LEGAL PROCEEDINGS
−Removed: From time to time, we become
−Removed: involved in or are threatened with legal disputes.
−Removed: While most of these disputes are not likely to have a material effect on our business,
−Removed: financial condition, or operations, the following matters are deemed by the Company to be material either due to the costs of litigation
−Removed: or the potential negative impacts to the Company should these matters not be resolved in our favor:
−Removed: ● Great Green Theory – On June
−Removed: 10, 2022, Emerald filed a lien and brought a suit in the Superior Court of Berkshire, Massachusetts
−Removed: to foreclose on the lien against Great Green Theory Land, LLC and Great Green Theory Cultivation,
−Removed: LLC who are the owners of the land and a construction project in Lee, Massachusetts.
−Removed: is claiming breach of contract and quantum merit against Great Green Theory for failure
−Removed: to pay approximately $1.3 million in payment applications.
−Removed: Great Green Theory has filed counterclaims
−Removed: against Emerald claiming liquidated damages of approximately $1.0 million for alleged unjustifiable
−Removed: delays on the project and alleging construction defects in the project.
−Removed: Emerald has settled
−Removed: two subcontractor suits against Emerald for non-payment to them of which Emerald has not
−Removed: received payment from Great Green Theory.
−Removed: ° Accounts receivable and accounts payable
−Removed: related to Great Green Theory – The selling Emerald shareholders have agreed to indemnify
−Removed: and defend the Company for any litigation or judgement stemming from this lawsuit.
−Removed: has recorded $1.3 million as a receivable and $0.4 million as a payable to sub-contractors
−Removed: on the opening balance sheet as of the date of the acquisition.
−Removed: ° Legal Costs to collect Great Green
−Removed: Theory accounts receivable – The Company has agreed to split the legal costs of this
−Removed: claim until the funds are recovered or until the claim of liquidated damages is relieved.
−Removed: Total estimated legal costs associated with this claim are approximately $0.3 million.
−Removed: Company recorded 50% of this amount as a liability on the opening balance sheet as of the
−Removed: date of the acquisition.
−Removed: ● Pullar – urban-gro’s
−Removed: former Chief Financial Officer, George Pullar, filed a suit in the District Court of Boulder
−Removed: County, Colorado against urban-gro and Bradley Nattrass, in his capacity as urban-gro’s
−Removed: CEO, claiming breach of fiduciary duty.
−Removed: The claims stem from a settlement agreement with
−Removed: Pullar and allegations that Mr.
−Removed: Nattrass and urban-gro failed to share enough non-public
−Removed: material information about urban-gro’s plans for fundraising that would have impacted
−Removed: Pullar’s decision to enter into the settlement agreement.
−Removed: urban-gro’s director
−Removed: and officer liability insurance carrier has indicated coverage is available to Mr.
−Removed: for this suit.
−Removed: We believe we have substantial defenses to the claim asserted in this lawsuit
−Removed: and intend to vigorously defend this action.
+Added: From time to time, the Company
+Added: is involved in routine litigation that arises in the ordinary course of business.
+Added: Other than below, there are no other legal proceedings
+Added: for which management believes the ultimate outcome would have a material adverse effect on the Company’s results of operations and
Gemini Loan Agreement Amendment and Default
20 unchanged sentences
outstanding interest, as of the applicable measurement date.
−Removed: In connection with the execution of the Amendment, we issued to Gemini,
−Removed: as an amendment fee, 150,000 shares of our common stock
+Added: In connection with the execution of the Amendment, we issued to Gemini, as
+Added: an amendment fee, 150,000 shares of our common stock, or 6,000 shares after giving effect to a 1-for-25 reverse stock split.
On July 31, 2025, Gemini issued
34 unchanged sentences
The fairness hearing occurred on October 14, 2025.
−Removed: Agile Term Loan
−Removed: On June 26, 2025, we and certain
−Removed: of our subsidiaries entered into a business loan and security agreement (the “Agile Loan Agreement”) with Agile Capital Funding,
−Removed: LLC and Agile Lending LLC (together, “Agile”).
