Item 2. Management’s Discussion and Analysis
Item 2. Management’s Discussion and Analysis of Financial Condition and Results of Operations.
Forward-Looking Statements
This Quarterly Report on Form 10-Q contains certain statements that are, or may be deemed to be, "forward-looking statements" within the meaning of Section 27A of the Securities Act of 1933, as amended (the "Securities Act"), and Section 21E of the Securities Exchange Act of 1934, as amended (the “Exchange Act”). All statements other than statements of historical fact contained in this Quarterly Report on Form 10-Q, including statements regarding our future results of operations and financial position, strategy and plans, and our expectations for future operations and economic performance, are forward-looking statements. The words “anticipate,” “contemplate,” “estimate,” “expect,” “project,” “plan,” “intend,” “target,” “believe,” “seek,” “may,” “might,” “will,” “would,” “could,” “should,” “can have,” “likely,” “continue,” “design,” “assume,” “budget,” “forecast,” “target,” and other words and terms of similar expressions, are intended to identify forward-looking statements.
We have based these forward-looking statements on assumptions and analysis made by us in light of our current expectations, perceptions about historical trends, current conditions and projections about future events and trends that we believe may affect our financial condition, results of operations, strategy, short-term and long-term business operations and objectives and financial needs.
Although we believe that the expectations reflected in our forward-looking statements are reasonable, actual results could differ from those expressed in our forward-looking statements. Our future financial position and results of operations, as well as any forward-looking statements, are subject to change and inherent risks and uncertainties, including those described in the section titled “Risk Factors” in our most recent Annual Report on Form 10-K as supplemented by Item 1A of this Quarterly Report on Form 10-Q. You should consider our forward-looking statements in light of a number of factors that may cause actual results to vary from our forward-looking statements including, but not limited to:
• our progress in the development of our liquefied natural gas (“LNG”) liquefaction and export project and any carbon capture and storage projects (“CCS projects”) we may develop and the timing of that progress;
• the timing and cost of the development, construction and operation of the first three liquefaction trains and related common facilities (“Phase 1”) of the multi-plant integrated natural gas and liquefaction and LNG export terminal facility to be located at the Port of Brownsville in southern Texas (the “Rio Grande LNG Facility”);
• the availability and frequency of cash distributions available to us from our joint venture which owns Phase 1 of the Rio Grande LNG Facility;
• the timing and cost of the development of subsequent liquefaction trains at the Rio Grande LNG Facility;
• the ability to generate sufficient cash flow to satisfy Rio Grande's significant debt service obligations or to refinance such obligations ahead of their maturity;
• restrictions imposed by NextDecade's or Rio Grande's debt agreements that limit flexibility in operating its business;
• increases in interest rates increasing the cost of servicing Rio Grande's indebtedness;
• our reliance on third parties to successfully complete the Rio Grande LNG Facility, any CCS projects we develop, and related pipelines and other infrastructure;
• our ability to develop and implement CCS projects;
• our ability to secure additional debt and equity financing in the future, including any refinancing of outstanding indebtedness, on commercially acceptable terms;
• the accuracy of estimated costs for the Rio Grande LNG Facility and CCS projects;
• our ability to achieve operational characteristics of the Rio Grande LNG Facility and CCS projects, when completed, including amounts of liquefaction capacities and amount of CO 2 captured and stored, and any differences in such operational characteristics from our expectations;
• the development risks, operational hazards and regulatory approvals applicable to our LNG and CCS project development, construction and operation activities and those of our third-party contractors and counterparties;
• the ability to obtain or maintain governmental approvals to construct or operate the Rio Grande LNG Facility and CCS projects;
• technological innovation which may lessen our anticipated competitive advantage or demand for our offerings;
13
Table of Contents
• the global demand for and price of LNG;
• the availability of LNG vessels worldwide;
• changes in legislation and regulations relating to the LNG and carbon capture industries, including environmental laws and regulations that impose significant compliance costs and liabilities;
• scope of implementation of carbon pricing regimes aimed at reducing greenhouse gas emissions;
• global development and maturation of emissions reduction credit markets;
• adverse changes to existing or proposed carbon tax incentive regimes;
• global pandemics, the Russia-Ukraine conflict, conflict in the Middle East, other sources of volatility in the energy markets and their impact on our business and operating results, including any disruptions in our operations or development of the Rio Grande LNG Facility and the health and safety of our employees, and on our customers, the global economy and the demand for LNG or carbon capture;
• risks related to doing business in and having counterparties in foreign countries, including as a result of tariffs;
• our ability to maintain the listing of our securities on the Nasdaq Capital Market or another securities exchange or quotation medium;
• changes adversely affecting the businesses in which we are engaged;
• management of growth;
• general economic conditions, including inflation and rising interest rates;
• our ability to generate cash; and
• the result of future financing efforts and applications for customary tax incentives.
