to higher costs, which would adversely affect results of operations and cash flows.
6 unchanged sentences
This volatility in the price of our common stock did not, in our view, reflect any significant change in our business or results of operations during the same period.
−Removed: The estimation of mineral reserves and mineralized material is imprecise and depends upon subjective factors.
−Removed: Estimated mineral reserves and mineralized material may not be realized in actual production.
+Added: The estimation of mineral reserves and mineral resources is imprecise and depends upon subjective factors.
+Added: Estimated mineral reserves and mineral resources may not be realized in actual production.
Our results of operations and financial position may be adversely affected by inaccurate estimates.
−Removed: The mineral reserve and mineralized material figures presented in our public filings are estimates made by our technical personnel and independent mining consultants with whom we contract.
−Removed: Mineral reserve and mineralized material estimates are a function of geological and engineering analyses that require us to make assumptions about production costs, recoveries and gold, silver, zinc and lead market prices.
−Removed: Mineral reserve and mineralized material estimation is an imprecise and subjective process.
+Added: The mineral reserve and mineral resource figures presented in our public filings are estimates made by our technical personnel and independent mining consultants with whom we contract.
+Added: Mineral reserve and mineral resource estimates are a function of geological and engineering analyses that require us to make assumptions about production costs, recoveries and gold, silver, zinc and lead market prices.
+Added: Mineral reserve and mineral resource estimation is an imprecise and subjective process.
The accuracy of such estimates is a function of the quality of available data and of engineering and geological interpretation, judgment and experience.
−Removed: Assumptions about gold, silver, zinc and lead market prices are subject to
−Removed: great uncertainty as those prices fluctuate widely.
−Removed: Declines in the market prices of gold, silver, zinc or lead may render mineral reserves and mineralized material containing relatively lower grades of mineralization uneconomic to exploit, and we may be required to reduce mineral reserve and mineralized material estimates, discontinue development or mining at one or more of our properties or write down assets as impaired.
−Removed: Should we encounter mineralization or geologic formations at any of our mines or projects different from those predicted, we may adjust our mineral reserve and mineralized material estimates and alter our mining plans.
+Added: Assumptions about gold, silver, zinc and lead market prices are subject to great uncertainty as those prices fluctuate widely.
+Added: Declines in the market prices of gold, silver, zinc or lead may render mineral
+Added: reserves and mineral resources containing relatively lower grades of mineralization uneconomic to exploit, and we may be required to reduce mineral reserve and mineral resource estimates, discontinue development or mining at one or more of our properties or write down assets as impaired.
+Added: Should we encounter mineralization or geologic formations at any of our mines or projects different from those predicted, we may adjust our mineral reserve and mineral resource estimates and alter our mining plans.
Updates to our mining plans or new or updated technical or geological information may also impact anticipated metal recovery rates.
−Removed: Any of these adjustments may adversely affect actual operating performance, production and financial condition, results of operations and cash flows.
+Added: Any of these adjustments may adversely affect actual operating performance, production, financial condition, results of operations and cash flows.
A significant delay or disruption in sales of concentrates or doré as a result of the unexpected disruption in services provided by smelters or refiners or other third parties could have a material adverse effect on our results of operations.
1 unchanged sentence
Access to refiners and smelters on economical terms is critical to our ability to sell our products to buyers and generate revenues.
−Removed: We have existing agreements with refiners and smelters, some of which operate their refining or smelting facilities outside the United States, and we believe we currently have contractual arrangements with a sufficient number of refiners and smelters so that the loss of any one refiner or smelter would not significantly or materially impact our operations or our ability to generate revenues.
−Removed: Nevertheless, services provided by a refiner or smelter may be disrupted by new or increased tariffs, duties or other cross-border trade barriers, the bankruptcy or insolvency of one or more refiners or smelters or the inability to agree on acceptable commercial or legal terms with a refiner or smelter.
−Removed: Such an event or events may disrupt an existing relationship with a refiner or smelter or result in the inability to create a contractual relationship with a refiner or smelter, which may leave us with limited, uneconomical or no access to refining or smelting services for short or long periods of time.
+Added: We have existing agreements with refiners and smelters, some of which operate their refining or smelting facilities outside the United States.
+Added: We believe we currently have contractual arrangements with a sufficient number of refiners and smelters so that the loss of any one refiner or smelter would not significantly or materially impact our operations or our ability to generate revenues.
+Added: Nevertheless, services provided by a refiner or smelter may be disrupted by new or increased tariffs, duties or other cross-border trade barriers, shipping delays, the bankruptcy or insolvency of one or more refiners or smelters or the inability to agree on acceptable commercial or legal terms with a refiner or smelter.
+Added: Such an event or events may disrupt an existing relationship with a refiner or smelter or result in the inability to create (or the necessity to terminate) a contractual relationship with a refiner or smelter, which may leave us with limited, uneconomical or no access to refining or smelting services for short or long periods of time.
Epidemics, pandemics or natural disasters may also impact refiners, smelters or other third parties with whom we have contractual arrangements or have an indirect effect on our ability to obtain refining, smelting or other third-party services.
3 unchanged sentences
There are significant hazards associated with mining activities, some of which may not be fully covered by insurance.
−Removed: The mining business is subject to risks and hazards, including environmental hazards, industrial accidents, the encountering of unusual or unexpected geological formations, cave-ins, flooding, earthquakes and periodic interruptions due to inclement or hazardous weather conditions or machine failure, such as the failure of the secondary crusher in Rochester’s new crushing circuit in 2019, which impacted crushing rates.
+Added: The mining business is subject to risks and hazards, including environmental hazards, industrial accidents, the encountering of unusual or unexpected geological formations, cave-ins, flooding, earthquakes and periodic interruptions due to inclement or hazardous weather conditions or machine failure.
