NextDecade Corporation, a Delaware corporation, is a Houston-based energy company primarily engaged in construction and development activities related to the liquefaction of natural gas and sale of LNG and the capture and storage of CO 2 emissions.
−Removed: We are constructing and developing a natural gas liquefaction and export facility located in the Rio Grande Valley in Brownsville, Texas (the “Rio Grande LNG Facility”), which currently has three liquefaction trains and related infrastructure under construction.
−Removed: The Rio Grande LNG Facility has received Federal Energy Regulatory Commission (“FERC”) approval and Department of Energy (“DOE”) FTA and non-FTA authorizations for the construction of five liquefaction trains and LNG exports totaling 27 million tonnes per annum (“MTPA”).
−Removed: Liquefaction trains 1 through 3 and related infrastructure are currently under construction and liquefaction trains 4 and 5 at the Rio Grande LNG Facility are currently in development.
−Removed: We are also developing a planned carbon capture and storage (“CCS”) project at the Rio Grande LNG Facility and other potential CCS projects that would be located at third-party industrial facilities through our NEXT Carbon Solutions business.
+Added: We are constructing and developing a natural gas liquefaction and export facility located in the Rio Grande Valley near Brownsville, Texas (the “Rio Grande LNG Facility”).
+Added: The Rio Grande LNG Facility has received Federal Energy Regulatory Commission (“FERC”) approval and Department of Energy (“DOE”) FTA and non-FTA authorizations for the construction of up to five liquefaction trains and LNG exports totaling up to 27 million tonnes per annum (“MTPA”).
+Added: Please see "Rio Grande LNG Facility Activity - Governmental Permits, Approvals and Authorizations" for more information regarding our FERC permit.
+Added: The Rio Grande LNG Facility has three liquefaction trains and related infrastructure ("Phase 1") under construction and liquefaction trains 4 and 5 are currently being commercialized.
+Added: We are also developing and beginning the permitting process for expansion trains 6 through 8 at the Rio Grande LNG Facility and developing a potential carbon capture and storage (“CCS”) project at the Rio Grande LNG Facility.
We were incorporated in Delaware on May 21, 2014, and were formed for the purpose of acquiring, through a merger, share exchange, asset acquisition, stock purchase, recapitalization, reorganization, or other similar business combination, one or more businesses or entities.
1 unchanged sentence
Prior to the merger with NextDecade LLC, we had no operations and our assets consisted of cash proceeds received in connection with our initial public offering.
+Added: We are focused on constructing and operating the Rio Grande LNG Facility safely, efficiently, on schedule, and on budget.
+Added: We seek to deliver secure, economically attractive, and sustainable energy solutions through the development and operation of liquefaction and CCS infrastructure.
Our common stock trades on the Nasdaq Capital Market (“Nasdaq”) under the symbol “NEXT.”
−Removed: Through our partially owned subsidiary, Rio Grande, we are constructing the Rio Grande LNG Facility on the north shore of the Brownsville Ship Channel.
+Added: Rio Grande LNG Facility Activity
+Added: Liquefaction Facilities Overview
+Added: Through our partially owned subsidiary, Rio Grande LNG, LLC ("Rio Grande"), we are constructing and developing the Rio Grande LNG Facility on the north shore of the Brownsville Ship Channel.
The site is located on 984 acres of land which has been leased long-term and includes 15 thousand feet of frontage on the Brownsville Ship Channel.
1 unchanged sentence
The Rio Grande LNG Facility has been approved by the FERC and authorized by the DOE to export up to 27 MTPA of LNG from up to five liquefaction trains.
−Removed: In July 2023, Rio Grande commenced construction on the first three liquefaction trains and related infrastructure (“Phase 1”) of the Rio Grande LNG Facility following a positive final investment decision (“FID”) and the closing of project financing by Rio Grande, which owns Phase 1 of the Rio Grande LNG Facility.
+Added: Please see "Rio Grande LNG Facility Activity - Governmental Permits, Approvals and Authorizations" for more information regarding our FERC permit.