Should one or more of the foregoing risks or uncertainties materialize in a way that negatively impacts us, or should the underlying assumptions prove incorrect, our actual results may vary materially from those anticipated in our forward-looking statements, and our business, financial condition, and results of operations could be materially and adversely affected.
The forward-looking statements contained in this Quarterly Report on Form 10-Q are made as of the date of this Quarterly Report on Form 10-Q. You should not rely upon forward-looking statements as predictions of future events. In addition, neither we nor any other person assumes responsibility for the accuracy and completeness of any of these forward-looking statements. Except as required by applicable law, we do not undertake any obligation to publicly correct or update any forward-looking statements.
All forward-looking statements attributable to us are expressly qualified in their entirety by these cautionary statements as well as others made in our most recent Annual Report on Form 10-K as well as other filings we have made and will make with the Securities and Exchange Commission (the “SEC”) and our public communications. You should evaluate all forward-looking statements made by us in the context of these risks and uncertainties.
Overview of Business and Significant Developments
Overview of Business
NextDecade Corporation, a Delaware corporation, is a Houston-based energy company primarily engaged in construction and development activities related to the liquefaction of natural gas and sale of LNG and the capture and storage of CO 2 emissions. We are constructing and developing a natural gas liquefaction and export facility located in the Rio Grande Valley near Brownsville, Texas (the “Rio Grande LNG Facility”). The Rio Grande LNG Facility has received Federal Energy Regulatory Commission ("FERC") approval and Department of Energy ("DOE") FTA and non-FTA authorizations for the construction of up to five liquefaction trains and LNG exports totaling up to 27 million tonnes per annum ("MTPA"). The Rio Grande LNG Facility has three liquefaction trains and related infrastructure ("Phase 1") under construction, Train 4 has been commercialized and is being progressed toward a final investment decision ("FID"), and Train 5 is being commercialized and progressed toward FID. We are also developing and beginning the permitting process for expansion Trains 6 through 8 at the Rio Grande LNG Facility and developing a potential carbon capture and storage ("CCS") project at the Rio Grande LNG Facility.
We are focused on constructing and operating the Rio Grande LNG Facility safely, efficiently, on schedule, and on budget. We seek to deliver secure, economically attractive, and sustainable energy solutions through the development and operation of liquefaction and CCS infrastructure.
14
Table of Contents
Unless the context requires otherwise, references to “NextDecade,” “the Company,” “we,” “us,” and “our” refer to NextDecade Corporation and its consolidated subsidiaries, and references to “Rio Grande” refer to Rio Grande LNG, LLC and its subsidiaries.
Significant Recent Developments
Significant developments since January 1, 2025 include the following:
Construction
• Under the engineering, procurement, and construction (“EPC”) contracts with Bechtel Energy, Inc. (“Bechtel”), Phase 1 progress is tracked for Train 1, Train 2, and the common facilities on a combined basis and Train 3 on a separate basis. As of June 2025:
• The overall project completion percentage for Trains 1 and 2 and the common facilities of the Rio Grande LNG Facility was 48.3%, which is in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 91.9% complete, procurement was 80.6% complete, and construction was 21.2% complete.
• The overall project completion percentage for Train 3 of the Rio Grande LNG Facility was 22.7%, which is also in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 55.7% complete, procurement was 45.5% complete, and construction was 2.2% complete.