These occurrences could result in damage to, or destruction of, mineral properties or production facilities, personal injury or death, environmental damage, reduced production and delays in mining, asset write-downs, monetary losses and possible legal liability.
5 unchanged sentences
Our future growth will depend upon our ability to expand existing mines and develop and start-up new mines, either through exploration at existing properties or by acquisition of other mining companies or properties.
−Removed: Because mines have limited lives based on proven and probable mineral reserves, our ability to achieve significant additional growth in revenues and cash flows will depend upon success in further developing and expanding existing properties and the opportunistic acquisition or development and start-up of new mining properties, such as the Silvertip mine, the Sterling/Crown project and the Lincoln Hill project and related assets.
+Added: Because mines have limited lives based on proven and probable mineral reserves, our ability to achieve significant additional growth in revenues and cash flows will depend upon success in further developing and expanding existing properties and the opportunistic acquisition or development and start-up of new mining properties, such as the Silvertip development property, the Sterling/Crown project and the Lincoln Hill project and related assets.
While initial development of the Palmarejo, Rochester, and Kensington mines has been substantially completed, development work continues to expand these mines while leveraging existing infrastructure.
−Removed: Palmarejo completed open pit mining several years ago and evolved to be an underground-only operation, developing two new underground mining
−Removed: At Rochester, a crushing circuit using high pressure grinding roll (“HPGR”) technology was commissioned in 2019, and, in 2020, we obtained permitting for, and began construction of POA 11, which is a significant additional expansion, including the construction of a new leach pad, a crushing facility equipped with two HPGR units, processing facilities and related infrastructure to support the extension of Rochester’s mine life.
+Added: Palmarejo completed open pit mining several years ago and evolved to be an underground-only operation, developing new underground mining operations.
+Added: At Rochester, a crushing circuit using high pressure grinding roll (“HPGR”) technology was commissioned in 2019, and, in 2020, we obtained permitting for, and began construction of POA 11, which is a significant additional expansion, including the
+Added: construction of a new leach pad, a crushing facility equipped with two HPGR units and a prescreen, processing facilities and related infrastructure to support the extension of Rochester’s mine life.
At Kensington, we completed development and commenced commercial production from a new deposit in 2018 and are currently seeking to amend our operating permit to allow for an additional 10 years of mine life by providing for expanded tailings and waste rock storage, increased mill throughput, enhanced infrastructure and other benefits (“POA 1”).
8 unchanged sentences
and insolvency or other financial difficulty encountered by a contractor which results in a delay in services or termination of a contract with the contractor.
−Removed: We cannot provide assurance that we will be able to successfully expand or extend the lives of existing mining operations, and a completed project may not yield the anticipated operational or financial benefit, any of which may have a material negative impact on returns on invested capital, operating costs or cash flows.
−Removed: In addition, we acquired several mining properties in recent years, namely, the Sterling/Crown project, the Lincoln Hill project and related assets and the Silvertip mine.
−Removed: We cannot guarantee that we will be able to successfully develop and start-up new mining properties, restart mining and processing activities at the Silvertip mine or acquire additional mining properties on favorable economic terms or at all.
+Added: Expected project benefits are based on estimates of a variety of key factors, including mineral reserves and resources, grade, recovery rates, and operating costs among others.
+Added: However, achieving results in line with those estimates is subject to risks and uncertainties such as variability in grade, recovery rates and cost inputs.
+Added: In 2021, Rochester experienced lower than expected silver recovery rates from its HPGR-crushed ore, which negatively impacted production, costs and cash flow.
+Added: We cannot provide assurance that we will be able to successfully expand or extend the lives of existing mining operations, and a completed project may not yield the anticipated operational or financial benefit, such as expected availability, throughput, metal recovery rates, concentrate quality, unit costs, operating margin and/or cash flows, any of which may have a material negative impact on returns on invested capital, operating costs or cash flows.
+Added: In addition, we acquired several mining properties in recent years, namely, the Sterling/Crown project, the Lincoln Hill project and related assets and the Silvertip development property.
+Added: We cannot guarantee that we will be able to successfully develop and start-up new mining properties, restart mining and processing activities at the Silvertip development property or acquire additional mining properties on favorable economic terms or at all.
We regularly evaluate and engage in discussions or negotiations regarding acquisition opportunities.
3 unchanged sentences
COVID-19, which was declared a pandemic by the World Health Organization on March 11, 2020, poses a material risk to our business and operations.
−Removed: If a significant portion of our workforce becomes unable to work or travel to our operations due to illness or state or federal government restrictions (including travel restrictions and “shelter-in-place” and similar orders restricting certain activities that may be issued or extended by authorities), we may be forced to reduce or suspend operations at one or more of our mines, which occurred at our Palmarejo complex in the second quarter of 2020 and at the Kensington mine in the third quarter of 2020, which could reduce production, limit exploration activities and development projects and impact liquidity and financial results.
−Removed: In addition, we have implemented several initiatives to protect the health and safety of our employees, contractors and communities during this pandemic, including COVID-19 testing, pre-shift quarantine requirements, site access symptom checks, contact tracing technology and procuring additional disinfectant and sanitation products and personal protective equipment for our employees, among others, some of which may result in additional costs to us.
−Removed: For example, we continue to require all employees who travel to the Kensington mine to submit to a quarantine before traveling to the mine and a testing protocol before travel to Juneau, Alaska, before traveling from Juneau to the mine and while at the mine site.
−Removed: We believe this is an important step to protect the health and safety of all workers who stay at the Kensington camp, although it has required changes to worker scheduling and is expected to result in higher labor costs due to additional overtime pay and pay during the quarantine period.
