Item 1. Legal Proceedings
ITEM 1. LEGAL PROCEEDINGS
GEM Lawsuit
On
November 1, 2024, we filed a lawsuit against GYBL in the Court pursuant to which we asserted two causes of action: (i) rescission of the
GEM Warrants issued to GYBL under the GEM Agreement, by and among us, GEM, under Section 29(b) of the Exchange Act, due to GYBL’s
underlying violation of Section 15(a) of the Exchange Act for effecting the GEM Warrants as an unregistered dealer, and (ii) in the alternative,
a declaratory judgment that the exercise price adjustment calculation of the GEM Warrants is governed by the terms provided in the GEM
Warrants, rather than the terms of the GEM Agreement. Following a motion to dismiss filed by GYBL on January 17, 2025, the Court granted
such motion to dismiss on March 14, 2025. On April 15, 2025, we filed an appeal of the Court’s decision dismissing our case to the
United States Court of Appeals for the Second Circuit (the “Second Circuit”). The parties filed a stipulation to withdraw
the appeal pending in the Second Circuit on March 11, 2026.
Additionally,
following the Court’s grant of GYBL’s motion to dismiss our lawsuit, GYBL filed a separate lawsuit against us, in which GYBL
is asserting two causes of action against us: (1) breach of the terms of the GEM Warrants, and (2) declaratory relief concerning the validity
and enforceability of the GEM Warrants. In addition to the declaratory relief, GYBL is seeking monetary damages in an amount to be determined
at trial, specific performance of the GEM Warrants and attorneys’ fees and litigation costs. On June 9, 2025, we filed a motion
to dismiss this lawsuit from GYBL. GYBL responded to our motion to dismiss on June 23, 2025, asserting that our motion to dismiss should
be denied, or, in the alternative, GYBL should be given leave to further amend its complaint. On June 30, 2025, the Company filed a reply
in support of its motion to dismiss. On August 21, 2025, the Court granted, in part, our motion to dismiss the amended complaint with
respect to GYBL’s claim for declaratory relief concerning the validity and enforceability of the GEM Warrants. The Court denied
our motion to dismiss in all other respects. Following the Court’s partial grant and partial dismissal of our motion to dismiss,
we filed an answer to GYBL’s amended complaint on September 4, 2025.