• In February 2025, the Company provided additional information regarding its development of additional liquefaction capacity at the Rio Grande LNG Facility beyond Trains 1 through 5. Trains 6 through 8 are wholly owned by NextDecade and are cumulatively expected to increase the Company's total liquefaction capacity by approximately 18 MTPA once constructed and placed into operation.
◦ Train 6, with expected LNG production capacity of approximately 6 MTPA, is being developed inside the existing levee at the site and adjacent to Trains 1 through 5. A pre-filing application with FERC for Train 6 is expected in 2025, and a full FERC application is expected in early 2026.
◦ The Company is evaluating multiple areas on the site for the development of Trains 7 and 8, with a total expected LNG production capacity of approximately 12 MTPA.
Strategic and Commercial
• In April 2025, the Company announced a 20-year LNG Sale and Purchase Agreement (“SPA”) with a subsidiary of Saudi Aramco (“Aramco”), pursuant to which the Aramco subsidiary will purchase 1.2 MTPA of LNG from Train 4 at the Rio Grande LNG Facility for 20 years, on a free on board (“FOB”) basis at a price indexed to Henry Hub, subject to a positive FID on Train 4.
• In April 2025, the Company announced that TotalEnergies exercised its LNG purchase option with respect to Train 4 and the Company entered into a 20-year LNG SPA with TotalEnergies, pursuant to which TotalEnergies will purchase 1.5 MTPA of LNG from Train 4 at the Rio Grande LNG Facility for 20 years, on an FOB basis at a price indexed to Henry Hub, subject to a positive FID on Train 4. The Company believes sufficient long-term commercial support is now in place to support a positive FID on Train 4.
• In May 2025, the Company announced a 20-year LNG SPA with JERA, pursuant to which JERA will purchase 2.0 MTPA of LNG from Train 5 at the Rio Grande LNG Facility for 20 years, on an FOB basis at a price indexed to Henry Hub, subject to a positive FID on Train 5.
• In June 2025, the Company finalized a pricing refresh of the Company's lump-sum, turnkey EPC contract with Bechtel for the construction of Train 4 and related infrastructure and executed a lump-sum, turnkey EPC contract with Bechtel for the construction of Train 5 and related infrastructure. Pricing validity under the Train 4 and Train 5 EPC contracts extends through September 15, 2025.
Financial
• In April 2025, Rio Grande LNG, LLC (“Rio Grande”) elected to terminate $250 million of commitments under its working capital facility due to a decrease in expected requirements for credit support during construction, which reduced the outstanding commitments under the working capital facility to $250 million and is expected to reduce related commitment fees by approximately $2 million annually.
• In May 2025, the Company’s wholly-owned subsidiary Rio Grande LNG Super Holdings, LLC, entered into an amended credit agreement with the lender of its existing senior secured loan to increase the loan amount by $50
15
Table of Contents
million to a total of $225 million initial principal. Incremental proceeds from the senior secured loan were disbursed at closing on May 14, 2025, and net proceeds will be used to fund working capital and general corporate purposes, including development expenses for expansion trains at the Rio Grande LNG Facility and specifically pre-FID expenses for Trains 4 and 5. Borrowings under the senior secured loan bear interest at 12.0%, with interest payable quarterly. Interest may be paid in-kind until March 31, 2027 and up to 50% in-kind thereafter. The senior secured loan matures December 31, 2030.
• In conjunction with the closing of the May 2025 amendment to the senior secured loan, the Company issued warrants that are exercisable for an aggregate of approximately 2.0 million shares of NextDecade common stock to the lender of the senior secured loan. The warrants are exercisable for five years after the amendment date. The warrants are exercisable at $9.30 per share, which represented a 30% premium to the volume weighted average price for the 30 trading-day period immediately preceding the amendment date.