+Added: If a significant portion of our workforce becomes unable to work or travel to our operations due to illness or state or federal government restrictions (including travel restrictions and “shelter-in-place” and similar orders restricting certain activities that may be issued or extended by authorities), we may be forced to reduce or suspend operations at one or more of our mines, which could reduce production, limit exploration activities and development projects and impact liquidity and financial results.
+Added: In addition, we have implemented several initiatives to protect the health and safety of our employees, contractors and communities during this pandemic, including COVID-19 testing, site access symptom checks, contact tracing technology and procuring additional disinfectant and sanitation products and personal protective equipment for our employees, among others, some of which have and may result in additional costs to us.
Illnesses or government restrictions, including the closure of national borders, related to COVID-19 also may disrupt the supply of raw goods, equipment, supplies and services upon which our operations rely.
−Removed: We also continue to monitor legislative initiatives in the U.S., Mexico and Canada to provide relief to businesses impacted by COVID-19 to determine their potential impacts or benefits (if any) to our business.
−Removed: The refiners and smelters upon which we rely to refine and process and, in some cases, purchase the gold and silver doré and gold, silver, zinc and lead concentrate produced by our mines, are also subject to these risks and may be required to reduce or suspend operations, which could impact our ability to sell our products to buyers and generate revenues.
−Removed: For example, in the first quarter of 2020, Argor-Heraeus, a Swiss refiner which provides refining services to several of our mines, announced that it was temporarily suspending operations in response to a government order.
−Removed: Following the temporary suspension, Argor-Heraeus recommenced operations.
−Removed: We may be subject to litigation if one or more employees contract COVID-19 at work or litigation initiated by stockholders who view decisions by the Board of Directors or management as inconsistent with duties to the Company under Delaware law or who may assert claims under federal securities laws.
+Added: We also continue to monitor legislative initiatives in the U.S., Mexico and Canada related to COVID-19 to determine their potential impacts or benefits (if any) to our business.
+Added: Third parties with whom we conduct business, including the refiners and smelters that, process and, in some cases, purchase the gold and silver doré and gold, silver, zinc and lead concentrate produced by our mines, are also subject to these risks and may be required to reduce or suspend operations, which could impact our ability to conduct our operations, advance exploration, development and expansion projects, sell our products and generate revenues.
+Added: We may be subject to litigation if one or more employees or contractors contract COVID-19 at work or litigation initiated by stockholders who view decisions by the Board of Directors or management as inconsistent with duties to the Company under Delaware law or who may assert claims under federal securities laws.
We understand that, as indicated by sharp increases in average premiums for director and officer insurance policies in recent months, insurers expect increased litigation relating to COVID-19.
The jurisdictions in which we operate have and may in the future continue to encounter financial difficulties resulting from one or both of lower tax revenue and new and increased costs related to COVID-19.
−Removed: As a result, national, state or local governments may seek to raise existing taxes or introduce new taxes that affect our business, which may adversely affect our business and financial results.
−Removed: For example, the state legislature of Nevada, where the Rochester mine, Sterling/Crown project and Lincoln Hill project are located, in response to a significant loss of tourism and gaming revenue during 2020, is considering an increase to the existing Nevada Net Proceeds Tax (“NNPT”) on net revenue, or conversion to a tax on gross proceeds, derived from mining.
−Removed: Any increase to the NNPT or conversion to a gross proceeds tax requires approval of two-thirds of members of both legislative houses in two consecutive legislative sessions followed by majority approval of Nevada voters on a statewide ballot.
−Removed: In addition, there have been recent proposals by elected officials in Mexico for significant increases in mining taxes, although it is unclear whether those proposals will result in legislation.
−Removed: To the extent the COVID-19 pandemic adversely affects our business and financial results, it may also have the effect of heightening many of the other risks described in this “Risk Factors” section, such as those relating to our operations and indebtedness and financing.
+Added: As a result, national, state or local
+Added: governments may seek to raise existing taxes or introduce new taxes that affect our business, which may adversely affect our business and financial results.
+Added: For example, in Nevada, where the Rochester mine, Sterling/Crown project and Lincoln Hill project are located, in response to a significant loss of tourism and gaming revenue during 2020, in June 2021 the Governor signed into law a new excise tax on gross proceeds derived from mining gold and silver.
+Added: To the extent the COVID-19 pandemic adversely affects our business and financial results, it may also have the effect of heightening many of the other risks described in this “Risk Factors” section as well as those contained in the 2020 10-K, such as those relating to our operations and indebtedness and financing.
Because of the highly uncertain and dynamic nature of events relating to the COVID-19 pandemic, it is not currently possible to estimate the full impact of the pandemic on our business.
1 unchanged sentence
We may be unable to successfully integrate and may not realize the expected benefits of recent or future acquisitions.
−Removed: There can be no assurance that the anticipated benefits of recent acquisitions (including the Silvertip mine and the Sterling/Crown and Lincoln Hill projects) or any future acquisition, will be realized on the originally anticipated timeline or at all.
+Added: There can be no assurance that the anticipated benefits of recent acquisitions (including the Silvertip development property and the Sterling/Crown and Lincoln Hill projects) or any future acquisition, will be realized on the originally anticipated timeline or at all.
The success and the ability to realize the anticipated benefits of any acquisition will depend upon our ability to effectively manage the integration, performance and operations of entities or properties we acquire.
The process of managing acquired businesses or assets may involve unforeseen challenges and may require a disproportionate amount of our resources, which may divert focus and resources from other strategic opportunities and/or from operational matters during this process.
−Removed: As an example, the ramp up of the Silvertip mine, acquired in late 2017, was slower and less profitable than originally anticipated, due primarily to more significant mill availability and maintenance challenges than were anticipated at the time Silvertip was acquired.