−Removed: Pursuant to the Agile Loan
−Removed: Agreement, Agile extended to us a term loan of $1,050,000.00 (the “Term Loan”) to be used to fund our general business requirements.
−Removed: The Agile Loan Agreement is for a term of twenty-eight weeks from its effective date and includes an administrative agent fee of $50,000.00
−Removed: to be remitted to Agile, which was added to the amount of the loan.
−Removed: We could make a full prepayment or partial prepayment of the Term
−Removed: Loan, however, upon the prepayment of any principal amount, we would be obligated to pay a premium payment of principal, which would be
−Removed: equal to the aggregate and actual amount of interest that would be paid through the maturity date.
−Removed: The Agile Loan Agreement contains standard
−Removed: events of default and representations and warranties by us and Agile including a mandatory prepayment, and an additional five (5%) percent
−Removed: interest rate following the occurrence of an event of default.
−Removed: The term loan is evidenced by a secured promissory note issued by us to
−Removed: Pursuant to the Agile Loan Agreement, upon an event of default, Agile will receive a security interest in certain of our assets,
−Removed: subject to certain exceptions.
Grow Hill Default
6 unchanged sentences
between us and Grow Hill (the “Security Agreement”), which does not include any assets of our subsidiaries.
−Removed: On October 14, 2025, we received
−Removed: service of process for a lawsuit filed by Grow Hill against us in the District Court for the City and County of Denver, Colorado (Case
−Removed: 2025CV33546) alleging breach of contract and fraud.
−Removed: Pursuant the complaint, Grow Hill stated that we were in default under the Secured
−Removed: Promissory Note due to a failure to timely make payments, and elected to accelerate all amounts due under the Secured Promissory Note,
−Removed: including a default fee equal to 1% of the outstanding principal amount.
−Removed: We are currently investigating available options to resolve the
−Removed: complaint and intends to vigorously defend the allegation of fraud.
+Added: On October 14, 2025, we received service of process for a lawsuit filed
+Added: by Grow Hill against us in the District Court for the City and County of Denver, Colorado (Case No.
+Added: 2025CV33546) alleging breach of contract
+Added: Pursuant to the complaint, Grow Hill stated that we were in default under the Secured Promissory Note due to a failure to timely
+Added: make payments, and elected to accelerate all amounts due under the Secured Promissory Note, including a default fee equal to 1% of the
+Added: outstanding principal amount.
+Added: We are currently investigating available options to resolve the complaint and intend to vigorously defend
+Added: the allegation of fraud.
J Brrothers Settlement
3 unchanged sentences
to the terms of the Settlement Agreement, among other things, we issued a promissory note to J Brrothers with an original principal amount
−Removed: of $395,556 and issued 150,000 unregistered shares of our common stock to J Brrothers.
−Removed: The note accrues simple interest at an annual rate
−Removed: of 12% and has a maturity date of March 18, 2026.
−Removed: The note must be repaid in monthly installments over a period of eight months, with
−Removed: the first seven payments being $50,000 per month and the final monthly payment being $64,047.
−Removed: Any remaining principal and accrued but
−Removed: unpaid interest will become due and payable on the maturity date, and the note may be prepaid without penalty.
−Removed: The note includes customary
−Removed: representations and warranties, customary events of default and a 17% default interest rate.
−Removed: RK Mechanical- complaint filed
−Removed: On June 27, 2025, RK Mechanical
−Removed: LLC (“RK”) filed a complaint against UG Construction and certain other defendants, with SVC Manufacturing Inc.
−Removed: as cross-claimant
−Removed: and UG Construction as cross-defendant, in the Superior Court of Arizona for Maricopa County (Case No.
−Removed: CV2025-022680).
−Removed: The complaint alleged
−Removed: that UG Construction served as general contractor for the construction of the construction of a PepsiCo plant in Tolleson, Arizona, and
−Removed: that as a result of work completed by RK, UG Construction owed $1,522,716 to RK as a result of alleged breach of contract, breach of implied
−Removed: covenant of good faith and fair dealing, violation of the Arizona Prompt Payment Act, and lien foreclosure.