Regulatory
• In March 2025, the U.S. Court of Appeals for the D.C. Circuit (the “D.C. Circuit Court”) issued a revision to its August 2024 decision regarding the Company's FERC order, resulting in a remand without vacatur of the FERC order for the first five liquefaction trains at the Rio Grande LNG Facility. Pursuant to the remand, FERC is to consider the issue of a supplemental Environmental Impact Statement (“SEIS”) in view of several executive orders issued since January 20, 2025.
• In March 2025, the FERC issued a draft SEIS for the first five liquefaction trains at the Rio Grande LNG Facility, providing for a public comment period that ended on May 19, 2025.
• In July 2025, the FERC issued a final SEIS for the first five liquefaction trains at the Rio Grande LNG Facility. Based on its published schedule, FERC anticipates issuing a final order on the remand by November 20, 2025.
Rio Grande LNG Facility Activity
Liquefaction Facilities Overview
We are constructing and developing the Rio Grande LNG Facility on the north shore of the Brownsville Ship Channel in south Texas. The site is located on approximately 1,000 acres of land, which has been leased long-term and includes 15,000 feet of frontage on the Brownsville Ship Channel. We believe the site is advantaged due to its proximity to abundant natural gas resources in the Permian Basin and Eagle Ford Shale, access to an uncongested waterway for vessel loading, and location in a region that has historically been subject to fewer and less severe weather events relative to other locations along the U.S. Gulf Coast. The Rio Grande LNG Facility has been permitted by the FERC and authorized by the DOE to export up to 27 MTPA of LNG from up to five liquefaction trains. Phase 1 at the Rio Grande LNG Facility is under construction, Train 4 has been commercialized and is being progressed toward FID, Train 5 is being commercialized and progressed toward FID, and we are developing and beginning the permitting process for Trains 6 through 8.
Phase 1 Overview and Construction Progress
In July 2023, construction commenced on Phase 1 of the Rio Grande LNG Facility following a positive FID and the closing of project financing by Rio Grande, which owns Phase 1 of the Rio Grande LNG Facility. Construction will be completed by Bechtel under fully wrapped, lump-sum turnkey EPC contracts, and the liquefaction trains will utilize Honeywell liquefaction technology, which is the predominant liquefaction technology utilized globally.
Pursuant to a joint venture agreement with equity partners for ownership of Rio Grande, we expect to receive up to approximately 20.8% of distributions of available cash generated from Phase 1 operations, provided that a majority of the cash distributions to which we are otherwise entitled will be paid for any distribution period only after our equity partners receive an agreed distribution threshold in respect of such distribution period and certain other deficit payments from prior distribution periods, if any, are made.
Phase 1 includes three liquefaction trains with a total expected LNG production capacity of approximately 18 MTPA, two 180,000 cubic meter full containment LNG storage tanks, two jetty berthing structures designed to load LNG carriers up to 216,000 cubic meters in capacity, and associated site infrastructure and common facilities including feed gas pretreatment facilities, electric and water utilities, two totally enclosed ground flares for the LNG tanks and marine facilities, two ground flares for the liquefaction trains, roads, levees surrounding the entire site, and warehouses, administrative, operations control room and maintenance buildings.
As of June 2025, progress on Trains 1 through 3 is in line with the schedule under the EPC contracts. During the second quarter 2025, the construction team continued piping fabrication, rebar installation, equipment setting and concrete placement, and structural steel erection in the areas of Trains 1, 2, and 3. The eighth wall lift was completed for Tank 1.
16
Table of Contents
Across the site, Bechtel also continued installing concrete foundations, instrument air receivers, floodgates, permanent fencing, temporary facilities, and other siteworks.
Phase 1 LNG Sale and Purchase Agreements
For Phase 1 of the Rio Grande LNG Facility, Rio Grande has entered into long-term LNG SPAs with nine creditworthy counterparties for aggregate volumes of approximately 16.2 MTPA of LNG. The SPAs have a weighted average term of 19.2 years. Under these SPAs, the customers will purchase LNG from Rio Grande for a price consisting of a fixed fee per MMBtu of LNG plus a variable fee per MMBtu of LNG, with the variable fees structured to cover the expected cost of natural gas plus fuel and other sourcing costs to produce LNG. In certain circumstances, customers may elect to cancel or suspend deliveries of LNG cargoes, in which case the customers would still be required to pay the fixed fee with respect to cargoes that are not delivered. A portion of the fixed fee under each SPA will be subject to annual adjustment for inflation. The SPAs and contracted volumes to be made available under the SPAs are not tied to a specific train; however, the commencement of the term of each SPA is tied to a specified train.