−Removed: Silvertip temporarily suspended mining and processing activities (unrelated to COVID-19) in February 2020 due to the foregoing reasons as well as a significant decrease in the prices of lead and zinc and a significant increase in treatment costs for lead and zinc.
+Added: As an example, the ramp up of the Silvertip development property, acquired in late 2017, was slower and less profitable than originally anticipated, due primarily to more significant mill availability and maintenance challenges than were anticipated at the time Silvertip was acquired.
In addition to the above, any acquisition would be accompanied by risks, including:
4 unchanged sentences
• processing facilities may not operate as well as anticipated, and may require significant maintenance, downtime and capital investment, such as the mill at Silvertip;
−Removed: • difficulties integrating and assimilating the operations and personnel of any acquired companies, realizing anticipated synergies and maximizing the financial and strategic position of the combined enterprise, and maintaining uniform standards, policies and controls across the organization;
+Added: • difficulties integrating and assimilating the operations and personnel of any acquired companies and supporting expanded operations, realizing anticipated synergies and maximizing the financial and strategic position of the combined enterprise, and maintaining uniform standards, policies and controls across the organization;
• difficulties or loss of social license to operate resulting from failure of efforts to establish positive relationships and/or agreements with local communities or local indigenous people;
−Removed: • the acquired business or assets may have unknown liabilities which may be significant.
+Added: • the acquired business or assets may have significant liabilities, such as environmental liabilities, or significant capital expenditures that we failed to discover or have underestimated.
We cannot predict the impact of future acquisitions on the price of our common stock or assure that we will be able to obtain necessary acquisition or development financing on acceptable terms or at all.
−Removed: Unprofitable acquisitions, or additional
−Removed: indebtedness or issuances of securities in connection with such acquisitions or any future mine development, may negatively affect our results of operations.
−Removed: Finally, our systems, procedures and controls may be inadequate to support the expansion of our operations resulting from an acquisition or development of a new mine.
−Removed: Our future operating results could be affected by the ability of our officers and key employees to manage changing business conditions and integrate an acquired business or new operation into Coeur.
−Removed: There may also be liabilities, such as environmental liabilities, or significant capital expenditures that we failed to discover or have underestimated in connection with any acquisition or development.
−Removed: Any such liabilities or capital expenditure requirements could have a material adverse effect on our business, financial condition or future prospects.
+Added: Unprofitable acquisitions, or additional liabilities, indebtedness or issuances of securities in connection with such acquisitions or any future mine development, may negatively affect our results of operations.
Significant investment risks and operational costs are associated with exploration and development activities.
2 unchanged sentences
Substantial expenditures are required to establish ore reserves, to extract metals from ores and, in the case of new properties, to construct mining and processing facilities.
−Removed: Our plans include several significant projects to construct or upgrade mining and processing facilities at our existing mining operations, including the POA 11 expansion project at Rochester and POA 1 planned mine-life extension at Kensington, and future plans to develop the Sterling/Crown and Lincoln Hill projects.
−Removed: These projects can take up to several months or years to complete, are complex and require significant capital expenditures.
−Removed: For example, the capital costs associated with the POA 11 expansion project in 2021 through 2023 are anticipated to be $396.8 million.
−Removed: These projects are subject to significant risks, including delays, extreme weather events, unexpected increases in the cost of required materials, and disputes with third-party providers of materials, equipment or services, and a completed project may not yield the anticipated operational or financial benefit, any of which may have a material negative impact on returns on invested capital, operating costs or cash flows.
+Added: Our plans include several significant projects to construct or upgrade mining and processing facilities at our existing mining operations, including the POA 11 expansion project at Rochester and the POA 1 planned mine life extension at Kensington, and future plans to develop the Sterling/Crown and Lincoln Hill projects.
+Added: These projects can take up to several
+Added: months or years to complete, are complex and require significant capital expenditures.
+Added: These projects are subject to significant risks described in this Item, any of which may have a material negative impact on returns on invested capital, operating costs or cash flows.
Mineral exploration involves many risks and is frequently unproductive.
14 unchanged sentences
The exact effect of these factors cannot be accurately predicted, but the combination may result in not receiving an adequate return on invested capital.
−Removed: In addition, exploration projects, such as the La Preciosa, Sterling/Crown and Lincoln Hill projects may have no operating history upon which to base estimates of future operating costs and capital requirements.
+Added: In addition, exploration projects, such as the Sterling/Crown and Lincoln Hill projects may have no operating history upon which to base estimates of future operating costs and capital requirements.
Exploration project items such as estimates of reserves, metal recoveries and cash operating costs are to a large extent based upon the interpretation of geologic data, obtained from a limited number of drill holes and other sampling techniques, and feasibility studies.
8 unchanged sentences
We conduct a review of the financial performance of our mines in connection with the preparation of our financial statements for each reported period and determine whether any triggering events are indicated.
−Removed: For example, during the fourth quarter of 2019, we performed a comprehensive analysis of the Silvertip property and determined that indicators of impairment existed, primarily as a result of continued deterioration in zinc and lead market conditions as well as ongoing challenges related to the processing facility.
−Removed: As a result of the impairment indicators, a
−Removed: recoverability test was performed and we concluded that the carrying value of the long-lived assets for the Silvertip property was impaired, and a non-cash impairment charge of $250.8 million was recorded during the fourth quarter of 2019.
−Removed: The write-down was allocated between Property, plant and equipment, net , Mining properties, net and Other non-current assets , in the amounts of $43.6 million, $201.5 million and $5.7 million, respectively.
−Removed: See Note 4 -- Impairment of Long-lived Assets and 16 -- Fair Value Measurements for additional detail of the assumptions used in the determination of the fair value of the long-lived assets tested for impairment.