+Added: Phase 1 at the Rio Grande LNG Facility is under construction, Trains 4 and 5 are currently being commercialized, and we are developing and beginning the permitting process for Trains 6 through 8.
+Added: In July 2023, Rio Grande commenced construction on Phase 1 of the Rio Grande LNG Facility following a positive final investment decision (“FID”) and the closing of project financing by Rio Grande, which owns Phase 1 of the Rio Grande LNG Facility.
Construction will be completed by Bechtel Energy Inc.
−Removed: (“Bechtel”) under fully wrapped, lump-sum turnkey engineering, procurement, and construction (“EPC”) contracts, and the facility will utilize APCI liquefaction technology, which is the predominant liquefaction technology utilized globally.
−Removed: Pursuant to a joint venture agreement with equity partners for ownership of Rio Grande, we expect to receive up to approximately 20.8% of distributions of available cash generated from Phase 1 operations;
−Removed: provided, that a majority of the cash distributions to which we are otherwise entitled will be paid for any distribution period only after our equity partners receive an agreed distribution threshold in respect of such distribution period and certain other deficit payments from prior distribution periods, if any, are made.
+Added: (“Bechtel”) under fully wrapped, lump-sum turnkey engineering, procurement, and construction (“EPC”) contracts, and the facility will utilize Air Products and Chemicals, Inc.
+Added: (“APCI”) liquefaction technology, which is the predominant liquefaction technology utilized globally.
+Added: Pursuant to a joint venture agreement with equity partners for ownership of Rio Grande, we expect to receive up to approximately 20.8% of distributions of available cash generated from Phase 1 operations, provided that a majority of the cash distributions to which we are otherwise entitled will be paid for any distribution period only after our equity partners receive an agreed distribution threshold in respect of such distribution period and certain other deficit payments from prior distribution periods, if any, are made.
+Added: Phase 1 LNG Sale and Purchase Agreements
Rio Grande has entered into long-term LNG Sale and Purchase Agreements (“SPAs”) with nine creditworthy counterparties for aggregate volumes of approximately 16.15 MTPA of LNG, which is over 90% of the expected Phase 1 nameplate LNG production capacity.
The SPAs have a weighted average term of 19.2 years.
−Removed: Under these SPAs, the customers will purchase LNG from Rio Grande for a price consisting of a fixed fee per MMBtu of LNG plus a variable fee per MMBtu of LNG, with the variable fees structured to cover the expected cost of natural gas plus fuel and other sourcing costs to produce LNG.
+Added: Under these SPAs, the
+Added: customers will purchase LNG from Rio Grande for a price consisting of a fixed fee per MMBtu of LNG plus a variable fee per MMBtu of LNG, with the variable fees structured to cover the expected cost of natural gas plus fuel and other sourcing costs to produce LNG.
In certain circumstances, customers may elect to cancel or suspend deliveries of LNG cargoes, in which case the customers would still be required to pay the fixed fee with respect to cargoes that are not delivered.
2 unchanged sentences
however, the commencement of the term of each SPA is tied to a specified train.
−Removed: Rio Grande’s portfolio of LNG SPAs for Phase 1 of the Rio Grande LNG Facility is as follows:
−Removed: TotalEnergies SE 5.4 20 FOB
−Removed: Shell NA LNG LLC
−Removed: ENN LNG Singapore Pte Ltd.
−Removed: China Gas Hongda Energy Trading Co., LTD
−Removed: Guangdong Energy Group
−Removed: Exxon Mobil LNG Asia Pacific
−Removed: Galp Trading S.A.
−Removed: Itochu Corporation
−Removed: 16.15 19.2 years
−Removed: weighted average
−Removed: (1) FOB - free on board;
−Removed: DES - delivered ex-ship
+Added: These SPAs help create a stable foundation of predictable, long-term cash flows to Rio Grande.