Each of these SPAs is currently effective, and deliveries of LNG under these SPAs will commence on the respective Date of First Commercial Delivery (“DFCD”), which is primarily tied to the substantial completion or guaranteed substantial completion dates of specific trains as defined in each SPA. In aggregate, approximately 14.65 MTPA of Phase 1 Henry Hub-linked SPAs have average fixed fees, unadjusted for inflation, totaling approximately $1.8 billion expected to be paid annually.
Marketing of Uncontracted Volumes
Rio Grande expects to sell any commissioning LNG volumes and operational LNG volumes in excess of SPA volumes into the LNG market through spot, short-term, and medium-term agreements. Rio Grande has entered into certain time charter agreements and expects to enter into additional time charter agreements with vessel owners to provide shipping capacity for LNG sales related to its existing Phase 1 delivered ex-ship SPA, commissioning volumes, and expected portfolio volumes.
Engineering, Procurement and Construction ( “ EPC ”)
The Company has entered into fully wrapped, lump-sum turnkey contracts with Bechtel, a well-established and reputable LNG engineering and construction firm, for the engineering, procurement, and construction of Phase 1, Train 4, and Train 5 at the Rio Grande LNG Facility, under which Bechtel has generally guaranteed cost, performance, and schedule. Under these EPC contracts, Bechtel is responsible for the engineering, procurement, construction, commissioning, and startup of liquefaction trains and their respective related infrastructure.
On July 12, 2023, Rio Grande issued final notice to proceed to Bechtel under the EPC contracts for Phase 1. Total expected capital costs for Phase 1 are estimated to be approximately $18.0 billion, including estimated EPC costs, owner’s costs, contingencies, and financing costs, and including amounts spent prior to FID under limited notices to proceed.
Natural Gas Transportation and Supply
We are in the process of executing a substantial and diversified natural gas feedstock sourcing and transportation strategy to spread risk exposure across multiple contracts, counterparties, and pricing hubs. We expect to enter into gas supply arrangements with a wide range of suppliers, and we also expect to leverage trading platforms and exchanges to lock in natural gas supply prices and/or hedge risk.
We have entered into agreements for transportation of natural gas to the Rio Grande LNG Facility on both a firm and interruptible basis to support commissioning and operations and provide the ability to purchase natural gas supplies at the Agua Dulce Hub, giving us access to prolific gas production from the Permian Basin and Eagle Ford Shale and providing significant flexibility to obtain competitively priced natural gas feedstock.
We believe our proximity to major reserve basins and shale plays, increasing pipeline capacity in the area, a significant amount of natural gas production and infrastructure investment, as well as our existing contacts and discussions with some of the largest regional operators, represent key elements of a comprehensive and effective feed gas strategy.
Final Investment Decision on Train 4
The Company has completed commercialization of Train 4 and has executed 20-year LNG SPAs totaling 4.6 MTPA of LNG with ADNOC, Aramco, and TotalEnergies in support of Train 4.
In June 2025, the Company finalized an EPC contract pricing refresh with Bechtel for Train 4 and related infrastructure. Pricing validity under the EPC contract for Train 4 extends through September 15, 2025.
17
Table of Contents
The Company launched the financing process for Train 4 in June 2025 and expects to finance construction of Train 4 using a combination of debt and equity funding at the project level. The Company is in the process of entering into a term loan bank facility at Rio Grande LNG Train 4, LLC for the debt portion of the funding.
The Company's Phase 1 equity partners each have options to invest in Train 4 equity which, if exercised, would provide 60% of the equity funding required for Train 4. The Company expects the Phase 1 equity partners to exercise their options to participate in Train 4 equity.