−Removed: On or about October 2025,
−Removed: a default judgment was entered against UG Construction for $1,511,716, plus prejudgment interest of $288,346 and post-judgment interest
−Removed: at 8.25% plus $10,057 in attorney fees.
−Removed: Action Equipment- complaint filed
−Removed: On April 21, 2025, Action Equip.
−Removed: (“Action”) filed a complaint against UG Construction in the Superior Court of Arizona for Maricopa County (Case No.
−Removed: CV2025-014165).
−Removed: The complaint alleged that UG Construction owed Action $380,932 plus interest and attorneys’ fees in connection with a contract
−Removed: pursuant to which Action leased equipment to UG Construction, and alleged breach of contract, breach of covenant of good faith and fair
−Removed: dealing, and unjust enrichment.
−Removed: A default judgment was subsequently entered against UG Construction, and Action filed a writ of garnishment
−Removed: on October 21, 2025.
+Added: of $395,556 and agreed to issue 150,000 unregistered shares of our common stock, or 6,000 shares after giving effect to a 1-for-25 reverse
+Added: stock split, to J Brrothers.
+Added: The note accrues simple interest at an annual rate of 12% and has a maturity date of March 18, 2026.
+Added: note must be repaid in monthly installments over a period of eight months, with the first seven payments being $50,000 per month and the
+Added: final monthly payment being $64,047.
+Added: Any remaining principal and accrued but unpaid interest will become due and payable on the maturity
+Added: date, and the note may be prepaid without penalty.
+Added: The note includes customary representations and warranties, customary events of default
+Added: and a 17% default interest rate.
+Added: As of December 31, 2025, the Company had made only the initial partial
+Added: payment of $25,000 on August 27, 2025.
+Added: The required $50,000 monthly payments for September through December 2025 were not made.
+Added: The outstanding
+Added: balance was approximately $374,512 at December 31, 2025, inclusive of accrued interest.
+Added: The note matured on March 18, 2026.
MJ’s Market, Inc
16 unchanged sentences
The lawsuit is ongoing.
−Removed: There can be no assurance
−Removed: that future developments related to pending claims filed in the future, whether as a result of adverse outcomes or as a result of significant
−Removed: defense costs, will not have a material effect on urban-gro’s financial condition, results of operations or cash flows.
+Added: RK Mechanical- complaint filed
+Added: On June 27, 2025, RK Mechanical LLC (“RK”) filed a complaint
+Added: against UG Construction and certain other defendants, with SVC Manufacturing Inc.
+Added: as cross-claimant and UG Construction as cross-defendant,
+Added: in the Superior Court of Arizona for Maricopa County (Case No.
+Added: CV2025-022680).
+Added: The complaint alleged that UG Construction served as general
+Added: contractor for the construction of a PepsiCo plant in Tolleson, Arizona, and that as a result of work completed by RK, UG Construction
+Added: owed $1,522,716 to RK as a result of alleged breach of contract, breach of implied covenant of good faith and fair dealing, violation
+Added: of the Arizona Prompt Payment Act, and lien foreclosure.
+Added: On or about October 2025, a default judgment was entered against UG Construction
+Added: for $1,511,716, plus prejudgment interest of $288,346 and post-judgment interest at 8.25% plus $10,057 in attorney fees.
+Added: Action Equipment- complaint filed
+Added: On April 21, 2025, Action
+Added: & Scaffold Co.
+Added: (“Action”) filed a complaint against UG Construction in the Superior Court of Arizona for Maricopa
+Added: County (Case No.
+Added: CV2025-014165).
+Added: The complaint alleged that UG Construction owed Action $380,932 plus interest and attorneys’ fees
+Added: in connection with a contract pursuant to which Action leased equipment to UG Construction, and alleged breach of contract, breach of
+Added: covenant of good faith and fair dealing, and unjust enrichment.
+Added: Urban-Gro, Inc.
+Added: On December 24, 2025, Christopher W.
+Added: Cullens (“Mr.
+Added: a former employee of urban-gro, Inc.
+Added: (the “Company”), filed a complaint against the Company and Bradley Nattrass, the Company's
+Added: Chief Executive Officer, in the District Court, Boulder County, State of Colorado (Case No.