+Added: We believe our SPAs are attractive to our customers for several reasons, including long-term reliable supply, volumes to support growing demand for LNG and to replace customers' contracts with legacy LNG suppliers, diversification of supply portfolios in terms of geography, price indexation, delivery points, and/or tenor, flexibility of volumes with no destination restrictions, and the ability of our LNG to help our customers achieve their environmental, social and governance (“ESG”) goals.
Each of these SPAs is currently effective, and deliveries of LNG under these SPAs will commence on the respective Date of First Commercial Delivery (“DFCD”), which is primarily tied to the substantial completion or guaranteed substantial completion dates of specific trains as defined in each SPA.
2 unchanged sentences
Rio Grande expects to sell any commissioning LNG volumes and operational LNG volumes in excess of SPA volumes into the LNG market through spot, short-term, and medium-term agreements.
−Removed: Rio Grande has entered into certain time charter agreements and expects to enter into additional time charter agreements with vessel owners to provide shipping capacity for LNG sales related to its existing DES SPA, commissioning volumes, and expected portfolio volumes.
+Added: Rio Grande has entered into certain time charter agreements and expects to enter into additional time charter agreements with vessel owners to provide shipping capacity for LNG sales related to its existing delivered ex-ship SPA, commissioning volumes, and expected portfolio volumes.
Engineering, Procurement and Construction ( “ EPC ”)
−Removed: Rio Grande entered into fully wrapped, lump-sum turnkey contracts with Bechtel, a well-established and reputable LNG engineering and construction firm, for the engineering, procurement, and construction of Phase 1 at the Rio Grande LNG Facility, under which Bechtel has generally guaranteed cost, performance, and schedule.
−Removed: Under the Phase 1 EPC contracts, Bechtel is responsible for the engineering, procurement, construction, commissioning, and startup of three liquefaction trains and related infrastructure.
+Added: Rio Grande entered into fully wrapped, lump-sum turnkey contracts with Bechtel, a well-established and reputable LNG engineering and construction firm, for the engineering, procurement, and construction of Phase 1, and one of our wholly-owned subsidiaries entered into a corresponding contract in regards to Train 4 at the Rio Grande LNG Facility, under which Bechtel has generally guaranteed cost, performance, and schedule.
+Added: Under the Phase 1 and Train 4 EPC contracts, Bechtel is responsible for the engineering, procurement, construction, commissioning, and startup of liquefaction trains and their respective related infrastructure.
On July 12, 2023, Rio Grande issued final notice to proceed to Bechtel under the EPC contracts for Phase 1.
−Removed: Total expected capital costs for Phase 1 are estimated to be approximately $18.0 billion, including estimated owner’s costs, contingencies, and financing costs, and including amounts spent prior to FID under limited notices to proceed.
+Added: Total expected capital costs for Phase 1 are estimated to be approximately $18.0 billion, including EPC costs, estimated owner’s costs, contingencies, and financing costs, and including amounts spent prior to FID under limited notices to proceed.
Natural Gas Transportation and Supply
−Removed: Rio Grande has entered into a firm transportation agreement for capacity on the Rio Bravo Pipeline to transport natural gas feedstock to the Rio Grande LNG Facility.
−Removed: The Rio Bravo Pipeline is being developed and will be constructed and operated by a wholly owned subsidiary of Enbridge Inc.
−Removed: (“Enbridge”).
−Removed: The Rio Bravo Pipeline will provide Rio Grande access to purchase natural gas supplies in the Agua Dulce area and will connect to six regional intra and interstate pipelines, giving Rio Grande access to prolific gas production from the Permian Basin and Eagle Ford Shale and providing significant flexibility to obtain competitively priced natural gas feedstock.
−Removed: The Rio Bravo Pipeline is under development and is expected to be constructed and completed prior to the start of commissioning of Train 1 at the Rio Grande LNG Facility.
−Removed: Rio Grande has also entered into an agreement for capacity on an interruptible basis with Enbridge’s Valley Crossing Pipeline to provide redundant capacity for commissioning and operations.
−Removed: We have proposed and are in the process of executing a substantial and diversified natural gas feedstock sourcing strategy to spread risk exposure across multiple contracts, counterparties, and pricing hubs.
