The Company also operates a chemistry lab facility in Zeeland, Michigan to support production.
+Added: In April 2025, the Company acquired VOXX, which operates primarily out of facilities in Hauppauge, NY, and Indianapolis, IN.
In addition, the Company operates overseas offices in Europe and Asia as further discussed below.
The location, square footage and use of the most significant facilities as of December 31, 2025 were as follows:
−Removed: Owned Locations Square Footage Date of Acquisition/Build (1)
+Added: Owned Locations Square Footage Use
Zeeland, MI 26,600 Warehouse, Office
11 unchanged sentences
Holland, MI 242,300 Manufacturing, Warehouse
−Removed: Holland, MI 29,900 2021 Office
+Added: Auburn Hills, MI
+Added: 30,600 Office, Engineering
Erlenbach, Germany 100,000 Office
+Added: Langenzenn, Germany
+Added: 120,000 Office, Warehouse
Shanghai, China 21,000 Office, Warehouse
Shanghai, China 60,000 Office, Warehouse, Light Assembly
−Removed: (1) Date of Acquisition/Build refers to first year of operations and does not refer to subsequent additions or expansions.
−Removed: In 2023, the Company completed construction on a 345,000 square-foot manufacturing facility located at a 140 acre site in Zeeland, Michigan, where the Company previously performed master planning and completed land infrastructure improvements.
+Added: Hauppauge, NY 55,400 Office
+Added: Hope, AR 198,400 Warehouse
+Added: Indianapolis, IN 114,000 Office
+Added: In 2023, the Company completed construction on a 345,000 square-foot manufacturing facility located at a 140 acre site in Zeeland, Michigan, where the Company previously performed master planning and completed land
+Added: infrastructure improvements.
The total cost of the building project was approximately $85 million, which was funded with cash and cash equivalents on hand.
3 unchanged sentences
Both of these expansion projects were funded with cash and cash equivalents on hand.
−Removed: During 2023, the Company began the design and initial build phase of the previously announced Gentex Discovery Preschool, an on-site daycare and preschool designed to provide Company employees with convenient, cost-effective access to quality childcare.
−Removed: Construction began in the third quarter of 2024 as previously announced, with an expected completion date in 2025.
−Removed: The total cost of the building project is expected to be $15 - $20 million, which will be funded with cash and cash equivalents on hand.
−Removed: The Company has also leased sales and engineering offices throughout North America, Europe, and Asia to support its sales and engineering efforts, and, in addition, has leased a manufacturing facility in Grand Rapids, Michigan:
+Added: In the fourth quarter of 2025, the Company completed construction of the previously announced Gentex Discovery Preschool, an on-site daycare and preschool designed to provide Company employees with convenient, cost-effective access to quality childcare.
+Added: The total cost of the building project was approximately $20 million and was funded with cash and cash equivalents on hand.
+Added: The Company has also leased sales and engineering offices throughout North America, Europe, and Asia to support its sales and engineering efforts, and, in addition, has leased manufacturing facilities in Grand Rapids, Michigan and Nogales, Mexico:
Country Number of Leased Offices/Facilities
2 unchanged sentences
The Company's Automotive Products segment operates in virtually all of the foregoing facilities.
−Removed: The Company's Other segment operates in certain Zeeland, Michigan facilities, as well as a research and development offices in Salt Lake City, Utah;
−Removed: Santa Clara, CA;
+Added: The Company's Premium Audio Products segment operates in the Indianapolis, Indiana facility, as well as sales offices in China, France, Germany, and the Netherlands.
+Added: The Company's Other segment operates in certain Michigan and Germany facilities, as well as research and development offices in Salt Lake City, Utah;
+Added: Santa Clara, California;
The Company believes its existing and planned facilities are currently suitable, adequate, and have the capacity required for current and near-term planned business.
7 unchanged sentences
Compared sentence by sentence after normalising whitespace, quotation marks, case and digits, so re-formatting and restated figures do not read as changed language. Wording changes appear as one removal and one addition. The current filing and the prior one are authoritative.