−Removed: In prior years, our assessment of the recoverability of our long-lived assets resulted in other write-downs in our Consolidated Statement of Comprehensive Income (Loss) and reduced the carrying value of Mining properties and Property, plant, and equipment on our balance sheet.
−Removed: See Note 2 -- Summary of Significant Accounting Policies in the notes to the Consolidated Financial Statements for further detail.
+Added: For example, during the fourth quarter of 2019, we performed a comprehensive analysis of the Silvertip property and determined that indicators of impairment existed, and we ultimately concluded that the carrying value of the long-lived assets for the Silvertip property was impaired, and a non-cash impairment charge of $250.8 million was recorded during the fourth quarter of 2019.
If there are further significant and sustained declines in relevant metal prices, or if we fail to control production and operating costs or realize the mineable ore reserves at its mining properties, we may terminate or suspend mining operations at one or more of its properties.
7 unchanged sentences
These risks include the possible unilateral cancellation or forced renegotiation of contracts in which we, directly or indirectly, may have an interest, unfavorable changes in foreign laws and regulations, royalty and tax increases (including taxes associated with the import or export of goods), risks associated with the value-added tax (“VAT”) and income tax refund recovery and collection process, erection of trade barriers, including tariffs and duties, claims by governmental entities or indigenous communities, expropriation or nationalization of property and other risks arising out of foreign sovereignty over areas in which our operations are conducted.
−Removed: As an example, as disclosed in Note 21 -- Commitments and Contingencies to the Consolidated Financial Statements, we are currently engaged in efforts to recover VAT paid to the Mexican government that is owed to Coeur associated with Coeur Mexicana’s prior royalty agreement, including through ongoing litigation.
−Removed: In addition, in November 2020 the President of Mexico introduced legislation that would limit outsourcing by companies in Mexico of certain services.
−Removed: If enacted, the proposed law is expected to result in increased costs to our operations in Mexico, including additional tax expense, increased compensation to certain employees and costs associated with restructuring our Mexican subsidiaries and employment arrangements to comply with the new law.
+Added: As an example, as disclosed in Note 20 -- Commitments and Contingencies to the Consolidated
+Added: Financial Statements, we are currently engaged in efforts to recover VAT paid to the Mexican government that is owed to Coeur associated with Coeur Mexicana’s prior royalty agreement, including through ongoing litigation and potential international arbitration.
+Added: While the Company believes that it remains legally entitled to be refunded the full amount of the VAT receivable and intends to rigorously continue its VAT recovery efforts, based on the continued failure to recover the VAT receivable and recent unfavorable Mexican court decisions, the Company determined to write down the carrying value of the VAT receivable of $26.0 million at September 2021.
The right to import and export gold, silver, zinc and lead may depend on obtaining certain licenses and quotas, which could be delayed or denied at the discretion of the relevant regulatory authorities, or could become subject to new taxes, tariffs or duties imposed by U.S.
20 unchanged sentences
Any such occurrences could materially and adversely affect our financial condition, results of operations and cash flows.
−Removed: Like any mining company, our mining assets are subject to geotechnical and hydrological risks, and a related incident could materially and adversely impact our production, profitability and financial condition and the value of our common stock.
+Added: Our mining assets are subject to geotechnical and hydrological risks, and a related incident could materially and adversely impact our production, profitability and financial condition and the value of our common stock.
Our mining assets are subject to geotechnical and hydrological risks which could impact the structural integrity of our mines, stockpiles, leach pads and tailings storage facilities.
1 unchanged sentence
Geotechnical and hydrological instabilities can be difficult to predict and are often affected by risks and hazards outside of our control, such as severe weather and considerable rainfall, which may lead to periodic floods, mudslides, wall instability and seismic activity, which may result in slippage of material.
−Removed: Waste rock in the form of tailings generated as a by-product of processed ore is produced at the Kensington, Palmarejo, and Silvertip Mines.
+Added: Waste rock in the form of tailings generated as a by-product of processed ore is produced at the Kensington and Palmarejo Mines.
We place tailings into engineered containments, underground as structural backfill, and as a dry stack material.
−Removed: In response to several recent tailings dam failures unrelated to our operations that have involved loss of life and resulted in severe property and environmental ecosystem damage, we completed a comprehensive review of our tailings dams and operational practices to characterize our risk profile.
+Added: In response to several recent tailings dam failures unrelated to our operations that have involved loss of life and resulted in severe property and environmental ecosystem damage, we completed a comprehensive review of our tailings dams
+Added: and operational practices to characterize our risk profile.
We concluded that our tailings dams represent a low exposure risk profile for several reasons, including that our tailings dams were constructed using construction methods recognized in the industry as the most stable tailings dam design using high strength and chemically stable rock in construction.
2 unchanged sentences
The failure of a tailings dam or tailings storage facility at one of our mine sites could result in severe, and in some cases catastrophic, property and environmental damage and loss of life.
−Removed: Geotechnical or hydrological failures could result in limited or restricted access to mine sites, suspension of operations, government investigations, lawsuits filed by parties who suffer injuries or property damage from such events, increased monitoring costs, remediation costs, loss of mineralized material and other impacts, which could have a material adverse effect on our results of operations and financial position as well as the value of our common stock.
+Added: Geotechnical or hydrological failures could result in limited or restricted access to mine sites, suspension of operations, government investigations, lawsuits filed by parties who suffer injuries or property damage from such events, increased monitoring costs, remediation costs, loss of mineral reserves and resources and other impacts, which could have a material adverse effect on our results of operations and financial position as well as the value of our common stock.
Our estimates of future production, costs, expenditures and financial results are imprecise, depend upon subjective factors, may not be realized in actual production and such estimates speak only as of their respective dates.