−Removed: We expect to enter into gas supply arrangements with a wide range of suppliers, and we also expect to leverage trading platforms and exchanges to
−Removed: lock in natural gas supply prices and/or hedge risk.
−Removed: Certain of our LNG offtake counterparties have the option to sell to Rio Grande some or all of the natural gas required to produce their respective contracted LNG volumes pursuant to structured options which define how much volume can be supplied and how much notice must be provided to switch to and from self-sourcing.
+Added: We are in the process of executing a substantial and diversified natural gas feedstock sourcing and transportation strategy to spread risk exposure across multiple contracts, counterparties, and pricing hubs.
+Added: We expect to enter into gas supply arrangements with a wide range of suppliers, and we also expect to leverage trading platforms and exchanges to lock in natural gas supply prices and/or hedge risk.
+Added: Rio Grande has executed agreements for transportation of natural gas to the Rio Grande LNG Facility on both a firm and interruptible basis to support commissioning and operations and provide the ability to purchase natural gas supplies at the Agua Dulce Hub, giving Rio Grande access to prolific gas production from the Permian Basin and Eagle Ford Shale and providing significant flexibility to obtain competitively priced natural gas feedstock.
+Added: We believe our proximity to major reserve basins and shale plays, increasing pipeline capacity in the area, a significant amount of natural gas production and infrastructure development, as well as our existing contracts and discussions with some of the largest regional operators, represent key elements of a comprehensive and effective feed gas strategy.
Final Investment Decision on Train 4 and Train 5 at the Rio Grande LNG Facility
−Removed: We expect to make a positive final investment decision and commencement of construction of Train 4 and related infrastructure, and subsequently Train 5 and related infrastructure, at the Rio Grande LNG Facility, subject to, among other things, finalizing and entering into EPC contracts, entering into appropriate commercial arrangements, and obtaining adequate financing to construct each train and related infrastructure.
−Removed: We have commenced certain pre-FID activities for Train 4, including the Front-end Engineering and Design ("FEED") and EPC contract processes with Bechtel.
−Removed: TotalEnergies SE ("TotalEnergies") has LNG purchase options of 1.5 MTPA for each of Train 4 and Train 5.
−Removed: If TotalEnergies exercises its LNG purchase options, we currently estimate that an additional approximately 3 MTPA of LNG must be contracted on a long-term basis for each of Train 4 and Train 5 prior to making a positive final investment decision for the respective train.
−Removed: We continue to advance commercial discussions with various potential counterparties and expect to finalize commercial arrangements for Train 4 in the coming months to support a positive final investment decision on Train 4.
−Removed: We expect to finance construction of Train 4 and associated infrastructure utilizing a combination of debt and equity funding.
+Added: We expect to make a positive final investment decision and commence construction of Trains 4 and 5 and related infrastructure at the Rio Grande LNG Facility, subject to, among other things, maintaining requisite governmental approvals, finalizing and entering into EPC contracts, entering into appropriate commercial arrangements, and obtaining adequate financing to construct each train and related infrastructure.
+Added: The Company has finalized an EPC contract with Bechtel for Train 4 and related infrastructure.
+Added: Pricing under the EPC Contract for Train 4 was valid through December 31, 2024, and a pricing refresh is in process and is expected to be completed in 2025.
+Added: The Company continues to advance commercial discussions with multiple potential counterparties and expects to finalize commercial arrangements for Train 4 in the coming months to support a positive FID on Train 4.
+Added: The Company entered into an LNG SPA with ADNOC for the sale of 1.9 MTPA of LNG from Train 4, as well as a non-binding Heads of Agreement (HoA) with Aramco for a 20-year SPA for the sale of 1.2 MTPA of LNG from Train 4.
+Added: The Company is working with Aramco to finalize a binding SPA.
+Added: Additionally, an affiliate of TotalEnergies SE ("TotalEnergies") has an LNG purchase option of 1.5 MTPA for Train 4, and the Company expects TotalEnergies to exercise the option.
