LEGAL PROCEEDINGS
−Removed: Other than described below, management is not
−Removed: aware of any material legal proceedings that are pending or that have been threatened against us or our subsidiaries or any of our respective
−Removed: properties, and none of our directors, officers, affiliates or record or beneficial owners of more than 5% of our common shares, or any
−Removed: associate of any such director, officer, affiliate or shareholder, is (i) a party adverse to us or any of our subsidiaries in any legal
−Removed: proceeding or (ii) has an adverse interest to us or any of our subsidiaries in any legal proceeding.
+Added: Other than described below, management is not aware of any material
+Added: legal proceedings that are pending or that have been threatened against us or our subsidiaries or any of our respective properties, and
+Added: none of our directors, officers, affiliates or record or beneficial owners of more than 5% of our common shares, or any associate of any
+Added: such director, officer, affiliate or shareholder, is (i) a party adverse to us or any of our subsidiaries in any legal proceeding or (ii)
+Added: has an adverse interest to us or any of our subsidiaries in any legal proceeding.
The Company is subject to periodic inspection
2 unchanged sentences
course of business, minor violations may occur;
−Removed: however, these are not expected to result in material expenditures or have any other
−Removed: material adverse effect on the Company.
+Added: however, these are not expected to result in material expenditures or have any other material
+Added: adverse effect on the Company.
A prior owner of the Van 4 Mine had been granted
−Removed: a first Temporary Cessation from reclamation of the mine by the Colorado Mined Land Reclamation Board (“MLRB”) which was
−Removed: set to expire June 23, 2017.
+Added: a first Temporary Cessation from reclamation of the mine by the Colorado Mined Land Reclamation Board (“MLRB”) which was set
+Added: to expire June 23, 2017.
Prior to its expiration, PRM formally requested an extension through a second Temporary Cessation.
3 unchanged sentences
who pursue environmental and conservation objectives filed a brief objecting to the extension.
−Removed: The MLRB board members voted to grant
−Removed: a second five-year Temporary Cessation for the Van 4 Mine.
+Added: The MLRB board members voted to grant a
+Added: second five-year Temporary Cessation for the Van 4 Mine.
Thereafter, the three objecting parties filed a lawsuit on September 18, 2017.
15 unchanged sentences
On January 22, 2020,
−Removed: 2020, the MLRB held a hearing and on March 2, 2020, the MLRB issued an order vacating the Van 4 Temporary Cessation, revoking the permit
−Removed: and ordered commencement of final reclamation, which must be completed within five (5) years.
−Removed: The Company commenced reclamation of the
−Removed: Van 4 Mine but progress has been delayed both by COVID-19 restrictions and countywide fire and open flame restrictions.
−Removed: The reclamation
−Removed: cost is fully covered by the reclamation bonds posted upon acquisition of the property.
+Added: the MLRB held a hearing and on March 2, 2020, the MLRB issued an order vacating the Van 4 Temporary Cessation, revoking the permit and
+Added: ordered commencement of final reclamation, which must be completed within five (5) years.
+Added: The Company commenced reclamation of the Van
+Added: 4 Mine but progress has been delayed both by COVID-19 restrictions and countywide fire and open flame restrictions.
+Added: The reclamation cost
+Added: is fully covered by the reclamation bonds posted upon acquisition of the property.
On February 4, 2020, the Colorado DRMS
34 unchanged sentences
the MLRB seeking a partial appeal of the July 22, 2020 decision by requesting termination of the Topaz Mine permit.
−Removed: On December 15, 2020, the same coalition of environmental groups amended
−Removed: their complaint against the MLRB seeking a partial appeal of the October 21, 2020 decision requesting termination of the Topaz Mine permit.
+Added: On December 15, 2020, the same coalition
+Added: of environmental groups amended their complaint against the MLRB seeking a partial appeal of the October 21, 2020 decision requesting
+Added: termination of the Topaz Mine permit.
