Item 3. Legal Proceedings
Item 3. Legal Proceedings
From time to time, we may be involved in legal proceedings or subject to claims incident to the ordinary course of business. The outcome of litigation is inherently uncertain, and there can be no assurances that favorable outcomes will be obtained. For example, o n July 20, 2021, we issued a purchase order (“PO”) to our supplier, Rhombus Energy Solutions, Inc. (“Rhombus”), for a quantity of DC Chargers and dispensers for EVs (“DC Chargers”), for a total price of $13.2 million. As previously disclosed, a dispute (the "Dispute") arose as to the PO, and an arbitration proceeding was initiated.
On February 2, 2024 (the “Settlement Date”), we and Rhombus entered into a settlement and release agreement (the “Settlement Agreement”) pursuant to which, among other things, we agreed to pay Rhombus approximately $0.46 million for certain initial DC Chargers within 15 days from the Settlement Date. We further agreed to pay Rhombus an aggregate of $2.4 million for certain DC Chargers upon shipment with payments correlating to the amounts shipped due prior to shipment, a minimum of 50% of which shall be paid within 12 months after the Settlement date, with the remaining balance, if any, to be paid within 24 months after the Settlement Date. The Settlement Agreement further provides for the dismissal of the legal action as to us and Rhombus. We and Rhombus agreed to release one another from any and all claims relating to the Dispute.
On February 21, 2025, we initiated a legal action against Rhombus related to its refusal to honor certain warranty and commissioning obligations with respect to DC Chargers we purchased from Rhombus. Rhombus has in turn filed a demand for an arbitration claiming that we breached terms of the previous settlement agreement between us and Rhombus by failing to purchase additional DC Chargers. We believe we do not have any obligation to purchase additional non-conforming DC Chargers. Therefore, we believe that Rhombus’s position does not have any merit, and we intend to exercise all available rights and remedies in our legal action against Rhombus. The outcome of any such proceedings are inherently uncertain, and the amount and/or timing of any gains or expenses resulting from such proceedings is not reasonably estimable at this time.
On February 11, 2026, the Company determined that the master services agreement, dated May 14, 2024 (the “Fresno Agreement”), by and between the Company and Fresno Economic Opportunities Commission (the “FEOC”) had been effectively terminated and provided notice to the FEOC of costs and amounts owed to the Company in connection with the termination. As previously disclosed, the Fresno Agreement outlined the general scope of work, timeline, and pricing pursuant to which the Company was to provide services and materials to the FEOC in connection with the FEOC’s fleet electrification program. The total possible estimated fees and expenses payable to the Company by FEOC for services and materials provided in relation to the project under the Fresno Agreement was approximately $15.7 million. The termination followed extensive discussions between the Company and the FEOC regarding the Fresno Agreement and the FEOC’s willingness to continue pursuing its fleet electrification project. Despite the Company’s substantial efforts to accommodate the FEOC’s requests and procuring multiple alternative options to fulfill certain funding obligations under the Fresno Agreement, the FEOC was unwilling to move forward with the project. The Company disputes whether the FEOC properly terminated the Fresno Agreement pursuant to its terms and has reserved its rights with respect thereto. However, as a practical matter, the Company no longer reasonably believes that the business relationship contemplated by the Fresno Agreement will continue. The Company is currently in negotiations with the FEOC to determine the amount of costs and fees owed to the Company for services provided prior to the date of termination, as it is entitled to under the Fresno Agreement. There can be no assurance as to the amount the Company will ultimately receive from the FEOC for services provided under the Fresno Agreement prior to the date of termination.
Please see Note 17 to the the Notes to the accompanying Consolidated Financial Statements included in this Annual Report on Form 10-K for details.
Item 4. Mine Safety Disclosures
Not applicable.
60