+Added: The Company expects to finance construction of Train 4 and associated infrastructure utilizing a combination of debt and equity funding.
The Company expects to enter into bank facilities for the debt portion of the funding.
−Removed: In connection with consummating the Rio Grande Phase 1 equity joint venture, our equity partners each have options to invest in Train 4 and Train 5 equity, which, if exercised, would provide approximately 60% of the equity funding required for each of Train 4 and Train 5.
−Removed: Inclusive of these options, we currently expect to fund 40% of the equity commitments for each of Train 4 and Train 5, and to have an initial economic interest of 40% in each of Train 4 and Train 5, increasing to 60% after our equity partners achieve certain returns on their investments in the respective train.
−Removed: We expect to undertake the financing process for Train 4 after the EPC contract and commercial arrangements are finalized.
+Added: In connection with consummating the Rio Grande Phase 1 equity joint venture, the Company's equity partners each have options to invest in Train 4 equity, which, if exercised, would provide approximately 60% of the equity funding required for Train 4.
+Added: Inclusive of these options, NextDecade currently expects to fund 40% of the equity commitments for Train 4, and to have an initial economic interest of 40% in Train 4, increasing to 60% after its equity partners achieve certain returns on their investments in Train 4.
+Added: The Company expects to make a positive FID on Train 4 after commercial and financing arrangements are finalized.
+Added: The Company is also progressing the development and commercialization of Train 5.
+Added: TotalEnergies holds an LNG purchase option for 1.5 MTPA for Train 5, and the Rio Grande Phase 1 equity partners have options to invest in Train 5 equity which are identical to their options to participate in Train 4 equity.
+Added: Development of Additional Liquefaction Capacity
+Added: The Company is developing and beginning the permitting process for additional liquefaction capacity at the Rio Grande LNG Facility site beyond Trains 1 through 5.
+Added: Trains 6 through 8 are wholly owned by NextDecade and are cumulatively expected to increase the Company's total liquefaction capacity by approximately 18 MTPA once constructed and placed into operation.
+Added: Train 6 is being developed inside the existing levee at the Rio Grande LNG Facility site and adjacent to Trains 1 through 5.
+Added: The Company expects to pre-file an application with FERC for Train 6 in 2025 and a full application with FERC in early 2026.
+Added: Trains 7 and 8 are being developed on the site outside of the existing levee.
Governmental Permits, Approvals and Authorizations
19 unchanged sentences
The FERC, the PHMSA and the Coast Guard entered into a Memorandum of Understanding in 2004 that establishes the FERC’s primary role in evaluating LNG facility applications and defines the process for coordinating the review of an LNG import or export facility application with the PHMSA and the Coast Guard.
−Removed: In 2018, the FERC and the
−Removed: PHMSA entered into a separate Memorandum of Understanding that establishes the process and timeline by which the PHMSA should determine whether an LNG facility will meet the PHMSA’s LNG safety siting standards.
−Removed: We have obtained all major permits required to build the Rio Grande LNG Facility and export LNG, including FERC approval and DOE FTA and non-FTA authorizations for the construction of five liquefaction trains and LNG exports totaling 27 MTPA.
+Added: In 2018, the FERC and the PHMSA entered into a separate Memorandum of Understanding that establishes the process and timeline by which the PHMSA should determine whether an LNG facility will meet the PHMSA’s LNG safety siting standards.
+Added: We have obtained all major permits required to build the Rio Grande LNG Facility and export LNG, including FERC approval and DOE FTA and non-FTA authorizations for the construction of up to five liquefaction trains and LNG exports totaling up to 27 MTPA.
On November 22, 2019, we received the Order from FERC authorizing the siting, construction and operation of the Rio Grande LNG Facility.
13 unchanged sentences
On August 3, 2021, the D.C.
−Removed: Circuit denied all petitions, except for two technical issues dealing with environmental justice and GHG emissions, which were remanded to the FERC for further consideration.