2 unchanged sentences
Neither our independent registered public accounting firm nor any other independent expert or outside party compiles or examines these forward-looking statements and, accordingly, do not express any opinion or any other form of assurance on these estimates and projections.
−Removed: Estimates and projections are made by our management and technical personnel and are qualified by, and subject to the assumptions contained or referred in the filing, release or presentation in which they are made, including assumptions about the availability, accessibility, sufficiency and quality of mineralized material, our costs of production, the market prices of gold, silver, zinc and lead, our ability to sustain and increase production levels, the ability to produce and sell marketable concentrates and doré and related treatment and refining charges, the sufficiency of our infrastructure, the performance of our personnel and equipment, our ability to maintain and obtain mining interests and permits, the state of government and community relations, and our compliance with existing and future laws and regulations.
+Added: Estimates and projections are made by our management and technical personnel and are qualified by, and subject to the assumptions contained or referred in the filing, release or presentation in which they are made, including assumptions about the availability, accessibility, sufficiency and quality of mineralization, recovery rates, our costs of production, the market prices of gold, silver, zinc and lead, our ability to sustain and increase production levels, the ability to produce and sell marketable concentrates and doré and related treatment and refining charges, the sufficiency of our infrastructure, the performance of our personnel and equipment, our ability to maintain and obtain mining interests and permits, the state of government and community relations, and our compliance with existing and future laws and regulations.
We sometimes state possible outcomes as high and low ranges which are intended to provide a sensitivity analysis as variables are changed but are not intended to represent that actual results could not fall outside of the suggested ranges.
8 unchanged sentences
As of December 31, 2021, contracts with respect to 132,000 ounces of gold were outstanding.
−Removed: See Note 17 — Derivative Financial Instruments in the notes to the Condensed Consolidated Financial Statements.
+Added: See Note 16 — Derivative Financial Instruments in the notes to the Consolidated Financial Statements.
The use of derivative instruments can expose us to risk of an opportunity loss and may also result in significant mark-to-market fair value adjustments, which may require us to post cash or other collateral or have a material adverse impact on reported financial results.
Our exposure may be particularly acute for our derivative instruments accounted for as cash flow hedges, because those contracts are cash net settled on a monthly basis.
−Removed: The ceiling on the gold ounces covered by the price risk management contracts described above, representing the highest price we could realize for those ounces under outstanding contracts, averages approximately $1,875 per ounce for 2021 production and $2,030 per ounce for 2022 production.
+Added: The ceiling on the gold ounces covered by the price risk management contracts described above, representing the highest price we could realize for those ounces under outstanding contracts, averages approximately $2,038 per ounce for 2022 production.
The price ceiling may be lower than actual spot gold prices at the time of sale under those contracts.
2 unchanged sentences
In the event of nonperformance in connection with a contract, we could be exposed to a loss of value for that contract.
−Removed: We are dependent upon information technology systems, which are subject to cybersecurity incidents, disruption, damage, failure and risks associated with implementation and integration.
−Removed: Our information technology systems used in our operations are subject to disruption, damage or failure from a variety of sources, including, without limitation, computer viruses, security breaches, cyberattacks, natural disasters and defects in design.
+Added: We are dependent upon information technology systems, which are subject to cybersecurity incidents, disruption, damage, failure and other risks associated with implementation and integration.
+Added: Our information technology systems used in our operations are subject to disruption, damage or failure from a variety of sources, including, without limitation, computer viruses, security breaches, cyberattacks, natural disasters and defects in
Cybersecurity incidents, in particular, are evolving and include, but are not limited to, malicious software, attempts to gain unauthorized access to data or machines and equipment, and other electronic security breaches that could lead to disruptions in systems, unauthorized release of confidential or otherwise protected information, the corruption of data or the disabling, misuse or malfunction of machines and equipment.
1 unchanged sentence
However, given the unpredictability of the timing, nature and scope of information or operational technology disruptions, we could potentially be subject to production downtimes, operational delays, operating accidents, the compromising of confidential or otherwise protected information, destruction or corruption of data, security breaches, other manipulation or improper use of our systems and networks or financial losses from remedial actions, any of which could have a material adverse effect on cash flows, financial condition or results of operations.
−Removed: We face increased cybersecurity risks due to the COVID-19 pandemic.
−Removed: For example, a portion of our workforce is working remotely to facilitate social distancing, and these employees may transmit data using unsecured internet connections despite training advising of those risks.
−Removed: In addition, our employees have faced increases in phishing and malware attacks and socially engineered cyberattacks which, in some cases, attempt to use the circumstances of the COVID-19 pandemic to gain unauthorized access to our information technology systems.
We could also be adversely affected by system or network disruptions if new or upgraded information technology systems are defective, not installed properly or not properly integrated into operations.
12 unchanged sentences
Continuous production and mine development is dependent on our ability to acquire and maintain water rights and claims and to defeat claims adverse to current water uses in legal proceedings.
−Removed: Although each of our operating mines currently has sufficient water rights and claims to cover its operational demands, we cannot predict the potential outcome of pending or future legal proceedings relating to water rights, claims and uses.
−Removed: Water shortages may also result from weather or environmental and climate impacts out of our control.
+Added: Although each of our operating mines currently has sufficient water rights and claims to cover its operational demands, we cannot predict the potential outcome of pending or future legal proceedings relating to enforcement of water rights, claims and uses, or potential pressure from other users of water, government agencies and officials, and/or non-governmental organizations to limit the amount of water made available to or used for mining activities, regardless of legally valid water rights.
+Added: Water shortages may also result from weather or environmental and climate impacts outside of our control.
Shortages in water supply could result in production and processing interruptions.
In addition, the scarcity of water in certain regions could result in increased costs to obtain sufficient quantities of water to conduct our operations.