NextDecade currently expects to fund 40% of the equity commitments for Train 4, and to have an initial economic interest of 40% in Train 4, which will increase to 60% after its equity partners achieve certain returns on their investments in Train 4. The Company is in the process of financing its equity capital for Train 4.
The Company expects to achieve a positive FID on Train 4 by mid-September 2025, subject to obtaining adequate financing.
Final Investment Decision on Train 5
The Company is also progressing Train 5 toward FID, and the commercialization process is underway for Train 5. In May 2025, the Company announced a 20-year LNG SPA with JERA for 2.0 MTPA of LNG in support of Train 5. The Company is targeting an additional 2.5 MTPA of long-term contracts to support a positive FID of Train 5.
In June 2025, the Company finalized an EPC contract with Bechtel for Train 5 and related infrastructure. Pricing validity under the EPC contract for Train 5 extends through September 15, 2025.
The Company began the financing process for Train 5 in the second quarter of 2025 and expects to finance construction of Train 5 using a combination of debt and equity funding at the project level. The Company expects to enter into bank facilities at Rio Grande LNG Train 5, LLC for the debt portion of the funding. Certain of the Company’s Phase 1 equity partners have options to invest in Train 5 equity, which if exercised, would provide 50% of the equity funding required for Train 5. Inclusive of these options, NextDecade currently expects to fund the balance of the equity commitments for Train 5, and to have an initial economic interest of up to 50% in Train 5, which will increase to up to 70% after its equity partners achieve certain returns on their investments in Train 5.
The Company continues to pursue financing for Train 5 and, subject to obtaining appropriate commercial support and financing, is targeting FID by mid-September 2025.
Development of Additional Liquefaction Capacity
The Company is developing and beginning the permitting process for additional liquefaction capacity at the Rio Grande LNG Facility site beyond Trains 1 through 5. Trains 6 through 8 are wholly owned by NextDecade and are cumulatively expected to increase the Company's total liquefaction capacity by approximately 18 MTPA once constructed and placed into operation.
Train 6 is being developed inside the existing levee at the Rio Grande LNG Facility site and adjacent to Trains 1 through 5. The Company expects to pre-file an application with FERC for Train 6 in 2025 and a full application with FERC in early 2026. The Company is evaluating multiple areas on the site for the development of Trains 7 and 8 and expects to provide an update on the expected permitting timeline for Trains 7 and 8 in 2025.
Governmental Permits, Approvals and Authorizations
We have obtained all major permits required to build and export LNG from the first five liquefaction trains and related infrastructure at the Rio Grande Facility, including FERC approval and DOE FTA and non-FTA authorizations for the construction of up to five liquefaction trains and LNG exports totaling up to 27 MTPA.
In March 2025, the D.C. Circuit Court issued a revision to its August 2024 decision regarding our FERC order, resulting in a remand without vacatur of the FERC order for the first five liquefaction trains at the Rio Grande LNG Facility. Pursuant to the remand, FERC is to consider the issue of a supplemental Environmental Impact Statement (“SEIS”) in view of several executive orders issued since January 20, 2025.
In March 2025, the FERC issued a draft SEIS for the first five liquefaction trains at the Rio Grande LNG Facility, providing for a public comment period that ended on May 19, 2025. In July 2025, the FERC issued a final SEIS for the first five liquefaction trains at the Rio Grande LNG Facility. Based on its published schedule, FERC anticipates issuing a final order on the remand by November 20, 2025.
18
Table of Contents
Corporate and Other Activities
We are required to maintain corporate and general and administrative functions to serve our business activities described above, including construction of Phase 1 at the Rio Grande LNG Facility, the development of Trains 4 through 8, and the development of a potential CCS project at the Rio Grande LNG Facility.
Liquidity and Capital Resources
Following FID on Phase 1 and the project financing obtained by Rio Grande, NextDecade and Rio Grande operate with independent capital structures. Although our sources and uses are presented from a consolidated standpoint, certain restrictions under debt and equity agreements limit the ability of NextDecade and Rio Grande to use and distribute cash. Rio Grande is required to deposit all cash received under its debt agreements into restricted accounts. The usage or withdrawal of such cash is restricted to the payment of obligations related to Phase 1 and other restricted payments, and such cash and capital resources are not available to service the obligations of NextDecade.