−Removed: Circuit did so without vacatur , and accordingly, the Rio Grande LNG Facility's authorization from the FERC remains legally valid and enforceable.
−Removed: A second appeal was also filed with the same court by the same parties, seeking a review of the FERC letter order amending the Order to account for the design change from six to five trains but the petitioners moved to voluntarily dismiss this appeal on August 23, 2021.
+Added: Circuit denied all the arguments raised in the challenges, except for two technical issues dealing with environmental justice and GHG emissions, which were remanded to the FERC for further consideration.
+Added: Circuit did so without vacatur, and accordingly, the Rio Grande LNG Facility's authorization from the FERC remained legally valid and enforceable.
On April 21, 2023, FERC issued its order responding to the D.C.
2 unchanged sentences
On August 17, 2023, parties petitioned the D.C.
−Removed: Circuit for review of the Remand Order, which is still pending.
+Added: Circuit for review of the Remand Order.
On November 24, 2023, a motion was filed with FERC to stay construction of the Rio Grande LNG Facility, which FERC denied on January 24, 2024.
−Removed: On February 2, 2024, parties filed a motion of the D.C Circuit to stay construction of the Rio Grande LNG Facility, which is still pending with the D.C.
−Removed: Parties also filed a similar appeal in the Fifth Circuit in respect to the U.S.
−Removed: Army Corps of Engineers permit issued pursuant to Section 404 of the Clean Water Act.
−Removed: On January 5, 2023, the court fully denied the appeal rejecting each of the challengers’ arguments.
−Removed: On November 17, 2021, Rio Grande filed a Limited Amendment with the FERC, seeking authorization to incorporate carbon capture and storage systems, which would enable Rio Grande to voluntarily capture and permanently store at least 90% of the CO 2 expected to be generated at the Rio Grande LNG Facility.
−Removed: Once captured, the CO 2 is expected to be transported to an underground geologic formation permitted by the U.S.
−Removed: Environmental Protection Agency (“EPA”) and relevant Texas agencies via the existing underground injection control (“UIC”) Class VI permitting regime for geologic sequestration of CO 2 .
−Removed: On April 14, 2023, FERC issued a notice that it was suspending its environmental analysis of the Limited Amendment, citing the need for additional information regarding the carbon capture systems.
−Removed: The Limited Amendment is pending with FERC.
−Removed: On October 14, 2022, Rio Grande received from FERC a two-year extension of time, until November 22, 2028, to complete construction of the Rio Grande LNG Facility and place it into service.
−Removed: Rio Grande’s initial order had required that Rio Grande complete construction of the Rio Grande LNG Facility within seven years of the date of the Order, by November 22, 2026.
−Removed: Rio Grande sought an extension of this deadline, explaining to FERC that despite NextDecade’s efforts to develop the Rio Grande LNG Facility, the COVID-19 pandemic impacted NextDecade’s ability to secure sufficient offtake agreements to reach a positive investment decision and commence construction of the Rio Grande LNG Facility.
−Removed: FERC found that this demonstrated good cause to extend the commencement of construction deadline, and accordingly approved Rio Grande’s request.
+Added: On February 2, 2024, parties filed a motion of the D.C Circuit to stay construction of the Rio Grande LNG Facility.
+Added: On March 1, 2024, the motion to stay was denied by the D.C.
+Added: On August 6, 2024, the D.C.
+Added: Circuit issued a decision vacating FERC's reauthorization of the Rio Grande LNG Facility and remanding the case to FERC again on the grounds that FERC should have issued a supplemental EIS related to environmental justice issues during its remand process, as well as with regard to FERC's consideration of the CCS proposal we had filed in November 2021.
+Added: We withdrew our FERC application for the CCS facilities on August 30, 2024.
+Added: On September 13, 2024, FERC issued notice of its intent to prepare a supplemental EIS in response to the D.C.
+Added: Circuit's decision vacating the Remand Order.
+Added: The notice set forth a schedule providing for issuance of a draft of the supplemental EIS in March 2025, the final supplemental EIS by the end of July 2025, and issuance of a final order by November 20, 2025.