The Company has joined with the MLRB in defense of their July 22, 2020 and October 21, 2020 decisions.
−Removed: On May 5, 2021, the Plaintiff in
−Removed: the Topaz Appeal filed an opening brief with the Denver District Court seeking to overturn the July 22, 2020 and October 21, 2020 MLRB
−Removed: permit hearing decisions on the Topaz Mine permit.
−Removed: The MLRB and the Company were to respond with an answer brief within 35 days on or
−Removed: before June 9, 2021, but instead sought a settlement.
−Removed: The judicial review process was delayed as extensions were put in place until August
+Added: On May 5, 2021, the Plaintiff in the Topaz Appeal filed an opening brief with the Denver District Court seeking to overturn the July 22,
+Added: 2020 and October 21, 2020 MLRB permit hearing decisions on the Topaz Mine permit.
+Added: The MLRB and the Company were to respond with an answer
+Added: brief within 35 days on or before June 9, 2021, but instead sought a settlement.
+Added: The judicial review process was delayed as extensions
+Added: were put in place until August 20, 2021.
A settlement was not reached and the MLRB and the Company submitted answer briefs on August 20,
−Removed: The Plaintiff submitted
−Removed: a reply brief on September 10, 2021.
−Removed: On March 1, 2022, the Denver District Court reversed the MLRB’s orders regarding the Topaz
−Removed: Mine and remanded the case back to MLRB for further proceedings consistent with its order.
−Removed: The Company and the MRLB have until April 19,
−Removed: 2022 to appeal the Denver District Court’s ruling.
−Removed: The Company is also working toward the completion of an updated Topaz mine Plan
−Removed: of Operations which is a separate federal requirement of the BLM for the conduct of mining activities on federal land.
+Added: The Plaintiff submitted a reply brief on September 10, 2021.
+Added: On March 1, 2022, the Denver District Court reversed the MLRB’s
+Added: orders regarding the Topaz Mine and remanded the case back to MLRB for further proceedings consistent with its order.
+Added: The Company and
+Added: the MRLB had until April 19, 2022 to appeal the Denver District Court’s ruling.
+Added: Neither the Company nor the MLRB appealed the Denver
+Added: District Court ruling.
+Added: Subsequently on March 20, 2023, the MLRB issued a board order for the Company to commence final reclamation, which
+Added: upon completion will terminate mining operations at the Topaz Mine.
+Added: Reclamation is to commence immediately at the Topaz Mine and is to
+Added: be completed within five years by March 2028.
+Added: The Company is currently working toward the completion of an updated Topaz Mine Plan of
+Added: Operations which is a separate federal requirement of the BLM for the conduct of mining activities on the federal land at the Topaz Mine
+Added: and needed to re-permit the Topaz Mine with Colorado’s DRMS .
MINE SAFETY DISCLOSURES
5 unchanged sentences
cornerstone of safety at Western, ensuring that employees are provided a safe and healthy environment and are intended to reduce workplace
−Removed: accidents, incidents and losses, comply with all mining-related regulations and provide support for both regulators and the industry
−Removed: to improve mine safety.
+Added: accidents, incidents and losses, comply with all mining-related regulations and provide support for both regulators and the industry to
+Added: improve mine safety.
The operation of our U.S.
based mine is subject
−Removed: to regulation by the Federal Mine Safety and Health Administration (“MSHA”) under the Federal Mine Safety and Health Act
−Removed: of 1977 (the “Mine Act”).
+Added: to regulation by the Federal Mine Safety and Health Administration (“MSHA”) under the Federal Mine Safety and Health Act of
+Added: 1977 (the “Mine Act”).
MSHA inspects our mine on a regular basis and issues various citations and orders when it believes
7 unchanged sentences
Compared sentence by sentence after normalising whitespace, quotation marks, case and digits, so re-formatting and restated figures do not read as changed language. Wording changes appear as one removal and one addition. The current filing and the prior one are authoritative.