31 unchanged sentences
October 31, 2026 and we believe it can be renewed on commercially reasonable terms.
−Removed: We also lease 30,879.3 sq.m facility with three
−Removed: manufacturing wards for principal manufacturing operations in Shigao Town, Renshou ,County, Meishan City, Sichuan Province, China, at
−Removed: which production of, assembly, packaging, warehousing of our touchscreen products.
−Removed: We believe these facilities are adequate to meet our
−Removed: current production requirements and provide room for moderate expansion.
−Removed: In addition, space of 1069.6 sq.
−Removed: m in Shigao Town,
−Removed: Renshou County, Meishan City, Sichuan Province, China was used for testing and experimenting of samples and products by our engineering
+Added: We also lease 30,879.3
+Added: sq.m facility with three manufacturing wards for principal manufacturing operations in Shigao Town, Renshou, County, Meishan City,
+Added: Sichuan Province, China, at which production of, assembly, packaging, warehousing of our touchscreen products.
+Added: We believe these
+Added: facilities are adequate to meet our current production requirements and provide room for moderate expansion.
+Added: In addition, space of 1069.6
+Added: m in Shigao Town, Renshou County, Meishan City, Sichuan Province, China was used for testing and experimenting of samples and products
+Added: by our engineering teams.
None of our properties are subject to material encumbrances
29 unchanged sentences
bonus of RMB15.0 million ($2.1 million).
−Removed: In order to minimize the interruption
−Removed: to our business, Sichuan Vtouch entered into a Leaseback Agreement with Sichuan Renshou on March 16, 2021.
−Removed: The Leaseback Agreement entitles
−Removed: us to lease back the Properties commencing from April 1, 2021 until December 31, 2021, at a monthly rent of RMB300,000 (approximately
−Removed: $46,154), which period was extended to October 31, 2022.
−Removed: On October 16, 2022, October 30, 2023, Sichuan Vtouch twice entered an extension
−Removed: to the Leaseback Agreement with Sichuan Renshou to extend the period it granted Sichuan Vtouch to lease back the Properties until October
−Removed: 31, 2024, at a monthly rent of RMB 400,000 ($56,339).
−Removed: On August 9, 2024, in order to incorporate the new facility construction schedule,
−Removed: the lease was renewed and extended till October 31, 2025, with a monthly rent of RMB 400,000 ($54,800).
+Added: In order to minimize the
+Added: interruption to our business, Sichuan Vtouch entered into a Leaseback Agreement with Sichuan Renshou on March 16, 2021.
+Added: Leaseback Agreement entitles us to lease back the Properties commencing from April 1, 2021 until December 31, 2021, at a monthly
+Added: rent of RMB300,000 (approximately $42,899), which period was extended to October 31, 2022.
+Added: On October 16, 2022, October 30, 2023,
+Added: August 9, 2024, and September 29, 2025, Sichuan Vtouch entered an extension to the Leaseback Agreement with Sichuan Renshou four
+Added: times to extend the period to lease back the Properties until October 31, 2026 at a monthly rent of RMB 400,000 ($57,199) in order
+Added: to incorporate the new facility construction schedule
New Facilities
5 unchanged sentences
We are in the process of obtaining
−Removed: the certificate of land use right for the new parcel and expect to receive the certificate from the local government in the first quarter
−Removed: On July 27, 2021, Sichuan
−Removed: Vtouch and Sichuan Chunqiu Development and Construction Group Co., Ltd.
−Removed: entered into a construction contract for a project to build the
−Removed: capacitive touchscreen and touch machine research and development production base.
−Removed: The project was initially scheduled to commence on
−Removed: August 15, 2021, and reach completion by August 15, 2022, with a provisional contract value of RMB76,000,000 (approximately $11.9 million),
−Removed: subject to adjustment based on the final completion settlement.
−Removed: However, the construction project was subsequently suspended due to the
−Removed: outbreak of Covid-19 and government-ordered shutdowns in China.
−Removed: As a result, the parties have agreed to extend the term of the contract
−Removed: to December 31, 2024.
−Removed: On April 11, 2025, Sichuan Vtouch entered into a supplemental construction contract with Sichuan Chunqiu Development
−Removed: & Construction Group Co.
−Removed: for an additional consideration of RMB 4,633,118 (equivalent to $0.6 million) regarding the completion
−Removed: of the Company’s facility construction project on the capacitive touchscreen and touch machine research and development, which extended
−Removed: the original contract term to December 31, 2025.
−Removed: As of the date of this Annual Report, we estimate that our capital needs for this acquisition
−Removed: and construction will be approximately RMB170.0 million (approximately $26.2 million), but there is no assurance that the estimated amount
−Removed: is sufficient to achieve our goals.
−Removed: We may need additional financing for our new facilities.
−Removed: In addition, we expect that this the construction
−Removed: of buildings and affixtures will be completed by end of 2025 and our production at the new facilities will commence in the second half
−Removed: of 2026, but there is no assurance and we may need extended time to achieve our business plan.
+Added: the certificate of land use right for the new parcel and expect to receive the certificate from the local government by the first half
+Added: On July 27, 2021, Sichuan Vtouch and Sichuan Chunqiu Development and
+Added: Construction Group Co., Ltd.
+Added: entered into a construction contract for a project to build the capacitive touchscreen and touch machine
+Added: research and development production base.
+Added: The project was initially scheduled to commence on August 15, 2021, and reach completion by
+Added: August 15, 2022, with a provisional contract value of RMB76,000,000 (approximately $10.9 million), subject to adjustment based on the
+Added: final completion settlement.
+Added: However, the construction project was subsequently suspended due to the outbreak of Covid-19 and government-ordered
+Added: shutdowns in China.
+Added: As a result, the parties have agreed to extend the term of the contract to December 31, 2024.
+Added: On April 11, 2025, Sichuan
+Added: Vtouch entered into a supplemental construction contract with Sichuan Chunqiu Development & Construction Group Co.
+Added: for an additional
+Added: consideration of RMB 4,633,118 (equivalent to $0.7 million) regarding the completion of the Company’s facility construction project
+Added: on the capacitive touchscreen and touch machine research and development, which extended the original contract term to December 31, 2025.
+Added: As of the date of this Annual Report, we estimate that our capital needs for this acquisition and construction will be approximately RMB253
+Added: million (approximately $36.2 million), but there is no assurance that the estimated amount is sufficient to achieve our goals.
+Added: need additional financing for our new facilities.
+Added: In addition, we expect that this the construction of buildings and affixtures will be
+Added: completed by end of first half of 2027 and our production at the new facilities will commence by the end of 2027, but there is no assurance
+Added: and we may need extended time to achieve our business plan.