Phase 1 FID Rio Grande Financing
In connection with the FID on Phase 1 of the Rio Grande LNG Facility, Rio Grande obtained approximately $6.2 billion in equity capital commitments, inclusive of commitments from NextDecade, entered into senior secured non-recourse bank credit facilities of $11.6 billion, consisting of $11.1 billion in construction term loans and a $500 million working capital facility, and closed a $700 million senior secured non-recourse private notes offering. Rio Grande expects to utilize these capital resources to fund the total cost of Phase 1, which is currently estimated at $18.0 billion and consists of EPC costs, owner’s costs and contingencies, dredging for the Brazos Island Harbor Channel Improvement Project, conservation of more than 4,000 acres of wetland and wildlife habitat area and installation of utilities, and interest during construction and other financing costs. Rio Grande has refinanced a total of over $1.85 billion of the original $11.1 billion Rio Grande term loan facilities into senior secured notes and loans since July 2023.
In April 2025, Rio Grande elected to terminate $250 million of commitments under its working capital facility due to a decrease in expected requirements for credit support during construction, which reduced the outstanding commitments under the working capital facility to $250 million.
Near Term Liquidity and Capital Resources of NextDecade Corporation
Prior to the FID on Phase 1 of the Rio Grande LNG Facility, our primary cash needs historically were funding development activities in support of the Rio Grande LNG Facility and our CCS projects, which included payments of initial direct costs of the Rio Grande site lease and expenses in support of engineering and design activities, regulatory approvals and compliance, commercial and marketing activities and corporate overhead. Following the FID on Phase 1 of the Rio Grande LNG Facility, costs associated with the Phase 1 EPC agreements, Rio Grande site lease, and other Phase 1 related costs are being funded by debt and equity proceeds received by Rio Grande.
Because our businesses and assets are under construction or in development, we have not historically generated significant cash flow from operations, nor do we expect to do so until liquefaction trains at the Rio Grande LNG Facility begin operating. We intend to fund development activities for the foreseeable future with cash and cash equivalents on hand and through the sale of additional equity, equity-based or debt securities in us or in our subsidiaries. There can be no assurance that we will succeed in selling equity or equity-based securities or, if successful, that the capital we raise will not be expensive or dilutive to stockholders.
Our current capital resources consist of approximately $158.5 million of cash and cash equivalents as of June 30, 2025.
Long Term Liquidity and Capital Resources of NextDecade Corporation
We will not receive significant cash flows from Phase 1 of the Rio Grande LNG Facility until it is operational, and the commercial operation date for the first train of Phase 1 is expected to occur in late 2027 based on the schedule under the EPC contracts. Any future phases of development at the Rio Grande LNG Facility and CCS projects will similarly take an extended period of time to develop, construct and become operational and will require significant capital deployment.
We currently expect that the long-term capital requirements for future phases of development at the Rio Grande LNG Facility and any CCS projects will be financed predominantly through the proceeds from future debt, equity-based, and equity offerings by us or our subsidiaries. As a result, our business success will depend, to a significant extent, upon our ability to obtain financing required to fund future phases of development and construction at the Rio Grande LNG Facility and any CCS projects, to bring them into operation on a commercially viable basis and to finance any required increases in staffing, operating and expansion costs during that process. There can be no assurance that we will succeed in securing additional debt and/or equity financing in the future to fund future phases of development and construction at the Rio Grande LNG Facility or complete any CCS projects or, if successful, that the capital we raise will not be expensive or
19
Table of Contents
dilutive to stockholders. Additionally, if these types of financing are not available, we will be required to seek alternative sources of financing, which may not be available on terms acceptable to us, if at all.