+Added: FERC has continued to act on our implementation filings and to authorize construction activities.
+Added: On October 21, 2024, the Company filed a petition for rehearing and rehearing en banc with the D.C.
+Added: On December 9, 2024, petitioners in the case and FERC filed responses to the Company's request for rehearing, and the Court's decision is pending.
+Added: Circuit's decision will not be effective until the Court has issued its mandate, which is not expected to occur until the appeals process has been completed.
+Added: The Company expects to take all available legal and regulatory actions, including but not limited to appellate actions and other strategies, to ensure that construction on Phase 1 will continue and that necessary regulatory approvals are maintained to enable the FID of Trains 4 and 5 at the Rio Grande LNG Facility.
NEXT Carbon Solutions
−Removed: Carbon capture and storage (“CCS”) is the process of (i) capturing CO 2 at an emissions source, (ii) compressing the CO 2 for transportation and (iii) safely injecting the compressed CO 2 into deep rock formations at a suitable site, where it is permanently stored and subsequently monitored according to EPA standards and requirements.
−Removed: The Paris Agreement is a multilateral, binding agreement that brings nations together in a common cause to combat climate change and adapt to its effects.
−Removed: We believe that deploying CCS equipment and technology is key to achieving global reductions in greenhouse gas emissions (which includes CO 2 among other gases), a goal of the Paris Agreement.
−Removed: NEXT Carbon Solutions is developing a proposed end-to-end CCS solutions for power plants and other industrial facilities that emit CO 2 as a byproduct of various processes within their operations.
−Removed: Without a CCS solution, the emitted CO 2 would otherwise be released to the atmosphere.
−Removed: Leveraging our team’s engineering and project management experience, we have developed proprietary processes focused on post-combustion carbon capture that are expected to lower the capital and operating costs of deploying CCS at industrial facilities, thereby making such potential projects more economically viable.
−Removed: We have proposed a CCS project at the Rio Grande LNG Facility, and we expect to partner with third parties to invest in the deployment of CCS technologies to capture and permanently store CO 2 emissions at their facilities.
−Removed: Service Offerings and Potential Market
−Removed: NEXT Carbon Solutions’ proprietary CCS processes will use an amine absorption system, one of the most common methods used for such purposes.
−Removed: Derived from extensive engineering efforts, our proprietary CCS processes are designed to generate the following expected benefits as compared to existing alternatives:
−Removed: • Enable CO 2 capture up to an expected 95% of emissions generated from a source facility;
−Removed: • Competitive cost (both capital and operating expenditures) of post-combustion CCS;
−Removed: • Use proven technology and equipment to capture CO 2 emissions at scale;
−Removed: • Minimize energy requirements;
−Removed: • Substantially reduce or, in some cases, eliminate consumption of fresh-water;
−Removed: • Reduce the land footprint required by the CCS facility.
−Removed: Our proprietary CCS processes do not include new equipment or technology.
−Removed: We have designed novel proposed applications of existing industrial-scale equipment to reduce the expected capital and operating expenditures associated with the CCS process applied at scale.
−Removed: These novel proposed designs and processes are covered by a portfolio of awarded and pending patents and are the intellectual property of the Company.
−Removed: NEXT Carbon Solutions proposed project designs are focused on the treatment and cooling stages of CO 2 -rich flue gas and therefore agnostic to amine type, allowing us to work with multiple third party providers to optimize the proposed projects and maintain their anticipated benefits.
−Removed: Our proposed end-to-end CCS offering includes the design, development, construction and operation of the capture, transportation, and storage components of a carbon capture and storage project.
−Removed: NEXT Carbon Solutions' marketing efforts for proposed projects are primarily focused on existing industrial facilities with emissions greater than one million tonnes of CO 2 per annum and located proximally with saline aquifers with adequate storage capacity.
−Removed: There are more than 600 facilities in the United States that produce more than one million tonnes of CO 2 per annum, representing a very robust addressable market.