−Removed: The loss of some or all water rights, in whole or in part, or ongoing shortages of water to which we have rights or significantly higher costs to obtain sufficient quantities of water (or the failure to procure sufficient quantities of water) could result in our inability to maintain production at current or expected levels, require us to curtail or shut down mining production and could prevent us from pursuing expansion or development opportunities, which could adversely affect our results of operations and financial condition.
−Removed: Laws and regulations may be introduced in some jurisdictions in which we operate which could also limit access to sufficient water resources, thus adversely affecting our operations.
+Added: The loss of some or all water rights, ongoing litigation to enforce existing water rights, ongoing shortages of water to which we have rights and/or significantly higher costs to obtain sufficient quantities of water could result in our inability to maintain production at current or expected levels, require us to curtail or shut down mining operations and could prevent us from pursuing expansion or development opportunities, which could adversely affect our results of operations and financial condition.
+Added: Laws and regulations may be introduced in some jurisdictions in which we operate which could also limit access to sufficient water resources, adversely affecting our existing operations or our expansion or development plans.
We may not be able to recognize the benefits of deferred tax assets.
4 unchanged sentences
To the extent that future cash flows and taxable income differ significantly from estimates, our ability to realize deferred tax assets could be impacted.
−Removed: Additionally, future changes in tax laws could limit our ability to obtain the future benefits represented by our deferred tax assets.
−Removed: Deferred tax assets in the United States are also subject to limitation if we experience a change in stock ownership in accordance with Section 382 of the Internal Revenue Code.
−Removed: Management has determined that we experienced ownership changes, for purposes of Section 382, during 2002, 2003, 2007, and 2015.
−Removed: Based on management’s calculations, we do not expect any of our deferred tax assets to expire unused as a result of the Section 382 annual limitations.
−Removed: However, the annual limitations may impact the timeframe over which the net operating loss carryforwards can be used, potentially impacting cash tax liabilities in a future period.
+Added: Additionally, future changes in tax laws could limit our ability to obtain the future benefits represented by our deferred tax assets and annual limitations may impact the timeframe over which the net operating loss carryforwards can be used, potentially impacting cash tax liabilities in a future period.
RISKS RELATED TO INDEBTEDNESS AND FINANCING
2 unchanged sentences
Our ability to make scheduled debt payments on outstanding indebtedness will depend on future results of operations and cash flows.
−Removed: Our results of operations and cash flows, in part, are subject to economic factors beyond our control, including the market prices of gold, silver, zinc and lead.
+Added: Our results of operations and cash flows, in part, are subject to economic factors beyond our control, including the market prices of gold, silver, zinc and lead, among other factors described in this Item.
We may not be able to generate enough cash flow to meet obligations and commitments under outstanding debt instruments.
2 unchanged sentences
In a rising interest rate environment, the costs of borrowing additional funds or refinancing outstanding indebtedness would also be expected to increase.
−Removed: In addition, the interest rate for our senior secured revolving credit facility (“RCF”), pursuant to a Credit Agreement entered into on September 29, 2017 among us, as borrower, certain of our subsidiaries, as guarantors, Bank of America, N.A., as administrative agent and Bank of America, N.A., Royal Bank of Canada, Bank of Montreal, Chicago Branch, the Bank of Nova Scotia and ING Capital LLC, as lenders, is determined, at our option, by the London Interbank Offered Rate (“LIBOR”), and we and our lenders may not be able to agree to a new benchmark interest rate before LIBOR is expected to be eliminated by the end of 2021, which may result in higher interest costs for us.
−Removed: The agreements governing our outstanding indebtedness restrict our ability to dispose of assets and use the proceeds from those dispositions and may also restrict our ability to raise debt or equity capital to be used to repay other indebtedness when it
+Added: The agreements governing our outstanding indebtedness restrict our ability to dispose of assets and use the proceeds from those dispositions and may also restrict our ability to raise debt or equity capital to be used to repay other indebtedness when it becomes due.
We may not be able to consummate those dispositions or to obtain proceeds in an amount sufficient to meet any debt service obligations then due.
−Removed: If we raise additional funds by issuing equity securities or securities convertible into equity securities, holders of our common stock could experience significant dilution of their ownership interest, and these securities could have rights senior to those of the holders of common stock.
The terms of our debt impose restrictions on our operations.
15 unchanged sentences
If we are unable to maintain our outstanding debt and financial ratios at levels acceptable to the credit rating agencies, or should our business prospects or financial results deteriorate, including as a result of declines in gold and silver prices or other factors beyond our control, our ratings could be downgraded by the rating agencies.
−Removed: A downgrade by the rating agencies could adversely affect the value of our outstanding debt securities, our existing debt, and our ability to obtain new financing on favorable terms, if at all, increase borrowing costs, and may result in increased collateral requirements under our existing surety bond portfolio, which in turn may adversely affect our results of operations and financial position.
+Added: A downgrade by the rating agencies could adversely affect the
+Added: value of our outstanding debt securities, our existing debt, and our ability to obtain new financing on favorable terms, if at all, increase borrowing costs, and may result in increased collateral requirements under our existing surety bond portfolio, which in turn may adversely affect our results of operations and financial position.
RISKS RELATED TO APPLICABLE LAWS AND REGULATIONS
3 unchanged sentences
The costs associated with compliance with such laws and regulations are substantial.
−Removed: Changes in existing laws, possible future laws and regulations, or more restrictive interpretations of current laws and regulations by governmental authorities, could
−Removed: cause additional expense, capital expenditures, restrictions on or suspensions of operations and delays in the development of new properties.