+Added: 2025CV31164).
+Added: Cullens served as Vice President
+Added: of Construction Operations pursuant to a written employment agreement and was terminated without cause on November 14, 2025, following
+Added: an unpaid furlough that began in August 2025.
+Added: The complaint asserts claims for:
+Added: (i) violation of the Colorado Wage
+Added: Claim Act, C.R.S.
+Added: § 8-4-101, et seq.
+Added: (the "CWA"), against the Company and Mr.
+Added: (ii) breach of contract against
+Added: and (iii) unjust enrichment against the Company, pleaded in the alternative.
+Added: Cullens alleges that, at the time of his
+Added: termination, he had earned and was vested in commissions totaling $650,000, which he contends constitute earned, vested, and determinable
+Added: wages due and payable immediately upon discharge under the CWA.
+Added: Cullens further alleges that he is entitled to a severance package
+Added: consisting of nine months of his base salary and nine months of COBRA premium payments pursuant to the terms of his employment agreement.
+Added: Cullens seeks, among other relief, payment of the unpaid commissions, statutory penalties of up to three times the unpaid wages under
+Added: the CWA, the full value of the severance package, reasonable attorney's fees and costs, and such other relief as the court deems just
+Added: On March 30, 2026, the Company and Mr.
+Added: Nattrass filed their answer
+Added: to the complaint, generally denying the material allegations or asserting that they lack sufficient information or knowledge to admit
+Added: or deny certain allegations.
+Added: Among other defenses, the Company asserts that Mr.
+Added: Cullens has been paid for his time worked, that all compensation
+Added: considered earned, vested, and determinable has been paid, that Mr.
+Added: Nattrass is not an "employer" under the CWA, and that Mr.
+Added: Cullens may have failed to mitigate his damages.
+Added: Concurrently with the answer, the Company filed counterclaims against
+Added: Cullens asserting:
+Added: (i) breach of contract;
+Added: (ii) breach of the implied covenant of good faith and fair dealing;
+Added: and (iii) unjust enrichment,
+Added: pleaded in the alternative.
+Added: The counterclaims arise out of an Acquisition Agreement and Plan of Merger entered into on or about March
+Added: 13, 2022, among the Company, Emerald Merger Sub, Inc., Emerald Construction Management, Inc., Christopher Cullens, Charles Cullens, and
+Added: Green Stone Property LLC (the "Acquisition Agreement"), and an Amended and Restated Indemnification Claim Agreement entered
+Added: into on or about August 10, 2023, between the Company and Mr.
+Added: Cullens (the “Amended Indemnification Agreement”).
+Added: alleges that, under Article VIII of the Acquisition Agreement and the Amended Indemnification Agreement, Mr.
+Added: Cullens is obligated to indemnify
+Added: the Company for certain pre-closing losses and specified project-related losses, including losses related to a project in Olathe, Kansas,
+Added: and legal fees associated with at least six pending indemnification claims.
+Added: The Company alleges that Mr.
+Added: Cullens has failed to make the
+Added: required indemnification payments.
+Added: The Company seeks an award of its losses and damages, costs, pre- and post-judgment interest, and attorneys'
+Added: fees and costs.
+Added: This litigation is in its preliminary stages.
+Added: The Company believes
+Added: the claims asserted in Mr.
+Added: Cullens' complaint are without merit and intends to vigorously defend against them while pursuing its counterclaims.
+Added: The outcome of this matter is inherently uncertain, and the Company is unable to predict the ultimate outcome or estimate the amount or
+Added: range of loss, if any, that may result from this matter.
+Added: Other – Trade
+Added: Due to cash flow and working
+Added: capital issues, the Company has been delinquent in paying vendors, some of which have filed lawsuits seeking judgment for payment.
+Added: amounts due to these vendors are included in accounts payable in the consolidated balance sheet as of December 31, 2025.
+Added: MINE SAFETY DISCLOSURES
Not applicable.
Compared sentence by sentence after normalising whitespace, quotation marks, case and digits, so re-formatting and restated figures do not read as changed language. Wording changes appear as one removal and one addition. The current filing and the prior one are authoritative.