−Removed: We believe the optimal transportation and storage component of our projects is a point-to-point design, whereby CO 2 captured from a source facility is permanently stored in a proximate and dedicated saline aquifer storage site.
−Removed: CO 2 storage hubs also represent a viable CO 2 storage alternative.
−Removed: Our analysis indicates that source emitters of greater than one million tonnes per annum are sufficient in size to support a point-to-point sequestration project and could serve as an anchor customer for the eventual development of a storage hub.
−Removed: Potential Sources of Value
−Removed: Integrated deployment of CCS processes at a source facility has the potential to generate value from a variety of sources including:
−Removed: government incentives, such as the Internal Revenue Code Section 45Q tax credit, build out and marketing of a portfolio of low cost, independently verified carbon credits, premiums resulting from more environmentally friendly products, such as products with a lower carbon footprint or intensity, and, in certain potential commercial arrangements, increased market share earned by the source facility following CCS deployment.
−Removed: We can offer prospective customers a variety of proposed commercial structures, which are aimed at providing sufficient flexibility to balance customers’ ESG and financial goals, commercial appetite, risk profiles, investing strategies, and capital availability.
−Removed: We also believe that some of our prospective customers may have significant financial upside due to improved competitive position resulting from a full integration of the source facility with CCS processes, and we will
−Removed: seek to share in this value creation when applicable.
−Removed: Further, we believe that current market conditions, incentives provided in the United States and prospective regulation in foreign countries, represent a unique opportunity for NEXT Carbon Solutions to develop a portfolio of CCS projects that would eventually generate meaningful financial returns to our shareholders.
−Removed: NEXT Carbon Solutions expects to negotiate commercial terms with prospective customers on a case-by-case basis depending on the unique characteristics of the relevant source facility.
+Added: NEXT Carbon Solutions (“NCS”) is developing a potential end-to-end carbon capture and storage (“CCS”) project at the Rio Grande LNG Facility, focused on post-combustion carbon capture.
+Added: The potential CCS project at the Rio Grande LNG Facility is in early development, and the Company is exploring subsurface and technology options for the project as well as potential avenues for commercialization.
+Added: The Company expects that development of the CCS project at the Rio Grande LNG Facility may lead to CCS project opportunities at third-party industrial facilities in the future.
+Added: Corporate and Other Activities
+Added: We are required to maintain corporate and general and administrative functions to serve our business activities described above, including construction of Phase 1 at the Rio Grande LNG Facility, the development of Train 4, Train 5, and additional liquefaction expansion capacity, and the development of a potential CCS project at the Rio Grande LNG Facility.
We are subject to a high degree of competition in all aspects of our business.
−Removed: See “Item 1.A — Risk Factors — Competition in the energy industry is intense, and some of our competitors have greater financial, technological and other resources.
−Removed: The Rio Grande LNG Facility will compete with liquefaction facilities worldwide to supply economically advantaged LNG to the global market.
+Added: See “Item 1.A — Risk Factors — Competition in the industries in which we operate is intense, and some of our competitors have greater financial, technological and other resources.
+Added: The Rio Grande LNG Facility will compete with liquefaction facilities worldwide to supply LNG to the global market.
In this market, we will compete with a variety of companies, such as independent, technology-driven companies, state-owned companies, and other independent oil and natural gas companies and utilities.
2 unchanged sentences
Our competitors in the CCS space may have longer operating histories, more development experience, greater name recognition, greater access to the CCS market, more employees and substantially greater financial, technical and marketing resources than we currently possess.
−Removed: As of December 31, 2023, we had 147 full-time employees and 13 independent contractors.
−Removed: We utilize independent contractors on an as-needed basis and have no collective bargaining agreements with our employees.
+Added: As of December 31, 2024, we had 237 full-time employees.
+Added: We have no collective bargaining agreements with our employees.
Our principal executive offices are located at 1000 Louisiana St., Suite 3300, Houston, Texas, 77002, and our telephone number is (713) 574-1880.
9 unchanged sentences