Sources and Uses of Cash
The following table summarizes the sources and uses of our cash for the periods presented (in thousands):
Six Months Ended June 30,
2025 2024
Operating cash flows $ (72,722) (22,838)
Investing cash flows (1,531,338) (1,374,290)
Financing cash flows 1,668,337 1,305,729
Net (decrease) increase in cash, cash equivalents and restricted cash 64,277 (91,399)
Cash, cash equivalents and restricted cash – beginning of period 392,762 294,478
Cash, cash equivalents and restricted cash – end of period $ 457,039 $ 203,079
Cash used in operating activities for the six months ended June 30, 2025 increased by approximately $49.9 million compared to the same period in 2024 primarily due to higher pre-operational expenditures and working capital investments to support the commencement of operations at the Rio Grande LNG Facility.
Cash used in investing activities for the six months ended June 30, 2025 increased by approximately $157.0 million compared to the same period in 2024 primarily due to increased expenditures associated with the Rio Grande LNG Facility.
Cash provided by financing activities for the six months ended June 30, 2025 increased by approximately $362.6 million compared to the same period in 2024. This was driven by an increase of approximately $79.3 million uptick in equity commitment receipts and the absence of approximately $1.3 billion of debt repayments in the current period. These increases were partially offset by a $1.0 billion reduction in debt proceeds.
Results of Operations
The following table summarizes costs, expenses and other income for the periods indicated (in thousands):
Three Months Ended June 30, Six Months Ended June 30,
2025 2024 2025 2024
Revenues $ — $ — $ — $ —
General and administrative expense 52,049 33,902 96,991 66,407
Development expense 1,248 2,409 1,555 4,918
Depreciation and amortization expense 2,971 3,223 6,120 6,326
Other — — 3,518 —
Total operating loss (56,268) (39,534) (108,184) (77,651)
Other (expense) income:
Derivative gain (loss) 25,157 109,067 (143,543) 367,939
Interest expense, net (28,833) (26,030) (56,038) (51,509)
Loss on debt extinguishment (9,160) (40,133) (9,160) (47,573)
Other, net (1,528) (1,066) 1,065 (2,127)
Net (loss) income attributable to NextDecade Corporation (70,632) 2,304 (315,860) 189,079
Less: net (loss) income attributable to non-controlling interest (9,765) 34,880 (166,188) 193,309
Net loss attributable to common stockholders $ (60,867) $ (32,576) $ (149,672) $ (4,230)
Net loss attributable to common stockholders was approximately $60.9 million, for the three months ended June 30, 2025 compared to net loss of $32.6 million during the same period in 2024. The $28.3 million increase was primarily a result of the following:
• General and administrative expenses increased by approximately $18.1 million, principally reflecting incremental headcount additions to support the commencement of operations at the Rio Grande LNG Facility.
20
Table of Contents
• Unrealized derivative gains decreased by approximately $83.9 million, primarily reflecting lower forward SOFR rates.
• Loss on debt extinguishment decreased approximately $31.0 million due to the lack of debt repayments during the current period.
• Due to the above changes, net income attributable to non-controlling interest during the three months ended June 30, 2025 decreased approximately $44.6 million as those activities are a component of Intermediate Holdings net income and loss.
Net loss attributable to common stockholders was approximately $149.7 million, for the six months ended June 30, 2025 compared to net loss of $4.2 million during the same period in 2024. The $145.4 million increase was primarily a result of the following:
• General and administrative expenses increased by approximately $30.6 million, principally reflecting incremental headcount additions to support the commencement of operations at the Rio Grande LNG Facility.
• Unrealized derivative gains decreased by approximately $511.5 million, primarily reflecting lower forward SOFR rates.
• Loss on debt extinguishment decreased approximately $38.4 million due to the lack of debt repayments during the current period.
• Due to the above changes, net income attributable to non-controlling interest during the six months ended June 30, 2025 decreased approximately $359.5 million as those activities are a component of Intermediate Holdings net income and loss.
Summary of Critical Accounting Estimates
There were no changes made by management to the critical accounting policies in the three months ended June 30, 2025. Please refer to the Summary of Critical Accounting Estimates section within MD&A and Note 2 to the consolidated financial statements of our Annual Report on Form 10-K for the year ended December 31, 2024 for a discussion of our critical accounting estimates and accounting policies.