+Added: Changes in existing laws, possible future laws and regulations, or more restrictive interpretations of current laws and regulations by governmental authorities, could cause additional expense, capital expenditures, restrictions on or suspensions of operations and delays in the development of new properties.
surface and underground mines like the Kensington, Rochester and Wharf mines and Sterling/Crown project are frequently inspected by the U.S.
1 unchanged sentence
Recently, MSHA has been conducting more frequent and more comprehensive inspections of mining operations in general.
−Removed: Similar inspections are conducted in British Columbia, Canada, at the Silvertip mine and in Mexico at the Palmarejo complex by the British Columbia Ministry of Energy, Mines and Petroleum Resources and the Mexican Secretaria del Trabajo y Prevision Social (Secretary of Labor and Social Safety), respectively.
+Added: Similar inspections are conducted in British Columbia, Canada, at the Silvertip development property and in Mexico at the Palmarejo complex by the British Columbia Ministry of Energy, Mines and Petroleum Resources and the Mexican Secretaria del Trabajo y Prevision Social (Secretary of Labor and Social Safety), respectively.
Failure to comply with applicable laws, regulations and permitting requirements may result in temporary or extended shutdowns, including orders issued by regulatory or judicial authorities causing operations to cease or be curtailed, which may require corrective measures including the payment of fines or penalties, capital expenditures, installation of additional equipment or remedial actions, any of which could have a material, adverse effect on our business and results of operations.
17 unchanged sentences
however, the facility designation process and fee was subjected to legal challenges by us and other third parties.
−Removed: Following legal challenges by Coeur and others, the DOE agreed to vacate the 2019 rule and commence a new rulemaking process, which is pending.
−Removed: The future rule could result in material cost being incurred to ship and store Coeur Rochester's mercury.
+Added: Following legal challenges by Coeur and others, the DOE agreed to vacate the 2019 rule and commence a new rule making process in 2021.
+Added: The future rule could result in material cost being incurred to ship
+Added: and store Coeur Rochester's mercury.
In addition, if any of these wastes causes contamination in or damage to the environment at a U.S.
3 unchanged sentences
Additional regulations or requirements also are imposed on our tailings and waste disposal areas in Alaska under the federal Clean Water Act (“CWA”), in Nevada under the Nevada Water Pollution Control Law which implements the CWA, in South Dakota under the South Dakota Water Pollution Control Act and the Administrative Rules of the State of South Dakota, in British Columbia (Canada) under the Health, Safety and Reclamation Code for Mines in British Columbia, the British Columbia Environmental Management Act and the Canadian Metal and Diamond Mining Effluent Regulations, and in Mexico under the General Law of Ecological Balance and Protection of the Environment (the "GLEBPE") and the regulations under the GLEBPE related to environmental protection in impact assessment matters.
−Removed: In addition, proposed CERCLA
−Removed: regulations requiring mining companies to obtain supplemental financial assurance could, if adopted, have a material adverse effect on results of operations and cash flows.
+Added: In addition, proposed CERCLA regulations requiring mining companies to obtain supplemental financial assurance could, if adopted, have a material adverse effect on results of operations and cash flows.
Airborne emissions are subject to controls under air pollution statutes implementing the Clean Air Act in Nevada, Alaska and South Dakota, and are regulated under the Environmental Management Act in British Columbia (Canada) and the GLEBPE and the regulations under GLEBPE related to prevention and control of the pollution of the atmosphere in Mexico.
24 unchanged sentences
We are currently, and may in the future become, subject to other litigation, arbitration or proceedings with other parties.
−Removed: If decided adversely to us, these legal proceedings, or others that could be brought against us in the future, could have a
−Removed: material adverse effect on our financial position or prospects.
+Added: If decided adversely to us, these legal proceedings, or others that could be brought against us in the future, could have a material adverse effect on our financial position or prospects.
In the event of a dispute arising at our foreign operations, we may be subject to the exclusive jurisdiction of foreign courts or arbitral panels or may not be successful in subjecting foreign persons to the jurisdiction of courts or arbitral panels in the United States.
19 unchanged sentences
Consequently, changes in the mix and source of earnings between countries could have a material impact on the Company’s overall effective tax rate.
+Added: In addition, new tax legislation in certain jurisdictions where we operate could negatively affect us.
+Added: For example, in Nevada, where the Rochester mine, Sterling/Crown project and Lincoln Hill project are located, in response to a significant loss of tourism and gaming revenue during 2020, in June 2021 the Governor signed into law a new excise tax on gross proceeds
+Added: derived from mining gold and silver.
+Added: In addition, there have been recent proposals by elected officials in Mexico for even more significant increases in mining taxes, although it is unclear whether those proposals will result in legislation.
+Added: It is difficult to predict whether proposed changes to tax laws in the jurisdictions where we operate will be passed and if passed, the impact of those changes on the Company.
+Added: Any additional taxes imposed on us could adversely affect our financial condition.
RISKS RELATED TO OUR COMMON STOCK
8 unchanged sentences
We are incorporated in Delaware and governed by the Delaware General Corporation Law.
−Removed: Delaware law allows a corporation to pay
−Removed: dividends only out of surplus, as determined under Delaware law or, if there is no surplus, out of net profits for the fiscal year in which the dividend was declared and for the preceding fiscal year.
+Added: Delaware law allows a corporation to pay dividends only out of surplus, as determined under Delaware law or, if there is no surplus, out of net profits for the fiscal year in which the dividend was declared and for the preceding fiscal year.
Under Delaware law, however, we cannot pay dividends out of net profits if, after we pay the dividend, our capital would be less than the capital represented by the outstanding stock of all classes having a preference upon the distribution of assets.
2 unchanged sentences
Compared sentence by sentence after normalising whitespace, quotation marks, case and digits, so re-formatting and restated figures do not read as changed language. Wording changes appear as one removal and one addition. The current filing and the prior one are authoritative.